Draft: 
No
Revision of previous policy?: 
No
Draft Year: 
2000
Effective Start Year: 
2000
Scope: 
National
Document Type: 
Rule/Regulation, Other
Economic Sector: 
Power
Energy Types: 
Power, Renewable
Issued by: 
Department of Energy
Overall Summary: 
A Department Circular providing revised rules and procedures to implement electrification program funded through Energy Regulations No. 1-94.
Access
Energy access action plan: 
Valutation and Approval of Energy Projects: (a) Priority shall be given to unenergized areas of the following: (i) Official Resettlement Areas; (ii) Host Barangays; and (iii) Host Municipalities/Host Cities. ---After electrification has reached the municipal or city level, the electrification fund of each energy generating facility in the same province or region, [...] shall be combined to finance unenergized areas in the host province or host region [...].---The National Electrification Administration (NEA) shall provide support to the Department in the identification of electrification projects [...]. ---All electrification projects shall be completed or energized consistent on the time or date specified in the MOA.
Renewable Energy
RE priorities: 
(g) All electrification projects shall be undertaken in a least-cost manner. The concerned franchised distribution utility or project implementor may either adopt the conventional line design or utilize indigenous and renewable energy sources to energize the area; [....]
Investment
Public Private Partnerships: 
A Memorandum of Agreement (MOA) shall be forged among the Department, relevant franchised distribution utility or project implementor, power producer and/or energy resource developer, NEA and the concerned LGU/s to effect the implementation of the project/s.
Governance
Energy institutional structures: 
The National Electrification Administration (NEA) shall provide support to the Department in the identification of electrification projects [...].