Sri Lanka Sustainable Energy Authority
Sri Lanka Sustainable Energy Authority | |
Code of practice for energy efficient buildings in Sri Lanka
is published
On this date of 30th June 2009 Under Clause 36 (g) of Sri Lanka Sustainable Energy Authority Act
Director General
Sri Lanka Sustainable Energy Authority 3G- 17, BMICH
Colombo 07
Telephone: 011-2677445
Printed by Design Systems (Pvt) Ltd. , Colombo 10 Cover and Design by Wasantha Siriwardena LayoutDesign by Ranga S. Udugama
he first Energy Efficiency Building Code (EEBC) of Sri Lanka was developed by the Ceylon Electricity
Board in 2000. This EEBC (2000) was the major precursor which prompted the Sri Lanka Sustainable Energy Authority todevelop a new code for energy efficient buildings by reviewing and amending
the extant EEBC, making allowance for advancing technologies and modern society requirements.
Our utmost gratitude goes to Mr. M.M.C.
Ferdinando Secretary to the Ministry of Power and Energy, Mr. Ananda S. Gunasekara, founder Chairman of theSLSEA and Dr. Krishan Deheragoda, Chairman of the SL SEA for their continuous support, guidance and
encouragement we received throughout.
The CODE OF PRACTICE FOR ENERGY EFFICIENT BUILDINGS IN SRI LANKA is
a result of exceptional team work conducted by leading consultants in Sri Lanka. Hereby, we express our gratitude to:
The subcommittee on implementation mechanism
M.S. Jayalath (Consultant) Wijitha Perera (Consultant)
Prasanna Wijetunga (Deputy Director, Urban Development Authority)
Mrs. Priyantha Ranawaka (Senior Engineer, Colombo Municipal Council)
The Subcommittee on lighting Tissa Gunasena (Consultant) Buddika Samarasekara (Electrical Engineer,Ceylon Electricity Board)
Sharmila Ragunathan (Head-Projects, Hayleys)
The subcommittee on ventilation and air conditioning
Wijitha Perera (Consultant) Wimal Jayakody (Consultant) Franklin Silva (Consultant)
The subcommittee on building envelope
Rahula Attalage (Professor, University of Moratuwa)
Thishan Jayasinghe (Professor, University of Moratuwa)
Narein Perera (Senior Lecturer, University of Moratuwa)
The subcommittee on electrical power and distribution
Ranil Senaratna (Director, Fentons) Rienzie Fernando (Consultant)
The subcommittee on pumps, motors and service water heating
Dr. A.G.T. Sugathapala (Senior Lecturer, University of Moratuwa)
D.D. Ananda Namal (Deputy General Manager, services, NERD Centre)
The project was managed by the Department of Energy Management of the SLSEA. We extend our gratitude to;
Harsha Wickramasinghe (Deputy Director General-Operations, SLSEA)
Upali Daranagama (Deputy-Director General-Strategy, SLSEA)
M.M.R. Pathmasiri (Director Energy Management, SLSEA)
Chamila Jayasekara (Head-Energy Efficient Systems, SLSEA)
Ms. Asanka Rahubadda (Engineer, Energy Efficiency, SLSEA)
Our heartfelt thanks go to the following institutions for their support in making this endeavour a success.
The Urban Development Authority The Colombo Municipal Council The University of Moratuwa
5. Electric Power and Distribution..................................................................... 22
5.1 General Principles of Energy Efficient Electrical Power Distribution.................... 22
5.2 Mandatory requirements............................................................................ 22
5.2.1 Electrical Distribution System....................................................................... 22
5.2.2 Transformers.............................................................................................. 23
5.2.3 Electric Motors............................................................................................ 23
5.3 Prescriptive Requirements......................................................................... 24
5.4 Design Considerations............................................................................... 24
5.5 Submission Procedure............................................................................... 25
5.6 Annexes..................................................................................................... 25
6. Service Water Heating................................................................................ 25
6.1 General Principles...................................................................................... 25
6.2 Sizing of Systems....................................................................................... 26
6.3 Mandatory requirements............................................................................ 26
6.3.1 Water Heating Equipment Efficiency............................................................ 26
6.3.2 Service Water Heating Piping Insulation........................................................ 26
6.3.3 Service Water Heating System Controls........................................................... 27
6.4 Prescriptive Requirements......................................................................... 27
6.4.1 Temperature Limits.................................................................................... 27
6.4.2 Heat Traps.................................................................................................. 27
6.5 Design Considerations............................................................................... 27
6.5.1 Supplementary Service Water Heating Systems............................................... 27
6.6 Submission Procedure............................................................................... 27
6.7 Annexes..................................................................................................... 27
Annex 1: Definitions, Abbreviations & Acronyms........................................................ 28
Annex 2: Lighting.................................................................................................... 34
Annex 3: Ventilation & Air Conditioning..................................................................... 43
Annex 4: Building Envelop...................................................................................... 46
Annex 5: Electrical Power and Distribution................................................................... 49
Annex 6: Service Water Heating............................................................................ 49
List of Tables
Table 2.1: Lighting Power Density............................................................................... 5
Table 2.2: Maximum Allowed Lighting Power for Building Exteriors..................................... 6
Table 2.3 Maximum Allowed Lighting Power for Roads/Grounds......................................... 6
Table 2.4: Minimum Lamp Efficacy Linear Fluorescent Lamps (0.6 to 1.2 meters)..................... 7
Table 2.5: Minimum Lamp Efficacy Integral-Type Compact Fluorescent Lamps........................ 7
Table 2.6: Minimum Lamp Efficacy Modular-Type Compact Fluorescent Lamps....................... 7
Table 2.7: Maximum Allowed Ballast Losses for Linear Fluorescent Lamps............................. 8
Table 2.8: Incandescent Lamp-Minimum Lamp Efficacy....................................................... 8
Table 2.9: HID Lamp – Minimum Lamp Efficacy & Maximum Allowed Ballast Losses................. 9
Table 3.3: A/C Equipment Standard Rating Conditions (°C)................................................... 14
Table 3.4: A/C Equipment Minimum Performance Standards................................................. 16
Table 4.3.1a: Maximum U-values for facades............................................................... 20
Table 4.3.2a: Maximum U-Factor values for Roofs.............................................................. 21
Table 5.1: Minimum Efficiencies for Three-Phase Induction Motors........................................ 23
Table 5.2: 11kV Transformer, 3 phase, oil immersed............................................................ 24
Table 5.3: 33kV Transformer, 3 phase, oil immersed............................................................ 25
Table 6.1: Minimum Energy Efficiency of Water Heating Equipment........................................ 26
Table 2.1.1A: Position Index Data............................................................................... 36
Table 2.10: Standard Maintained Illuminance.............................................................. 38
Table 2.11: Design Maintained Illuminance.................................................................. 39
Table 2.12: Installed Power Density (Courtesy: CIBSE Code of Interior Lighting – 1994)............. 40
Table 2.13: Power Credits for Certain Types of Lighting Controls............................................ 41
Table 2.14: Power Credits for Automatic Daylighting Controls............................................. 42
Table 3.1: Piping Insulation........................................................................................ 43
Table 3.2: Minimum Duct Seal Level........................................................................... 44
Table 4.1: Solar Correction Factors (CF) (dimensionless)...................................................... 46
Table 4.2: Shading Coefficient (SC) for Horizontal Overhang Projections................................. 47
Table 4.3: Shading Coefficient (SC) for Vertical Side-Fin Projections....................................... 47
Table 4.4: Shading Coefficient (SC) for Horizontal & Vertical “Egg-Crate” Projections.................. 48
Table 6.1: Minimum Pipe Insulation Thicknesses for Service Hot Water Systems....................... 49
The CODE OF PRACTICE FOR ENERGY EFFICIENT BUILDINGS IN SRI LANKA was compiled by the Sri Lanka Sustainable Energy Authority (SLSEA) upon reviewing and amending the Energy Efficient Building Code[CEB - 2000].
1.1 Purpose
To introduce energy efficient design and/ or retrofits to commercial buildings, industrial facilities and large scale housing schemesto enable designing, construction and maintenance to be carried out under minimal energy consumption without compromising the building’s function, and/or the comfort and health of occupants.
To set criteria and minimum standards for energy efficiency in design and/or retrofits in commercial buildings and to provide criteriafor determining compliance.
To encourage energy efficiency designs exceeding minimum standards.
1.2 Exemptions
The code however does not cover energy consumption processes of equipment that are in the buildings other than in the form ofbuilding elements.
1.3 Compliance
Requirements
This CODE OF PRACTICE FOR ENERGY EFFICIENT BUILDINGS IN SRI LANKA sets forth the requirements for design and/or retrofit of commercial buildings and industrial installations.
This code of practice covers the following building elements:
a) Building envelop
b) Ventilation & Air conditioning
c) Lighting
d) Electrical power and distribution
e) Service Water Heating
All commercial buildings, industrial facilities and large scale housing developments having one or more of the followingfeatures,
a) Four or more stories
b) Floor area of 500 m2 or more
c) Electrical power demand of 100 kVA or more
d) Air-conditioning cooling capacity of 350 kW (output) or more are subject to the regulations of
this code.
This code covers only the energy performance aspects of a given building. The code in no way relates to the health andsafety aspects of personnel during the construction phase of the building, but importantly, does not supersede any other existing statutory criteria and/or codes pertaining to the above aspects.This code may be used as an additional set of regulationssupplementing the already existing regulations and requirements.
1.4 Implementation
This programme would be implemented through Urban Development Authority (UDA), Provincial Councils and Local Authorities. All new buildings with one or more features stated in 1.3.3 are expected to conform to the building code regulations. The SLSEA will provide the necessary assistance to the Local Authorities to evaluate sections regarding energy efficiencyaspects in the CODE in all building applications as necessary. Programmes to develop an effective implementation mechanismwill include the selection of implementation mechanism and consultations of the local government bodies to understand the existing building approval process and incorporate practices given in this CODE to the existing structures.
1.4.1 Implementing agencies
- SLSEA –The responsible Agency for the implementation of CODE
- UDA, Provincial Councils and Local Authorities (Municipal Councils, Urban Councils and Pradeshiya Sabha) -implementing partners of the CODE
1.4.2 Implementation
mechanism
The code in the present form is basically to be used for Commercial Buildings. Industrial buildings, Hotels and large apartmentcomplexes are to be brought in subsequently. The method of implementation therefore is expected to cover all above areas.
- The UDA, Colombo Municipal Council and other Municipal Councils in the country together with all other Local GovernmentEstablishments will be the major partners responsible for implementing these regulations from the planning stage. Theseorganisations will here in after be referred to as Implementing Authorities.
- The Implementing Authorities will introduce an additional compliance requirement (similar to the fire code compliance) as an integral part of the building plan approval procedure.
