Overall Summary: 
These Regulations provide for Procedure, Terms and Conditions for grant of Transmission Licence. In particular, they deal with the selection of project and implementing agency; grant of licence; transmission charges; terms and conditions of licence; and miscellaneous.
Investment
Bidding and Tendering: 
The Empowered Committee shall identify the projects included in the transmission plan to be developed under the guidelines for competitive bidding.---No person shall be eligible for grant of licence unless it is– (a) selected through the process under the guidelines for competitive bidding, [...].
Governance
Energy management principles: 
No person shall be eligible for grant of licence unless it is– (a) selected through the process under the guidelines for competitive bidding, or (b) a state owned or controlled company identified as a project developer on or before 5.1.2011, or (c) a generating company which has established the dedicated transmission line, and intends to use such dedicated transmission line as the main transmission line and part of the inter-State transmission system.