Meta Data
Draft: 
No
Revision of previous policy?: 
No
Draft Year: 
2006
Effective Start Year: 
2006
Scope: 
National
Document Type: 
Plan/Strategy, Other
Economic Sector: 
Power
Energy Types: 
Power
Issued by: 
The Prime Minister of Government
Overall Summary: 
A Decision to approve the roadmap and conditions for formation and development of different levels of the electricity market in Vietnam.
Access
Energy access priorities: 
To ensure the stable and reliable supply of electricity with higher and higher quality.
Investment
Energy sector investment priorities: 
To attract investment from all economic sectors inside and outside the country into electricity-related activities, gradually reduce the state investment in the power industry.
Independent power producers: 
Vietnam's electricity market shall be formed and developed through three levels: [...] Step 1 Level 1:Independent power producers (IPP) not owned by the EVN shall continue selling electricity to the EVN under concluded long-term power purchase agreements (PPA). - At the end of the experimental step, major power plants of the EVN, which play an important role in the power system, must be transformed into IPPs in form of independent state companies; the other power plants must be transformed into IPPs in form of joint-stock companies in preparation for a complete competitive electricity production market.[...] -Step 2 Level 1: To permit IPPs not owned by the EVN to participate in price offering in order to start the complete competitive electricity production market (after the sole-purchaser model); electricity producers shall sell electricity on the market through PPAs or competitive price offers on the spot market, provided that the amount of electricity sold in either of these two forms is regulated by the Electricity Regulation Department.
Electricity wholesale markets: 
Vietnam's electricity market shall be formed and developed through three levels: - Level 1 (2005-2014): The competitive electricity production market. - Level 2 (2015-2022): The competitive electricity wholesale market. - Level 3 (after 2022): The competitive electricity retail market.---Step 1 Level 2: To permit the selection of a number of major distributors and customers for establishment of the experimental competitive electricity wholesale market. To permit the establishment of a number of wholesalers in order to enhance the competitiveness in electricity wholesale. Current electricity-transmitting companies may be consolidated into a sole national electricity-transmitting company under the EVN; distributors, system operators and transaction administrators in the electricity market shall continue to be managed by the EVN.---Step 2 - level 2: The complete competitive electricity wholesale market (from 2017 to 2022).
Investment climate development: 
To attract investment from all economic sectors inside and outside the country into electricity-related activities, gradually reduce the state investment in the power industry.
Governance
Energy management principles: 
To step by step develop a competitive electricity market in a stable manner, eliminate subsidy for the power industry, increase the electricity consumers' right to select electricity suppliers.---To ensure sustainable development of the power industry.