- The relevant section of the building permit application, with the relevant drawings and the submittals will be forwarded to aspecial Code compliance certifying body specifically set up for the purpose.
- The Code compliance certifying body will be established by the SLSEA. This body will comprise of two committees asappointed by the SLSEA. The Monitoring and Approval committee will be empowered to recommend approval of the building application. This committee will be assisted by the Technical Evaluation Committee, which, after carefully studying the submittals, will submit their recommendations to the Monitoring and Approval committee.
- The Monitoring and Approval committee will consist of senior specialists in the relevant fields covering the entire Code. They will be selected and appointed by theSLSEA.
- The Technical Evaluation Committee will consist of technically qualified persons having adequate experience in the areas ofspecialty coming under the Code and who have been trained in the implementation procedure for the Code. This committee will process the submittals and make their recommendations to the Monitoring and Approval Committee.
- The SLSEA will obtain the services of existing professional associations and bodies to obtain their services as partners or obtain their assistance in selecting suitable persons for the Technical Evaluation Committee.
- The Monitoring and Approval Committee will make the final recommendation to the Responsible Agency (SLSEA). TheSLSEA will issue a letter of compliance to the relevant agency for eligible projects, considering the recommendations of theMonitoring and Approval committee. It will be the Code compliance approval for the project.
- The inspection of the building on completion will be carried out either by the Technical Evaluation committee or any otherorganisation or committee appointed by the SLSEA. Certificate of Conformity will be issued for the projects, which shall besuccessful at this stage of evaluation. Certificate of Conformity will be the final document expressing the compliance of the certified building to the Code. The compliance certificate will be issued for a specific period of time (3 – 5 years). The certificate needs to be revalidated subsequent to an inspection thereafter.
- The buildings complying with the Code will be given a ‘Star Rating’ depending on the level of compliance. A marking schemeneeds to be worked out for this purpose.
2. Lighting
2.1 General Principles of Energy Efficient Lighting Practice
Lighting is, perhaps, the single largest consumer of energy (kilowatt hours) in a building (other than when air-conditioning is used). It also contributes largely towards increasing of cooling loads in buildings in tropical climates, as lighting generates heat,which in turn results in higher consumption of energy for air conditioning requirements.
There are a number of technologies available today, that can significantly reduce this component but it has to be done with utmost care as it needs to be accepted by the Occupants who actually experience the lighting installation. Further, latest research hasrevealed that qualitative aspects of lighting can bring about increase in productivity and therefore, it is a matter of arriving at solutions, without compromising the qualitative aspects, to reduce energy. This also calls for creativity on the part of lightingdesigners, for instance, to maximise the use of daylight and apply dynamic lighting solutions and colours in a sensible way, withoutcompromising safety aspects.
This CODE will set the maximum allowable loads for building lighting systems as well as lower limits for the acceptable efficienciesfor commonly used lighting components (lamps and ballasts). The Lighting Designer therefore is to face the challenge of using this CODE as a minimum energy performance standard to develop lighting systems that balance appealing and effective visual environments with minimal energy usage.
2.1.1 Objective
The objective of this section of the CODE is to use minimal electrical energy to provide lighting to the quantity and quality ofstandards. It is however necessary to evaluate the equipment, techniques and services available for both existing and proposed installations in order to meet these requirements.
Following are six basic rules for achieving energy efficiency in lighting.
- Use the most efficient but suitable light source
- Ensure efficient usage of lamp light output
- Ensure proper maintenance of lighting equipment
- Use well-designed energy efficient lighting schemes
- Establish controlled switching operations and maximise use of daylight
- Consider appropriate interior décor: use light-colours whenever possible.
2.1.2 Spaces covered
a) Interior spaces of buildings
b) Exterior areas including facades, entrances, exit ways, loading docks etc.
c) Roads, grounds and other areas including open air/ enclosed areas where lighting is installed and powered by the buildingelectrical system.
2.1.3 Exemptions
a) Commercial greenhouses
b) Lighting power for theatrical productions, television broadcasting, portions of entertainment facilities such as dancing floorsin hotel ballrooms, night-clubs, discos and casinos where lighting is an essential technical element of the function performed.
c) Theatre facilities in medical and dental applications
d) Outdoor sports facilities
e) Exterior lighting of public monuments
f) ) Special applications such as research laboratories, museums etc.
g) Emergency lighting that is automatically OFF during normal operation
h) High-risk security areas identified by local ordinances or regulation or by security or safety personnel
2.2 Mandatory Requirements
2.2.1 Lighting Controls
The two main factors involved in the energy efficient lighting systems are the lamp wattage and the duration of its operation. Both these factors are equally important and could be made to contribute to energy efficiency through ‘Lighting Controls’.
2.2.1.1 Area Controls
The simplest way to improve lighting efficiency is to turn off lights when they are not in use. All lighting systems must haveswitching or control capabilities to allow lights to be turned off when they are not required.
a) All spaces enclosed by walls or ceiling height partitions shall be provided with one manually operated on/off lighting control(switch) for each space. Each space must have its own switching; gang switching of several spaces is not permitted.
b) All manually operated switching devices must be located in such a way that it is visible to the operational personnelhandling the switch(es). In public areas such as lobbies, concourses, etc., the switches may be located in areas accessible only to authorised persons.
Exemptions
Continuously illuminated areas within a building, for reasons of security or emergency egress, are exempted from the switchingrequirements as long as the maximum lighting power density used for this purpose does not exceed 5 watts per square meter.
2.2.1.2 Automatic lighting controls
= Photo electric sensor and timer controls with manual override option
All the lighting in external areas of the buildings including road ways, car parks… etc shall be equipped with either photo electric sensor or timer control based on the application. This may be applicable to all the areas where lighting needs arepredictable and predetermined.
= Occupancy based controls
Occupancy-based strategies are best suited to spaces that have highly variable and unpredictable occupancy patterns.Occupancy or motion sensors are used to detect occupant motion, lighting the space only when it is occupied.
= Daylight control
Use of day lighting shall maintain in all buildings.This may be achieved either manually through separate dedicated switchingprovided for day-lit areas or by using automatic controls.
Further, Designers shall be encouraged to maintain a minimum average daylight factor of 2 – 5 % in which case it can be supplemented with electric lighting. For definitions and calculations of average daylight factor and limiting depth criteria,please refer to the annex 2.
2.2.2 Maximum Allowable Power for Illumination Systems
The lighting power density (LPD) for building lighting systems shall not exceed the values given in Table 2.1. LPD is calculated by dividing the total connected load for all lighting systems in the building by the gross lighted floor area of the building. For building types not listed in Table 2.9 selection of a reasonable equivalent is permitted.
Table 2.1 Lighting Power Density
Building Area Type | LPD (W/m2) | Building Area Type | LPD (W/m2) |
Automotive Facility | 9.7 | Multifamily | 7.5 |
Convention Centre | 12.9 | Museum | 11.8 |
Dining: Bar Lounge/Leisure | 14.0 | Office | 10.8 |
Dining: Cafeteria/Fast Food | 15.1 | Parking Garage | 3.2 |
Dining: Family | 17.2 | Performing Arts Theatre | 17.2 |
Dormitory/Hostel | 10.8 | Police/Fire Station | 10.8 |
Gymnasium | 11.8 | Post Office/Town Hall | 11.8 |
Healthcare-Clinic | 10.8 | Places of worship | 14.0 |
Hospital/Health Care | 12.9 | Retail /Mall | 16.1 |
Hotel | 10.8 | School/University | 12.9 |
Library | 14.0 | Sports Arena | 11.8 |
Manufacturing Facility | 14.0 | Transportation | 10.8 |
Motel | 10.8 | Warehouse | 8.6 |
Motion Picture Theatre | 12.9 | Workshop | 15.1 |
In cases where both a general building area type and a specific building area type arelisted, the specific building area type shall apply. |
2.2.3 Building Exterior Lighting Power
Building exterior and grounds lighting power densities. The connected lighting power shall not exceed the power limits specified in Table 2.2 and 2.3 for each of the listed building exterior applications. Trade-offs between applications will not bepermitted.
Table 2.2 Maximum Allowed Lighting Power for Building Exteriors
Application | Maximum Allowed Power Limits(W/linear m) |
Building entrance (with canopy)Low Traffic (hospital, office, school) High Traffic (retail, hotel, airport, theatre) | 32.4 (of canopied area) 64.8 (of canopied area) |
Building entrance (without canopy) | 98.4 (of door width) |
Building Exit | 65.6 (of door width) |
LoadingLoading AreaLoading Door | 3.0 (W/m2) 50.0 (of door width) |
Table 2.3 Maximum Allowed Lighting Power for Roads/Grounds
Application | Maximum Allowed Power Limits(W/m2) |
Storage and work area | 2.0 |
Areas for casual use (picnic grounds,gardens, parks, scenic landscapes) | 1.0 |
Driveways,/walkwaysPrivate Public | 1.0 1.5 |
Parking lotsPrivatePublic | 1.2 1.8 |
Emergency, Security and Exit Lights
When selecting luminaries to the above usage depends on the requirements specified by the rules and regulations corresponding to the relevant authorities due consideration shall be given to the energy efficient luminaries.
2.3 Prescriptive
Requirements
2.3.1 General and Task Lighting Considerations
There may be situations in a lighting installation where the maximum required light level does not need to be maintained throughout the area. In such situations, the lighting designer may focus on providing ‘Design Maintained Illuminance’ for the taskareas while maintaining ‘Standard Maintained Illuminance’ in the surrounding areas. Depending on the concept, this may be achieved by using localised lighting to supplement the general lighting that could be maintained at a minimum.
2.3.2 Selection of Appropriate Components
2.3.2.1 Light Source Selection
The use of incandescent or tungsten halogen lamps for general lighting should be discouraged unless the applicationspecifically requires so. Wherever applicable, general lighting should be provided with fluorescent lamps of appropriate colour.
Although incandescent and tungsten halogen light sources are the least expensive to install, they are less energy efficientcompared to sources such as fluorescent lighting or other discharge lamps. (Refer the Annex 2 for the comparison of lamp efficiencies)
Use of compact fluorescent lamps in ‘downlights’ in ceiling under 4 m and use of high pressure sodium vapour or metal halide lamps for ‘high bay’ applications (ceiling over 4 m) are generally recommended.
2.3.2.2 Lighting Equipment
Efficiency Levels
= Fluorescent
It is recommended to use the most efficient, cost effective lamp for each application. The lamp efficacy shall not be lesser thanvalues indicated in Table 2.4 for linear fluorescent lamps and Table 2.5 and 2.6 for compact fluorescent lamps respectively. Notethat the lamp efficacy is the efficacy of the lamp alone and it does not include the ballast losses. Lamp efficacy is calculated by dividing the lamp’s rated light output (in lumens) by the rated lamp power (watts). For the system lighting power density (LPD) limits (which include both lamp and ballast) see section 2.2.2.
Table 2.4: Minimum Lamp Efficacy of Linear Fluorescent Lamps (0.6 to 1.2 meters)
Lamp Length(mm) | Lamp Power(W) | Diameter(mm) | Minimum LampEfficacy (lm/W) |
600 | 18 | 26 | 55 |
1200 | 36 | 26 | 66 |
1500 | 58 | 26 | 66 |
Fluorescent ballast loss maxima
The ballast losses in linear fluorescent lamp ballasts should not exceed the values given in Table 2.7.
Table 2.7: Maximum Allowed Ballast Losses for Linear Fluorescent Lamp
Ballast Type | Maximum Allowed Ballast Loss(W) |
Electromagnetic | |
For 18 W single-lamp | 8 |
For 36 W single-lamp | 8 |
Electronic | |
For 18 W single-lamp | 4 |
For 18 W double-lamp | 6 |
For 36 W single-lamp | 4 |
For 36 W double-lamp | 7 |
Incandescent
The lamp efficacy for incandescent lamps should not be lesser than the efficacies listed in Table 2.8.
Table 2.8: Incandescent Lamp-Minimum Lamp Efficacy
Lamp Power (W) | Minimum Lamp Efficacy (lm/W) |
40 | 10.6 |
60 | 12.0 |
75 | 12.7 |
100 | 13.6 |
High Intensity Discharge
The lamp efficacy for high intensity discharge lamps (e.g. sodium, metal halide, mercury) should not be lesser than efficacies listed in Table 2.8, and the ballast losses for HID lamps should not exceed the values listed in Table 2.9.
Table 2.9: HID Lamp – Minimum Lamp Efficacy & Maximum Allowed Ballast Losses
Lamp Power(W) | Minimum Lamp Efficacy(lm/W) | Maximum Allowed BallastLoss (W) |
50 | 57 | 10 |
70 | 64 | 15 |
100 | 53 | 15 |
150 | 76 | 20 |
175 | 70 | 22 |
250 | 74 | 26 |
320 | 67 | 28 |
400 | 68 | 30 |
1000 | 104 | 60 |
1500 | 98 | 85 |
2.3.2.3 Luminaires
Use the most efficient luminaires/ fixtures complying with the manufacturer information of the fixture application. The efficiency of alighting fixture is given by its light output ratio (LOR) which is defined as the ratio of the lumens from the luminaire to the sum of the individual lumen values of the lamps inside the luminaire. For most fixtures used in commercial buildings, this information is made available through the luminaire/ fixture manufacturers.
For general-purpose lighting systems, use fixtures that have a minimum LOR of at least 0.50. It is never encouraged to use luminaires with LOR below 0.5. Exceptions to this would be a space with critical glare control needs (high- end graphics workstation, for example).
2.3.2.4 Emergency and Exit Lighting
Exit sign luminaire operating at greater than 20 Watts shall have a minimum source efficacy of 35 lumens per Watt. Light Emitting Diodes (LEDs) should be used in exit signs wherever possible.
Emergency lighting includes all of egress lighting, illuminated exit signs and all other lights specified as necessary to provide the required illumination. Emergency lightsystems shall be designed and installed so that failure of any individual lighting element, such as the lamp burnout, would not leave any space that requires emergency illumination in total darkness. Switches installed in emergency lighting circuits shall bearranged so that only authorised persons will have control over emergency lighting.
2.4 Strategy for Energy
Eefficient Lighting
(a) Work out best compromise between light quantity & quality
(b) Use lamps and ballast with maximum efficiencies
(c) Use of automatic controls such as day light sensors , time based controls or occupancy sensors
(d) Install lighting equipment with high power factor and low harmonic distortion
(e) Establish maintenance schedule for cleaning, group re-lamping and disposal techniques
(f) Efficient use of a lighting system depends upon the surrounding interior features, such as the ceiling height, windows,colour and reflectivity of room surfaces and furnishings.
Where possible, the lighting designer should work with both the architect and interior designer to ensure the combination of features that significantly enhance lighting levels, such as large windows and light- coloured finishes… etc.
2.5 Submission Procedure
The engineer or architect responsible for the lighting installation shall provide a complete set of plans to the buildingowner, depicting lighting devices, also to be accompanied by the following information.
a) The standard and design maintained illuminance for all the interior spaces
b) The specifications and numbers of each type of lighting device
c) The total wattage of each type of lighting device including nominal rating and control gear losses.
d) The installed lighting load for interior and exterior spaces
2.6 Annexes
- Comparison of Lamp Efficiencies
- Calculation of Glare Index direct from the Basic formula (Courtesy: CIBSE Guide TM 10)
- Position Index Data
- Recommended Illuminance Levels: Design Considerations and design guidelines
- Lighting Controls Credits.
3. Ventilation and Air Conditioning
3.1 Mandatory
Requirements
3.1.1 Load Calculations
3.1.1.1 Calculation Procedures
Cooling system design loads for the purpose of sizing systems and equipment shall be determined in accordance with theprocedures described in the latest edition of the ASHRAE Handbook 2004 or latter or other publications conforming to equalstandards.
3.1.1.2 Indoor Design Conditions
The indoor conditions of an air-conditioned space shall be designed for a dry bulb temperature of 25° C ± 1.5° C and relativehumidity of 55 % ± 5 %. The combination of suitable high temperatures and humidity may be used within the comfort zone forenergy saving purposes, provided that the conditions maintained herein are agreeable to the occupants.
3.1.1.3 Outdoor Design Conditions
Dry bulb temperatures of 31° C and wet bulb temperatures of 27° C. (See section 4 for more details). For computer aided designs, data from Climatologic Tables from the Meteorological Department of Sri Lankamay be used.
3.1.1.4 Ventilation and Exhaust
Outdoor air ventilation rates shall comply with ASHRAE Standard 62.1 2007 (Ventilation for Acceptable Indoor Air Quality). Itis also encouraged to use CO2 monitors and controls for installations with high and variable people occupancy. Outdoor air quantities however may exceed those shown in Standard 62 ascribed to special occupancy or process requirements or control of air contamination.
3.1.2 System and Equipment Sizing
3.1.2.1 A/C Systems and Equipment
A/C Systems and Equipment shall be sized to provide no more than the space and system loads calculated in accordance withsub- section 3.1.1 above, consistent with available equipment capacity.
3.1.2.2 Multiple Units
Multiple units of the same equipment type, such as multiple chillers, with combined capacities exceeding the design load may be specified to operate concurrently only if controls are provided in sequence, or otherwise, the operation of each unit should be optimallycontrolled based on the load.
3.1.2.3 Capacity
Capacity of any individual unit shall not be less than 20 kW (output), excepting backup units for specified areas.
3.1.2.4 Pressure Drop
It is recommended that when selecting equipment, the pressure drops in the chilled water cooling coils, water cooled condensersand evaporator coils should be kept below 6 m of water (20 ft of water) total pressure drop across the coil.
3.1.3 Fan System Design Criteria
3.1.3.1 General
The following design criteria apply to all A/C fan systems used for comfort ventilating and/or air conditioning. For the purposes of this sub- section. The energy demand of a fan system is defined as the sum of the demand of all fans operating at designed conditions to supply air from the cooling source to the conditioned space(s) and to the source in return or outdoors as an exhaust.
Exceptions
Systems with total fan system nameplate motor power of 4 kW or less.
3.1.3.2 Constant Volume Fan Systems
For fan systems that provide a constant air volume whenever the fans are operating, there shall be a requirement of at least 590 l/s of supply air volume per kW of total inputpower for the motors to provide the combined fan system at design conditions.
3.1.3.3 Variable Air Volume (VAV) Fan Systems
For fan systems that are able to vary system air volume automatically as a function of load, there shall be a requirement of at least 420 l/s of supply air volume per kW of total input power for the motors to provide the combined fan system at designedconditions.
3.1.4 Pumping System Design Criteria
3.1.4.1 General
The following design criteria apply to all pumping systems used for comfort air conditioning. For the purposes of this sub-section, the energy demand of a pumping system is defined as the sum of the demand of all pumps operating at designed conditions to supply fluid from the cooling source to the conditioned space(s) or to heat transfer device(s) and to the source inreturn.
3.1.4.2 Friction Rate
Piping systems shall be designed at friction pressure loss rate of 100 to 400 Pa per meter of equivalent pipe length subject tothe velocity in the system pipe lines not exceeding 2.5 m/s. Lower friction rates may be required for proper noise or corrosioncontrol.
3.1.4.3 Sizing, Selection, and System Design
The following aspects of pumping systems should be designed to minimise life-cycle system costs. Pipe size, components and layout should be optimised to reduce system pressure drops, thus reducing the pump and motor sizes required. Once theoperating flow and pressure are established, the pump should be carefully selected for maximum efficiency, and not less than 70 %. The flow rate should never exceed 110 % of designed flow. Once the pump shaft power requirement is determined, the motor with the highest efficiency at the design load should be selected to meet or exceed Minimum Motor Efficiency values in Table 5.1. The motor horsepower rating should notexceed 125 % of the calculated maximum load being served.
If a standard rated motor is not available within the range, the next largest standard motor size may be used. It is recommended that pump speeds should be kept less than 1500 rpm. Variable-speed pumps should be considered for variable-flow systems, especially for large systems. Variable-flow chilled water systems should also be evaluated, either as variable flow through the chiller as allowed by many manufacturers; or as primary-secondary pumping systems with constant chiller flow andvariable building system flow.
3.1.4.4 Variable Flow
Pumping systems that serve control valves designed to modulate or step open and closed as a function of load, shall be designed for variable fluid flow. Flow may be altered using variable-speed driven pumps, staged multiple pumps, or pumps riding their characteristic curves.
3.1.5 Separate Air Distribution Systems
3.1.5.1 Zones with Non-Simultaneous Operation
Zones that are expected to operate non- simultaneously for more than 300 hours per year shall be served by separate airdistribution systems. As an alternative, off-hour controls shall be provided in accordance with Section 3.1.7.3.
3.1.5.2 Zones with Special
Process Requirements
Zones with special process temperature and/or humidity requirements shall be served by separate air distribution systems fromthose serving zones requiring only comfort cooling, or shall include supplementary provisions so that the primary systems may bespecifically controlled for comfort purposes only.
Exceptions
Zones requiring comfort cooling only, which are served by a system primarily used for process temperature and humidity control, need not be served by a separate system if the total supply air to these zones is no more than 25 % of the total system supply air, or the total conditioned floor area of the zones is less than 100 m².
3.1.5.3 Zones with Different Load Characteristics
Separate air distribution systems should be considered for areas of the building having substantially different cooling characteristics, such as perimeter zones in contrast to interior zones.
3.1.6 Temperature Controls
3.1.6.1 System Control
Each A/C system shall include at least one temperature control.
3.1.6.2 Zone Controls
The supply of cooling energy to each zone shall be controlled by individual thermostatic controls responding to temperature within the zone.
In the case of large buildings, the area is broken up in to sections called Zones for purpose of air-conditioning. Normally, eachzone is serviced by one AHU and therefore the conditions in each zone needs to be controlled by a thermostat. Each thermostat in operation in turn will control the input of cooling energy (normally by way of chilled water) thereby resulting in effective economiccontrol.
3.1.6.3 Thermostats
Zone controls shall have an inbuilt feature to prevent the setting of the individual zone temperature lower than the indoor designed conditions (24° C). Temperature sensors shall be located in the zone or in the return air path.
The lowest temperature that can be set by a thermostat provided for each zone is limited to the Designed Indoor Temperature (24° C). However, a temperature higher than the designed indoor temperature can be set by the zone thermostat, if necessary, but should not be set below the designed condition..
3.1.7 Off-Hour Controls
3.1.7.1 Equipment Shutdown During Non-Use
A/C systems shall be equipped with automatic controls capable of accomplishing a reduction of energy use through equipmentshutdown, or increase in the temperature set point, during periods of non-use or alternative use of the spaces served by the system. In case of scheduled long term shutdowns of equipment, arrangements must be made to isolate the power supply to the crank caseheaters.
Exceptions
(a) Systems serving areas that are expected to operate continuously.
(b) Equipment with a connected load of 2 kW or less may be controlled by readily accessible manual off-hour controls.
3.1.7.2 Outside Air Control During Non-Use
Outdoor air supply and exhaust systems shall be provided with motorised or gravity dampers or other means of automatic volumeshutoff or reduction during periods of non- use of alternative use of the spaces served by the system.
Exceptions
(a) Systems serving areas that are expected to operate continuously.
(b) Systems that have a design air flow of 500 l/s or less.
(c) Gravityandothernon-electricalventilation systems may be controlled by readily accessible manual damper controls.
(d) Where temperature limits are restricted by process requirements such as combustion- air intakes.
3.1.7.3 Zones with Non-Simultaneous Operation
Systems that serve zones that can be expected to operate non-simultaneously for more than 300 hours per year shall include isolation devices and controls to shut off the supply of cooling to each zone independently. For central systems and plants, controls and devices shall be provided to allow stable system and equipment operation for any length of time while serving only the smallest isolation area served by the systemor plant. Isolation is not required for zones that are expected to operate continuously.
Isolation areas may be pre-designed for buildings where occupancy patterns are not known at the time of the system design, such as in speculative buildings. Zones may be grouped into a single isolation area provided that the total conditioned floor areadoes not exceed 250 m² per group nor includes more than one floor.
3.1.8 Piping Insulation
3.1.8.1 Chilled Water Piping
All A/C system chilled water piping shall be thermally insulated in accordance with Table 3.1. This provides not only to reduceheat gain from the outside, but also to avoid condensation on the surface of the installation. The insulation shall be suitably protected from damage and reference is expected to be made to the insulation manufacturer’s catalogue in this regard.
Exceptions
Piping insulation shall not be required in any of the following areas:
(a) Piping that conveys fluids that have a design temperature above 20° C. Note that if the indoor designed conditions are exceeded, insulation may require a higher temperature piping to prevent condensation.
(b) Piping that conveys fluids that have not been heated or cooled through the use of fossil fuels or electricity.
Details of standard piping insulation and methods of calculation are specified in Annex 3.
3.1.9 Air Handling System Insulation
3.1.9.1 A/C System Ducts and Plenums
All air-handling ducts and plenums installed as part of an AC air distribution system shall be thermally insulated.
Exceptions
Duct insulation is not required in any of the following cases:
(a) Factory installed plenums, casings or ductwork furnished as a part of AC equipment, provided that they are eitherinsulated at the factory or installed in a conditioned space
(b) Exhaust air ducts
(c) Outdoor air ducts
(d) Return air ducts within conditioned space
Details of methods of calculation of thermal resistance are specified in Annex 3.
3.1.10 Air Handling System Ducts
Ductwork and plenums shall be sealed in accordance with Table 3.2 and with standard industry practice as defined in SMACNA 1995 (Sheet Metal and Air ConditioningContractors’ National Association, HVAC Duct Construction Standards - Metal & Flexible, 1995).
Plenums shall be avoided in the supply side of the ducting as far as practically possible.
Minimum Design conditions are specified in Annex 3
3.1.11 A/C Equipment
Equipmentshallmeetorexceedtheminimum performance shown in Table 3.4 when tested at the standard rating conditions shownin Table
3.3. Note that except for the cooling towers, the rating conditions are those used internationally (for ease of comparison) rather than being typical of Sri Lankan conditions. VAC designers should determine equipment load profiles and obtain applied part-load values (APLVs) from the manufacturers to better estimate the actual energy use of the equipment as it is used. With the load and APLV information, designers should then select equipment based on minimising life-cycle cost of the system.
Table 3.3: A/C Equipment Standard Rating Conditions (°C)
Fluid | Water-cooledwaterchillers | Air-cooledwaterchillers | Water-cooledunitary A/C | Air-cooledunitaryA/C | Cooling Towers |
Leaving chilled water | 6.7 | 6.7 | N/A | N/A | N/A |
Entering chilled water | 12.2 | 12.2 | N/A | N/A | N/A |
Leaving cooling water | 35.0 | N/A | 35.0 | N/A | 31.0 |
Entering cooling water | 29.4 | N/A | 29.4 | N/A | 36.5 |
Condenser air inlet | N/A | 35.0 | N/A | 35.0 | N/A |
Evaporator air inlet | N/A | N/A | 27 DB/ 19.5 WB | 27 DB/ 19.5 WB | N/A |
Cooling tower air inlet | N/A | N/A | N/A | N/A | 27.0 WB |
a IPLVs and part load rating conditions are only applicable to equipment with capacity modulation.
b Section 12 contains a complete specification of the referenced test procedure, including the referenced year version of the testprocedure.
c Single – phase, air - cooled air conditioners
< 65,000 Btu/h are regulated by NAECA. SEER values are those set by NAECA
The compressor shall not be controlled by either hot gas bypass or other evaporator pressure regulator control systems unless thesystem is designed with multiple steps for unloading. The capacity of the hot gas bypass shall be limited to not more than 50 %of the total capacity in systems up to 70 kW of rated capacity, and not more than 25 % of the total capacity in systems over 70 kW ofrated capacity.
Water-to-water heat recovery systems (double-bundle chillers) should be used for water heating only after carrying out anenergy balance, cost-benefit analysis and life- cycle costing. Systems producing hot water at temperatures exceeding 42° C arediscouraged.
3.1.12 Testing, Adjusting, Balancing and Commissioning
Air system balancing shall be accomplished in a manner to minimise throttling losses and fan speeds shall be adjusted to meetdesigned flow conditions.
Hydronic system balancing shall be accomplished in a manner to minimise throttling losses and the pump impellers shall be trimmed or pump speeds shall be adjusted to meet designed flow conditions.
A/C control systems shall be tested to assure that control elements are calibrated and adjusted and that are in proper working condition.
Systems larger than 350 kW of cooling shall be commissioned in accordance with the procedures in ASHRAE Guideline1-1996, The HVAC Commissioning Process.
3.1.13 Water Treatment
The makeup water for systems larger than
350 kW of cooling shall be analysed by a recognised authority to determine the chemical characteristics of the water. This procedure shall be repeated once in every 365 days from the date of the commissioning of the plant to track changes in chemical characteristics in water if any.
Appropriate water treatment equipment shall be specified and installed to minimise the possibility of corrosion to the water cooling circuits, scale formation, and biological growth as well as the presence of suspended solids and sludge formation. Measures to reduce the quantity of water to be added to the water circuit should also be addressed with the intent to reduce waterusage and pumping energy costs.
Water treatment may be in the form of automatically dosing chemicals, magnetic de- scalers, filtration equipment, ozonedosing, or a combination of these methods.
Water treatment shall be in accordance with procedures detailed in ASHRAE 1995 HVAC Applications Handbook, Chapter 44 (Corrosion Control and Water Treatment), or other equivalent publications.
In installations where large air handling units or packaged units are used, arrangements should be made to collect thecondensate water to be used as cooling tower makeup water.
3.1.14 Maintenance
(a) An operation and maintenance manual shall be provided to the owner. The manual shall include basic data relating to theoperation and maintenance of A/C systems and equipment, as built drawings showing test points, recommended maintenancespares, list of suppliers and their contact details, including but not limited to original copies of manufacturers’ O & M manuals for all pieces of equipment. Required routine maintenance actions shall be clearly identified. Where applicable, A/C controlsinformation such as diagrams, schematics, control sequence descriptions, and maintenance and calibration information shall beincluded.
Sri Lanka Sustainable Energy Authority | |
EquipmentType | SizeCategory | HeatingSectionType | Sub- Categoryor RatingCondition | Minimum Efficiency a | TestProcedure b |
AirConditioners,Air Cooled | <65,000 Btu/h c | All | Split System | 10.0 SEER(before1/23/2006) 12.0 SEER (as of 1/23/2006) | ARI210/240 |
Single Package | 9.7 SEER (before1/23/2006) 12.0 SEER (as of 1/23/2006) |
Through –the –Wall, Air Cooled | ≤30,000 Btu/h c | All | Split System | 10.0 SEER (before1/23/2006) 10.9 SEER (as of1/23/2006) 12SEER (as of 1/23/2010) |
Single Package | 9.7 SEER (before1/23/2006) 10.6 SEER (as of1/23/2006) 12SEER (as of 1/23/2010) |
| | | | |
Small- DuctHigh –Velocity,AirCooled Air Conditioners, Air Cooled | <65,000 Btu/h c ≥65,000 Btu/hand <135,000 Btu/h ≥135,000 Btu/hand <240,000 Btu/h ≥240,000 Btu/hand <760,000 Btu/h ≥760,000 Btu/h | All ElectronicResistance( or None)All other ElectronicResistance( or None) All other ElectronicResistance( or None) All other ElectronicResistance( or None) All other | Split System Split System and SinglePackage Split System andSingle Package Split System andSingle Package Split System andSingle Package Split System and Single Package Split System andSingle Package Split System andSingle Package Split System andSingle Package | 10 SEER 10.3 EER 10.1 EER 9.7 EER 9.5 EER 9.5 EER 9.7 IPLV 9.3 EER 9.5 IPLV 9.2 EER 9.4 IPLV 9.0 EER 9.2 IPLV | ARI 340/360 |
Sri Lanka Sustainable Energy Authority | |
EquipmentType | SizeCategory | HeatingSectionType | Sub- Categoryor RatingCondition | Minimum Efficiencya | TestProcedure b |
AirConditioners,and WaterandEvaporativelyCooled CondensingUnits, Air Cooled CondensingUnits, Water andEvaporativelyCooled | <65,000 Btu/h c ≥65,000 Btu/hand <135,000 Btu/h ≥135,000 Btu/hand <240,000 Btu/h ≥240,000 Btu/h ≥135,000 Btu/h ≥135,000 Btu/h | All other ElectronicResistance( or None)All other ElectronicResistance( or None)All other ElectronicResistance( or None)All other - | Split SystemSinglePackage Split System and Single Package Split System andSingle Package Split System and SinglePackage Split System and SinglePackage Split System andSingle Package Split System andSingle Package | 12.1 EER 11.5 EER 11.3 EER 11.0 EER 10.8 EER 11.0 EER 10.3 IPLV 10.8 EER 10.1 IPLV 10.1 EER 11.2 IPLV 13.1 EER 13.1 IPLV | ARI 210/240 ARI 340/360 ARI 365 - |
(b) The owner should implement a
- Building Envelope
preventive maintenance program and
schedule periodic maintenance on all the critical items ofthe air-conditioning system such as compressors, cooling towers, pumps, condensers, air handlers, controls, filters and piping.
Owner shall appoint a responsible officer to be in charge of the equipment to make sure that the equipment and the system are operated as efficiently as possible. Key control parameters of the system must be periodically compared against the commissioning data to ensure that the system is operating at or near designed conditions.
Arrangements shall be made to ensure that the above mentioned maintenance procedures are followed diligently.
4.1.1 Submission Procedure
Plans on refrigeration and air-conditioning, prepared by an experienced Chartered Mechanical Engineer, will be providedto the Building Owner, containing the following information.
(a) The cooling capacity in kW of each air- handling unit and air-conditioning plant
(b) The capacity in l/s of each fan
(c) The location and capacity of each fresh air intake
(d) Supply, exhaust and return duct work distinctly coloured for clarity
(e) A summary of the air-conditioning load calculations and equipment performance figures
3.2 Annexes
- Piping insulation equations and standard values
- Air handling system insulation equations
- Air handling system ducting design considerations
- Comfort Zone Diagram
Building Envelope element of an occupied
building facility contributes to a substantial share of the cooling or heating load.The Heating, Ventilating and Air-conditioning (HVAC) system has to cater to this load as well in order to maintain the comfort and/or process conditions.Thus, the Building Envelop element plays an important role with respect to energy consumed and cost of energy in itsoperating phase during the entire life of the building facility.
4.1 General Principles of Energy Efficient Envelope Design
4.1.1 Pre-Considerations
Minimising the solar gain through the building envelope happens to be a primary consideration within the Sri Lankan context. Hence, siting and orientation of the building with its long axis in line with east-west, avoiding openings facing east and west directions, especially the west, use of light coloured walls & roof surfaces, appropriate internal & externalshading for fenestration, moderate window to wall ratios, minimum air infiltration into the occupied space and economic utilisation of building envelope insulation are recommended pre-considerations at the design stage.
4.1.2 Consideration of Climatic Zones and Building Typology
- Climatic Zones – 03 Climatic zones shall be considered: The outdoor design condition would vary based on thecorresponding climatic zone.This will in turn dictate the thermo-physical properties of all building elements.
i) warm-humid - (DBT, WBT) (310 oC, 270 oC)
ii) warm-dry - (DBT, WBT) (330 oC, 260 oC)
iii) uplands - (DBT, WBT) (280 oC ,230 oC)
- BuildingTypology – 02 types of building categories are considered based on duration of operation.
i) Day-Time operation (Offices, Shops, etc.)
ii) Extended operation (Hotels, Hospitals, Condominiums, Supermarkets, etc.)
4.1.3 Method of Compliance
This will be achieved by meeting the overall requirement – the Overall Thermal Transfer Value (OTTV) – subject to satisfying prescriptive criteria of each building envelope sub-element descried ahead.
4.2 Mandatory Requirements
4.2.1 U-values
U-values for roofs, fenestrations and facades (for determining the corresponding OTTVi values) shall be determinedfrom property data provided in Appendix 4.
4.2.2 Envelope Sealing
The following areas of the building envelope shall be sealed, caulked, gasketed or weather- stripped to minimise airleakage for buildings whose occupancy areas are treated other than by natural or any mechanical means of ventilation:
a) Joints around fenestration and doors
b) Junctions between walls and foundations, between walls & building corners, between walls and structural floors and roofs and between roof or wall panels
c) Openings at penetrations of utility services through roofs, walls and floors
d) Site built fenestrations and doors
e) Building assemblies used as ducts or plenums
f) ) Joints, seams and penetrations of vapour retarders
g) All other openings in the building envelope
4.2.3 Air Leakage
Fenestration and doors shall be designed to limit air leakage such that the air infiltration does not exceed 5 l/s m2 forglazed swinging entrance doors and for revolving doors and 2 l/s m2 for all other fenestration and doors.
4.2.4 National Building Regulations
Any existing national building regulations for minimum natural ventilation and daylight harnessing shall be complied with.
4.3 Prescriptive Requirements
4.3.1 External Wall with/without Fenestration (Facades)
a) Visual Light Transmittance (VLT)
The Mean Visual Light Transmittance (VLT) for all fenestrations shall be greater than 0.15
b) OTTVi values for Facades
Table 4.3.1a: Maximum U-values for facades
(External walls with/without Fenestration)
| Day-Timeoperation(Wm-2K-1) | Extendedoperation(Wm-2K-1) |
Warm-humid | 0.45 | 0.40 |
Warm-dry | 0.45 | 0.40 |
Upland | 0.38 | 0.35 |
Note:
i) OTTV for each of the distinct façades of the building (OTTVi) shall be estimated in accordance with the formula givenin the Appendix 4a.
ii) U-factors for opaque walls shall be estimated using Thermal Properties from Appendix 4b.
iii) Solar correction factor (CF) for fenestrations shall be selected from Appendix 4c.
iv) Combined Shading Coefficient (SC) for fenestrations shall be selected from Appendix 4d.
4.3.2 Roofs
a) Exterior roof surface solar absorptivity for non-tiled roofing surfaces shall be less than 0.4.
b) U-Factor for roofs
Table 4.3.2a: Maximum U-Factor values for Roofs.
| Day-Time operation (Wm-2K-1) | Extended operation (Wm-2K-1) |
| Tiled | Non-Tiled | Tiled | Non-Tiled |
Warm-humid | 0.30 | 0.40 | 0.30 | 0.28 |
Warm-dry | 0.25 | 0.40 | 0.25 | 0.28 |
Upland | 0.20 | 0.35 | 0.20 | 0.25 |
Note:
OTTV for the roof of the building (OTTVroof) shall be estimated in accordance with the formula given in theAppendix 4a using WWR=0.
4.3.3 Windows
Heat gain through windows could be controlled and reduced in many ways.
Strategies include the control of:
a) Window area, expressed as window-to-wall ratio (WWR).
b) Glass type, expressed as the shading coefficient for the glass (SCg).
c) Use of internal shading devices (SCint) and external shading devices (SCext) (external sunscreens, overhangs, fins,venetian blinds).
4.4. Compliance
i) All above stated Mandatory requirements shall be met
ii) Area weighted cumulative OTTV of the Actual building design combining actual OTTVi values of all facades of the building and U-factor values of roofs (hence the OTTVroof) shall be less than the corresponding cumulative OTTV of the Actual building design estimated using all prescriptive values and also than a value of 50 W/m2.
4.5 Submission procedure
i) OTTV & U-value estimations for facades & roofs shall be done using the VB-XL environment based code provided with the BEC or any other suitable substitute.
ii) Relevant data, accompanied by drawings shall be provided by the client with authorised manufacturers’specifications wherever applicable.
iii) Data on air leakage shall be provided by the client with supportive evidence
4.6 Annexes
- OTTV formula
- Solar Correction Factor for Fenestrations (CF)
- Combined Shading Coefficients (SC)
- Electric Power and Distribution
maximum demand is greater than 250 kVA, shall have the electrical distribution system designed so that energyconsumption can be check-
metered. The electrical power feeder for each facility for which check-metering is required
5.1 General Principles of Energy Efficient Electrical Power Distribution
5.1.1 This section applies to all building electrical systems, except extra low voltage systems, if wired separately.
5.1.2 The following sub-sections address only energy-efficiency issues and not other aspects of design, installation, operation, and maintenance of building electrical power and distribution systems.
5.1.3 For existing buildings at the stage of rewiring, all criteria under 5.2.1 shall apply.
5.1.4.No part of this section shall be construed as encouraging energy efficiency at the expense of safety and performance. The CODE shall in no way supersede electrical safety requirements in Section 60 (2) (e) 5 detailed in theSubsidiary Legislation under the Electricity Act.
5.2 Mandatory requirements
5.2.1 Electrical Distribution System
5.2.1.1 Supply connection exceeding 1000 kVA shall have a built-in recording facility to record demand (kVA), energy consumption (kWh), and total power factor in permanently installed energy meters. The metering shall also display current (Amperes in each phase and the neutral), voltage (Voltage between phases and between each phase and neutral), andpercentage total harmonic distortion (THD of current).
5.2.1.2 Supply connections not exceeding 1000 kVA but over125 kVA shall have a built-in recording facility to recorddemand (kVA),energy consumption (kWh), and total power factor.
5.2.1.3 Supply connections not exceeding 125 kVA shall have a built-in recording facility to record energy consumption(kWh).
5.2.1.4 Check Metering. Buildings, where the shall be subdivided in accordance with the following categories.
(a) Lighting and socket outlets
(b) Air-conditioning systems and equipment
(c) Other load centres with high probable energy consumption, such as kitchen, laundry, and restaurants in hotels, orsurgery rooms in hospitals
5.2.1.5 Divisional/Tenant sub-metering. A building occupied by many divisions of the same organisation or Multiple Tenant Buildings shall have sub-metering for each tenant. Each tenant having a maximum demand of 100 kVA or more shallhave provision to permit check-metering the tenant load as per 5.2.1.4 above. Common air-conditioning systems need not meet these tenant check-metering requirements.
5.2.1.6 Power Factor Correction. All electricity supplies exceeding 100A, 3 phase shall maintain their power factor between0.98 lag and unity at the point of connection. Loads should have power factor correction at the point of use (capacitors onmotors and lighting fixtures with ballasts; harmonic filters on non-linear loads); if necessary further correction equipment at the main switchboard should be provided to meet the overall requirement.
5.2.1.7 Neutral Current. Building loads should be balanced such that the fundamental component of the neutral current in any three- phase installation does not exceed 10 % of the design current of the entire installation when the designcurrent is being drawn.
5.2.1.8 Conductor Sizing. Designers should have documentary evidence to demonstrate how, subject to safety andperformance constraints, electrical conductors have been selected in a manner that minimises life-cycle costs.
5.2.1.9 Energy Audit, Prior to energizing the electrical installation, a pro-forma energy audit should be carried out encompassing all LV energy consuming equipment and the associated network to ensure that thedesign of the entire electrical system has been optimised in a cost-effective manner.
5.2.2 Transformers
5.2.2.1 All transformers that are part of the building electrical distribution system should be selected to minimise the combination of no-load, part-load, and full-load losses, without compromising the electrical system operation and reliabilityrequirements.
5.2.2.2 If the total capacity of such transformers exceeds 250 kVA, a calculation of total estimated annual operatingcosts of the transformer losses shall be made and compared to the cost of more efficient transformers. This calculation shall be based on estimated hours of transformer operation atprojected loading conditions and the associated transformer losses. Based on this analysis, transformer(s) with the lowestlife-cycle cost shall be selected.
5.2.3 Electric Motors
All permanently wired electric motors that serve the building shall meet the requirements of this section.
5.2.3.1 Three-phase induction motors shall have a nominal full-load motor efficiency not less than shown as“Required” in Table 5.1.
5.2.3.2 Efficiencies of motor types and sizes not covered in Table 5.1 are not regulated by this section. However,designers should use
Table 5.1: Minimum Efficiencies for Three-Phase Induction Motors
Motor Output (kW) | Required Efficiency (%) | Recommended Efficiency (%) |
2 pole | 4 pole | 2 pole | 4 pole |
1.1 | 82.2 | 83.8 | 85.5 | 86.5 |
1.5 | 84.1 | 85.0 | 86.5 | 86.5 |
2.2 | 85.6 | 86.4 | 86.5 | 89.5 |
3.0 | 86.7 | 87.4 | 87.2 | 89.5 |
4.0 | 87.6 | 88.3 | 89.5 | 89.5 |
5.5 | 88.5 | 89.2 | 89.5 | 91.0 |
7.5 | 89.5 | 90.1 | 90.2 | 91.7 |
11.0 | 90.6 | 91.0 | 91.0 | 93.0 |
15.0 | 91.3 | 91.8 | 92.4 | 93.0 |
18.5 | 91.8 | 92.2 | 93.0 | 93.6 |
22.0 | 92.2 | 92.6 | 93.0 | 94.1 |
30.0 | 92.9 | 93.2 | 93.6 | 94.1 |
37.0 | 93.3 | 93.6 | 93.6 | 94.5 |
45.0 | 93.7 | 93.9 | 94.1 | 95.0 |
55.0 | 94.0 | 94.2 | 94.5 | 95.0 |
75.0 | 94.6 | 94.7 | 95.0 | 95.4 |
Reference Conditions: Nominal full-load efficiencies per IEC 34 – 2 test procedure.
highly efficient motors for other categories not specifically covered by this standard. Such categories include smaller andlarger poly-phase motors, poly- phase motors of 6 and 8 poles, and single phase motors.
5.2.3.3 Motor nameplates shall list the minimum and the nominal full-load motor efficiencies and the full-load powerfactor.
5.2.3.4 Motor horsepower rating shall not exceed 200 % of the calculated maximum load being served.
5.2.3.5 Motor uses should insist on proper rewinding practices for any rewound motors. If such practices cannot be assured, the damaged motor should be replaced with a new efficient one rather than suffer the significant efficiency penaltyassociated with typical rewinding practices. A list of practices to be followed at a minimum is given in Annex 5.
5.3 Prescriptive Requirements
5.3.1 Additional Metering. The designer and user should consider additional metering where it would be useful for analysisto improve efficiency in the end-use loads and the distribution systems serving them. The outputs of such metering could bebeamed wirelessly to a location such as the one occupied by the officer designated by the organisation to optimise energyusage, so that the rate of energy consumption (should be displayed in monetary terms where the meter is programmable) andits variations are constantly visible to this officer. It is also preferable to design additional internal metering for sub sections of energy consumption such as lighting, air conditioning etc.
5.3.2 System designers should select motors tominimisethelife-cyclecostofthemotor-driven system. Such analysis will often result in the use of motors of a higher efficiency than required herein. The“Recommended” efficiencies in Table
5.1 provide a suggested improved efficiency level for motor selection. Designers should perform a life-cycle cost analysis to select the proper motor.
5.4 Design Considerations
5.4.1 Three-phase oil-immersed transformers shall be selected based on maximum allowable losses in Tables 5.2 and 5.3.
Exceptions
(a) Transformers below 100 kVA and above 1000 kVA
(b) AC and DC drive transformers
(c) All rectifier transformers and transformers designed for higher harmonics
(d) Autotransformers
(e) Non-distribution transformers, such as UPS (Uninterruptible Power Supply) transformers
(f) Special impedance transformers applied for special cases
(g) Grounding or testing transformers
Table 5.2: 11kV Transformer, 3 phase, oil immersed
TransformerCapacity (kVA) | Maximum Allowable Losses at FullLoad (% Load Loss + No–LoadLoss) |
100 | 2.5 |
160 | 2.3 |
250 | 2.1 |
400 | 1.5 |
630 | 1.4 |
800 | 1.4 |
1000 | 1.2 |
Reference conditions: 100 % of nameplate load at a temperature of 750 C.
Table 5.3: 33kV Transformer, 3 phase, oil immersed
TransformerCapacity(kVA) | Maximum Allowable Losses atFull Load (% Load Loss +No–Load Loss) |
100 | 2.7 |
160 | 2.2 |
250 | 1.8 |
400 | 1.5 |
630 | 1.5 |
800 | 1.5 |
1000 | 1.2 |
Reference conditions: 100 % of nameplate load at a temperature of 750 C.
5.5 Submission Procedure
Building owners shall be provided in writing basic data relating to the design, operation and maintenance of the electricaldistribution system of the building. This shall include:
(a) A single-line diagram of the building electrical system, inclusive of all the metering equipment.
(b) Floor plans showing locations of equipment, distribution gear, power factor correction equipment and the meteringequipment.
(c) Schematic diagrams of electrical control systems used for power saving (if any).
(d) Manufacturers’ data sheets confirming the maximum losses, allowed for transformers by clause 5.4.1 (applicable only for consumer owned transformers) and allowed for motors by clause 5.2.3.1.
5.6 Annexes
1. Guidelines for Maintaining Motor Efficiency During Rebuilding
- Service Water Heating
6.1 General Principles
6.1.1 This section applies to all service water heating systems and equipment.
6.1.2 The following sub-sections address only energy-efficiency issues and not other aspects of design, installation, operation and maintenance of service water heating systems.
6.1.3 The energy usage in these buildings can be significantly reduced if the following conservation measures areadopted.
a) Metering of hot water usage
b) Metering of hot water temperature
c) Controlling hot water flow rate
d) Maintaining hot water generating and storing facilities
e) Insulate and maintain the insulation of all hot water storage, tanks and circulating pipelines
6.1.4 These requirements apply to equipment used to produce and distribute hot water for:
a) Restrooms
b) Showers
c) Laundries
d) Pools and spas
e) Car washes, beauty salons and other commercial enterprises
f) hotels
6.2 Sizing of Systems
6.2.1 Service water heating system design loads for the purpose of sizing systems and equipment shall follow manufacturers’ recommendations.
6.2.2 Design Considerations
a) Minimise standby losses with heat traps, thermal insulation and temperature controls.
b) Reduce distribution losses with thermal insulation and system temperature controls or eliminate through point-of-useheaters.
c) Reduce hot water waste with flow-limiting or metering terminal devices.
d) Increase overall system performance with high efficiency sources.
6.3 Mandatory requirements
6.3.1 Water Heating Equipment Efficiency
6.3.1.1 All water heating equipment, hot water supply boilers used solely for heating potable water, pool heaters and hot water storage tanks shall meet criteria listing in Table 6.1.
6.3.1.2 Electric resistance water heaters are strongly discouraged except as backup for other SHW systems. Electric heat pump water heaters have considerably higher energy efficiency than electric resistance water heaters, particularlywithin the local climatic context.
6.3.1.3 Efficiency for electric resistance water heaters is given in terms of maximum Standby Loss (SL), where V is themeasured volume in litres. SL is the maximum watts based on a 38.9° C temperature difference between stored water andambient requirements.
Equipment Type | MinimumEfficiency |
Electric ResistanceWater Heaters | 5.9 + 5.3V SL (W) |
Gas Storage Water Heaters | 78% ET |
GasInstantaneousWater Heaters | 78% ET |
Gas Hot Water Supply Boilers | 77% ET |
Oil Hot Water Supply Boilers | 80%ET |
Dual Fuel Gas/OilHot Water SupplyBoilers | 80% ET |
6.3.1.4 Minimum efficiency for oil & gas- fired water heaters is given in terms of Thermal Efficiency (ET), which includes thermal losses from the heater shell.
6.3.1.5 Solar water heaters shall have a minimum efficiency of 60 % and have at least R-
2.2 insulation behind the collector plate.
6.3.2 Service Water Heating Piping Insulation
6.3.2.1 Entire hot water systems including storage tanks, pipelines shall be insulated properly to minimise the heat losses. The following hot water piping shall be insulated to levels specified in Section 6.4.2
(a) Recirculating system piping, including the supply and return piping of a circulating tank type water heater
b) The first 2.4 meters of outlet piping for a constant temperature non-recirculating storage system
(c) The inlet pipe between the storage tank and a heat trap in a non-recirculating storage system
(d) Pipes that are externally heated
6.3.2.2 Piping for heating systems with a design operating temperature of 60o C or greater shall have at least R-0.70 insulation. Piping for heating systems with a design operating temperature of less than 60o C butgreater than 40o C shall have at least R-0.35 insulation.
6.3.2.3 Insulations exposed to weather shall be protected by aluminum sheet metal, painted canvas, plastic cover, or similarmaterials.
6.3.3 Service Water Heating System Controls
6.3.3.1 Temperature controls shall be provided to limit the maximum temperature of water delivered to wash basinfaucets in public restrooms to 43° C.
6.3.3.2 Sanitary codes or nationally adopted standards define the conditions of the hot water required for eachapplication under consideration.
6.3.3.3 Systems designed to maintain usage temperatures in hot water pipes, such as recirculating hot water systems, shall be equipped with automatic time switches or other controls that can be set to switch off the usage temperature maintenance system during extended periods when hot water is not required.
6.3.3.4 Recirculating pumps shall be equipped with controls limiting operation to a period, staring from the beginning ofthe heating cycle to a maximum of 5 minutes following the end of the cycle, in maintaining storage tank water temperatures.
6.4 Prescriptive Requirements
6.4.1 Temperature Limits 6.4.1.1Temperaturecontrolsshallbeprovided
to limit point-of-use water temperatures not exceeding 50° C.
6.4.2 Heat Traps
Vertical pipe risers serving storage water heaters and storage tanks not having integral heat traps and serving a non-recirculating system shall have heat traps on both the inlet and outlet piping as close as possible to the storage tank. A heat trapis a means to counteract the natural convection of heated water in a vertical pipe run, by either a device specifically designed for the purpose or anarrangement of tubing that forms a loop of 360 degrees, or piping that from the point of connection to the water heater (inletor outlet) includes a length of piping directed downward before being connected to the vertical piping of the supply wateror hot water distribution system, as applicable.
6.5 Design Considerations
6.5.1 Supplementary Service Water Heating Systems
Where appropriate, supplementary service water heating system should be designed to maximise the energy efficiency of the system, incorporating the following:
(a) Solar water heating systems to supply all or part of service water demand.
(b) Heat recovery from hot discharge systems
(c) Use of alternative fuels such as LPG
(d) Electric heaters as last resort.
6.6 Submission Procedure
The Engineer responsible for the service hot water system installation shall provide complete details to the BuildingOwner inclusive of the following information.
(a) Input energy consumption rate (kW/kcal)
(b) Design operating temperature range
(c) For boilers, maximum design pressure, tested pressure (Pa)
(d) Type of fuel used
(e) Listing of equipment
(f) Storage tank capacity
(g) Maximum draw-off rate (l/s)
6.7 Annexes
Minimum Pipe Insulation Thicknesses for Service Hot Water Systems
Annex 1: Definitions, Abbreviations and Acronyms
General
Certain terms, abbreviations, and acronyms are defined in this section for the ease of understanding this code.The
definitions remain applicable to all sections of the code. Terms that are not defined shall have their ordinarily acceptedmeanings within the context in which they are used.
Definitions
Addition: an extension or increase in floor area or height of a building outside of the existing building envelope
Alteration: any change, rearrangement, replacement, or addition to a building or its systems and equipment; anymodification in construction or building equipment
Area: see roof and wall, conditioned floor, day-lighted, façade, fenestration, lighted floor
Authority: the agency or agent responsible for enforcing this standard
Automatic: self-acting, operating by its own mechanism when actuated by some non manual influence, such as achange in current strength, pressure, temperature or mechanical configuration.
Automatic control device: a device capable of automatically turning loads off and on without manual intervention
Balancing, air system: adjusting airflow rates through air distribution system devices, such as fans and diffusers, bymanually adjusting the position of dampers, splitters vanes, extractors, etc., or by using automatic control devices, suchas constant air volume or variable air volume boxes
Ballast: a device used in conjunction with an electric-discharge lamp to cause the lamp to start and operate under
proper circuit conations of voltage, current, waveform, electrode heat, etc.
Boiler: a self-contained low-pressure appliance for supplying steam or hot water
Building: a structure wholly or partially enclosed within exterior walls, or within exterior and party walls, and a roof,affording shelter to persons, animals or property.
Building, existing: a building or portion there-of that was previously occupied or approved for occupancy by theauthority having jurisdiction
Building complex: a group of buildings in a contiguous area under single ownership
Building entrance: any doorway set of doors, turnstiles or other form of portal
that is ordinarily used to gain access to the building by its users and occupants
Building envelope: the exterior plus the semi-exterior portions of a building. For the purposes of determining building envelope requirements, the classifications are defined as follows:
(a) Building envelope, exterior: the elements of a building that separate conditioned spaces from the exterior
(b) Building envelope, semi-exterior: the elements of a building that separate conditioned space from unconditioned space or that encloses semi-cooled spaces through which thermal energy may be transferred to orfrom the exterior, or to or from unconditioned spaces, or to or from conditioned spaces
Building exit: any doorway set of doors, or other form of portal that is ordinarily used only for emergency way out orconvenience exit
Building grounds lighting: lighting provided through a building’s electrical service for parking lot, site, roadway,pedestrian pathway, loading dock and security applications
Building material: any element of the building envelope through which heat flows and that heat is included in thecomponent U-factor calculations other than air films and insulation
Circuit breaker: a device designed to open and close a circuit by non-automatic means and to open the circuitautomatically at a predetermined over-current without damage to itself when properly applied within its rating
Coefficient of Performance (COP) – cooling: the ratio of the rate of heat removal to the rate of energy input, inconsistent units, for a complete refrigerating system or some specific portion of that system under designated operatingconditions
Commercial building: all buildings except for multi-family buildings of three stories or fewer above grade and single-family buildings
Conditioned space: a cooled space, heated space, or indirectly conditioned space.
Construction documents: drawings and specifications used to construct a building, building systems, or portionsthereof
Control: to regulate the operation of equipment
Control device: a specialized device used to regulate the operation of equipment
Day-lighted area: the daylight illuminated floor area under horizontal fenestration (skylight) or adjacent to verticalfenestration (window)
Demand: the highest amount of power (average kVA over an interval) recorded for a building or facility in a selectedtime frame
Design capacity: output capacity of a system or piece of equipment at design conditions
Design conditions: specified environmental conditions, such as temperature and light intensity required to beproduced and maintained by a system and under which the system must operate
Distribution system: a device or group of devices or other means by which the conductors of a circuit can bedisconnected from their source of supply
Door: all operable opening areas (which are not fenestration) in the building envelope, including swinging androll-up doors, fire doors, and access hatches. Doors that are more than one-half glass are considered fenestration.For the
purposes of determining building envelope requirements, the classifications are defined as follows:
(a) Door, non-swinging: roll-up sliding, and all other doors that are not swinging doors.
(b) Door, swinging: all operable opaque panels with hinges on one side and opaque revolving doors.
Effective aperture, horizontal fenestration: a measure of the amount of daylight that enters a spacethrough
horizontal fenestration (skylights). It is the ratio of the skylight area times the visible light transmission divided bythe gross roof area above the day-lighted area.
Efficacy: the lumens produced by a lamp/ballast system divided by the total watts of input power (including theballast), expressed in lumens per watt
Efficiency: performance at a specified rating condition
Remittance: the ratio of the radiant heat flux emitted by a specimen to that emitted by a blackbody at the sametemperature and under the same conditions
Enclosed building: a building that is totally enclosed by walls, floors, roofs, and openable devices such as doors and operable windows
Energy: the capacity for doing work.
It takes a number of forms that may be transformed from one into another such as thermal (heat), mechanical (work),electrical and chemical. Customary measurements are watts (W)
Energy Efficiency Ratio (EER): the ratio of net cooling capacity in Btu/h to total rate of electric input in watts underdesignated operating conditions
Energy Factor (EF): a measure of water heater overall efficiency
Equipment: devices for comfort conditioned, electric power, lighting, transportation or service water heatingincluding, but not limited to furnaces, boilers, air conditioners, heat pumps, chillers, water heaters, lamps, luminaries, ballasts, elevators, escalators or other devices or installations
Equipment, existing: equipment previously installed in an existing building
Facade area: area of the facade, including overhanging soffits, cornices, and protruding columns, measured inelevation in a vertical plane, parallel to the plane of the face of the building. Non-horizontal roof surfaces shall beincluded in the calculations of vertical facade area by measuring the area in a plane parallel to the surface.
Fan system power: the sum of the nominal power demand (nameplate W or HP) of motors of all fans that arerequired to operate at design conditions to supply air from the heating or cooling source to the conditioned space(s) andreturn it to the source of exhaust it to the outdoors.
Fenestration: all areas (including the frames) in the building envelope that let in light, including windows, plasticpanels, clerestories, skylights, glass doors that are more than one-half glass, and glass block walls.
(a) Skylight: a fenestration surface having a slope of less than 60 degrees from the horizontal plane. Otherfenestration, even if mounted on the roof of a building, is considered vertical fenestration.
Fenestration area: the total area of fenestration measured using the rough opening and including the glass or plastic, sash, and frame.
Heat: the form of energy that is transferred by virtue of a temperature difference or a change in state of a material.
Illuminance: the density of the luminous flux incident on a surface. It is the quotient of the luminous flux multiplied by the area of the surface when the latter is uniformly illuminated.
Infiltration: the uncontrolled inward air leakage through cracks and crevices in any building element and around windows and doors of a building.
Joule (J): is the work done or the energy expended when a force of one Newton moves the point of application adistance of one metre in the direction of that force.
Kelvin (K): the unit of thermodynamic temperature. It is 1/273.16 of the thermodynamic temperature of the triplepoint of water.
Kilogram (kg): the unit of mass.
Kilovolt-ampere (kVA): where the term “kilovolt-ampere” (kVA) is used in this
standard, it is the product of the line current (amperes) times the nominal system voltage (kilovolts) times 1.732 for three-phase currents. For single-phase applications, kVA is the product of the line current (amperes) times thenominal system voltage (kilovolts).
Kilowatt (kW): the basic unit of electric power, equal to 1000 W.
Lamp: a generic term for man-made light source often called bulb or tube.
Large scale housing developments: structured building development of residential properties. Earlier popularthroughout the US & UK, these areas of high population density.
Lighted floor area, gross: the gross floor area of lighted spaces.
Lighting, decorative: lighting that is purely ornamental and installed for aesthetic effect. Decorative lighting shall not include general lighting.
Lighting, emergency: lighting that provides illumination only when there is a general lighting failure.
Lighting, general: lighting that provides a substantially uniform level of illumination throughout an area. General lighting
shall not include decorative lighting or lighting that provides a dissimilar level of illumination to serve a specializedapplication or feature within such area.
Lighting Efficacy (LE): the quotient of the total lumens emitted from a lamp or lamp/ballast combination divided by the watts of input power, expressed in lumens per watt.
Lighting system: a group of luminaries circuited or controlled to perform a specific function.
Lighting Power Density (LPD): the maximum lighting power per unit of area of a building classification of spacefunction.
Lumen (lm): unit of luminous flux.
Radiometrically, it is determined from the radiant power. Photometrically, it is the luminous flux emitted within a unit solidangle (one steradian) by a point source having a uniform luminous intensity of one candela.
Lumen maintenance control: a device that senses the illumination level and causes an increase or decrease of illuminance to maintain a preset illumination level.
Luminaries: a complete lighting unit consisting of a lamp or lamps together with the housing designed to distributethe light, position and protect the lamps, and connect the lamps to the power supply.
Manual (non-automatic): requiring personal intervention for control. Non- automatic does not necessarily imply
a manual controller, only that personal intervention is necessary.
Manufacturer: the company engaged in the original production and assembly of products or equipment or a company that purchases such products andequipment manufactured in accordance with company specifications.
Mean temperature: one-half the sum of the minimum daily temperature and maximum daily temperature.
Mechanical cooling: reducing the temperature of a gas or liquid by using vapor compression, absorption, desiccant dehumidification combined with evaporative cooling, or another energy- driven thermodynamic
Service water heating: heating water for domestic or commercial purposes other than space heating andprocess requirements
Set point: point at which the desired temperature (°C) of the heated or cooled space is set
Shading Coefficient (SC): the ratio of solar heat gain at normal incidence through glazing to that occurringthrough 3 mm (1/8 in) thick clear, double-strength glass.
Shading coefficient, as used herein, does not include interior, exterior, or integral shading devices
Simulation program: a computer program that is capable of simulating the energy performance of buildingsystems
Site-recovered energy: waste energy recovered at the building site that is used to offset consumption ofpurchased fuel or electrical energy supplies
Solar Heat Gain Coefficient (SHGC): the ratio of the solar heat gain entering the space through thefenestration area to the incident solar radiation. Solar heat gain includes directly transmitted solar heat andabsorbed solar radiation, which is then
reradiated, conducted, or convected into the space.
Space: an enclosed space within a building. The classifications of spaces are as follows for the purpose of determining building envelope requirements.
(a) Conditioned space: a cooled space, heated space, or directly conditioned space.
(b) Semi-heated space: an enclosed space within a building that is heated by a heating system whose outputcapacity is greater or equal to 10.7 W/m2 (3.4 Btu/h-ft2) of floor area but is not a conditioned space.
(c) An enclosed space within a building that is not conditioned space or a semi-heated space. Crawlspaces, attics,and parking garages with natural
or mechanical ventilation are not considered enclosed spaces.
U-factor (Thermal Transmittance): heat transmission in unit time through unit area of a material or constructionand the boundary air films, induced by unit temperature difference between the environments on each side. Unitsof U are W/m2-oC (Btu/h-ft2-°F).
Thermostat: an automatic control device used to maintain temperature at a fixed or adjustable set point.
Tinted: (as applied to fenestration) bronze, green, or grey coloring that is integral with the glazing material. Tintingdoes not include surface applied films such as reflective coatings, applied either in the field or during themanufacturing process.
Transformer: a piece of electrical equipment used to convert electric power from one voltage to another voltage
Variable Air Volume (VAV) system: HVAC system that controls the dry-bulb temperature within a space by varyingthe volumetric flow of heated or cooled supply air to the space
Vent damper: a device intended for installation in the venting system or an individual, automatically operated,fossil fuel-fired appliance in the outlet or downstream of the appliance draft control device, which is designed to automatically open the venting system when the appliance is in operation and to automatically close off theventing system when the appliance is in standby or shutdown condition.
Ventilation: the process of supplying or removing air by natural or mechanical means to or from any space.Such air is not required to have been conditioned.
Wall: that portion of the building envelope, including opaque area and fenestration, that is vertical or tilted at anangle of 60° from horizontal or greater. This includes above- and below-grade walls, between floor spandrels,peripheral edges of floors, and foundation walls.
Abbreviations and Acronyms
ASHRAE - American Society of Heating, Refrigerating and Air-Conditioning Engineers
ASTM - American Society for Testing and Materials
Btu- British thermal unit
Btu/h - British thermal units per hour
Btu/ft2-°F -British thermal units per square foot per degree Fahrenheit
Btu/h-ft2 -British thermal units per hour per square foot
Btu/h-ft-°F -British thermal units per lineal foot per degree Fahrenheit
Btu/h-ft2-°F- British thermal units per hour per square foot per degree Fahrenheit
C –Celsius
COC - Certificate of Conformity
CODE - Code of Practice on Energy Efficient Buildings in Sri Lanka
cfm - cubic feet per minute
cm - centimeter
COP - coefficient of performance
EER - energy efficiency ratio
EF - energy factor
ft - foot
h - hour
HC- heat capacity
h-ft2-°F/Btu -hour per square foot per degree Fahrenheit per British thermal unit
h-m2-°C/W- hour per square meter per degree Celsius per Watt
hp- horsepower
HVAC- heating, ventilation, and air conditioning
I-P inch-pound
in.- inch
IPLV - integrated part-load value
kVA - kilovolt-ampere
kW -kilowatt
kWh - kilowatt-hour LE - lighting efficacy lin - linear
lin ft- linear foot lin m -linear meter lm - lumen
LPD - lighting power density
m - meter
mm - millimeter
PF- projection factor
R -R-value (thermal resistance)
SC - shading coefficient
SEA - Sri Lanka Sustainable Energy Authority
SHGC- solar heat gain coefficient
SL - standby loss
VAV - variable air volume
VLT - visible light transmission
W - watt
W/ft2 - watts per square feet
W/m2 - watts per square meter
W/m2-°C - watts per square meter per degree Celsius
W/m2 - watts per hour per square meter
W/m-°C - watts per lineal meter per degree Celsius
W/m2-°C - watts per hour per square meter per degree Celsius
Wh - watthour
1) Comparison of Lamp Efficiencies
2) Calculation of Glare Index direct from the Basic formula ((Courtesy: CIBSE Guide TM 10)
Part calculation of glare index direct from the basic formula
The individual glare constant,g,for each luminaire in the installation is obtained from the glare formula 1,2,3 .
G = 0.9L 1.6ω0.8/L P1.6
Where (see Fig 1)
Ls = luminance of each individual luminaire in the direction of the observer’s eye .. cd/m2
Ω=solid angle subtended by each luminaire at the observer’s eye …ST
Lb= background (surround) luminance- defined as that uniform luminance of the whole surrounding
which produces the same illuminance on a vertical plane at the observer’s eye as the visual field under consideration, excluding the glare sources .. cd/m2
P= position index for each individual luminaire which relates to its displacement from the line of sight
Glare index from an installation
The Glare index for an installation is obtained from the following equation by summing the glare constants.
Glare Index GI = 10 log 10 (0.5 ∑g)
The value of the Glare Index should be quoted correct to one decimal place.
3) Average Daylight Factor and Limiting Depth Criteria ((Courtesy: Designing Buildings for Daylight byJames Bell and William Burt)
D= W/A* (T Ө/ (1-R2))
Where
D = average daylight factor
W=window area in m2 (using table 5 to correct for framing)
A= area of all surfaces of the room in m2 (floor, ceiling and walls including windows)
T = glass transmittance ( from table 30 corrected for dirt ( using table 4)
Ө= visible sky angle, in degrees
R = average reflectance of area A (from table 2)
4. To be successfully day-lit from one side, the depth (L) of the room should be limited to meet the following condition:
Where;
L =depth of room from window to back wall
w =width of the room measured across the window wall
h =height of the window head above the floor
Rb = area weighted average reflectance in the back half of the room ( the value for a typical office is likely to be around0.5)
Source BS Day light code 2 , pg 19
4 Recommended Illuminance Levels
4.1 Standard Maintained Illuminance It is the responsibility of the Lighting
Designer to select the illumination level required for any given task.
The Standard Maintained Illuminance values are tabulated in Table No. 2.10 and these values shall be the startingpoint for any lighting design. For further information on ‘Standard Maintained Illuminance’ for specific tasks, please refer“Code of Interior Lighting
– 1994”, published by the Chartered Institution of Building services Engineers (CIBSE), UK.
Table 2.1.1A: Position Index Data
H/R 0.00 | 0.10 | 0.20 | 0.30 | 0.40 | 0.50 | 0.60 | 0.70 | 0.80 | 0.90 | 1.00 | |
1.00 | 1.26 | 1.53 | 1.90 | 2.35 | 2.86 | 3.50 | 4.20 | 5.00 | 6.00 | 7.00 |
1.05 | 1.22 | 1.46 | 1.80 | 2.20 | 2.75 | 3.40 | 4.10 | 4.80 | 5.80 | 6.80 |
1.12 | 1.30 | 1.50 | 1.80 | 2.20 | 2.66 | 3.18 | 3.88 | 4.60 | 5.50 | 6.50 |
1.22 | 1.38 | 1.60 | 1.87 | 2.25 | 2.70 | 3.25 | 3.90 | 4.60 | 5.45 | 6.45 |
1.32 | 1.47 | 1.70 | 1.96 | 2.35 | 2.80 | 3.30 | 3.90 | 4.60 | 5.40 | 6.40 |
|
1.43 | 1.60 | 1.82 | 2.10 | 2.48 | 2.91 | 3.40 | 3.98 | 4.70 | 5.50 | 6.40 | |
1.55 | 1.72 | 1.98 | 2.30 | 2.65 | 3.10 | 3.60 | 4.10 | 4.80 | 5.50 | 6.40 |
1.70 | 1.88 | 2.12 | 2.48 | 2.87 | 3.30 | 3.78 | 4.30 | 4.88 | 5.60 | 6.50 |
1.82 | 2.00 | 2.32 | 2.70 | 3.08 | 3.50 | 3.92 | 4.50 | 5.10 | 5.75 | 6.60 |
1.95 | 2.20 | 2.54 | 2.90 | 3.30 | 3.70 | 4.20 | 4.75 | 5.30 | 6.00 | 6.75 |
|
2.11 | 2.40 | 2.75 | 3.10 | 3.50 | 3.91 | 4.40 | 5.00 | 5.60 | 6.20 | 7.00 | |
2.30 | 2.55 | 2.92 | 3.30 | 3.72 | 4.20 | 4.70 | 5.25 | 5.80 | 6.55 | 7.20 |
2.40 | 2.75 | 3.12 | 3.50 | 3.90 | 4.35 | 4.85 | 5.50 | 6.05 | 6.70 | 7.50 |
2.55 | 2.90 | 3.30 | 3.70 | 4.20 | 4.65 | 5.20 | 5.70 | 6.30 | 7.00 | 7.70 |
2.70 | 3.10 | 3.50 | 3.90 | 4.35 | 4.85 | 5.35 | 5.85 | 6.50 | 7.25 | 8.00 |
|
2.85 | 3.15 | 3.65 | 4.10 | 4.55 | 5.00 | 5.50 | 6.20 | 6.80 | 7.50 | 8.20 | |
2.95 | 3.40 | 3.80 | 4.25 | 4.75 | 5.20 | 5.75 | 6.30 | 7.00 | 7.65 | 8.40 |
3.10 | 3.55 | 4.00 | 4.50 | 4.90 | 5.40 | 5.95 | 6.50 | 7.20 | 7.80 | 8.50 |
3.25 | 3.70 | 4.20 | 4.65 | 5.10 | 5.60 | 6.10 | 6.75 | 7.40 | 8.00 | 8.65 |
3.43 | 3.86 | 4.30 | 4.75 | 5.20 | 5.70 | 6.30 | 6.90 | 7.50 | 8.17 | 8.80 |
|
3.50 | 4.00 | 4.50 | 4.90 | 5.35 | 5.80 | 6.40 | 7.10 | 7.70 | 8.30 | 8.90 | |
3.60 | 4.17 | 4.65 | 5.05 | 5.50 | 6.00 | 6.60 | 7.20 | 7.82 | 8.45 | 9.00 |
3.75 | 4.25 | 4.72 | 5.20 | 5.60 | 6.10 | 6.70 | 7.35 | 8.00 | 8.55 | 9.15 |
3.85 | 4.35 | 4.80 | 5.25 | 5.70 | 6.22 | 6.80 | 7.40 | 8.10 | 8.65 | 9.30 |
3.95 | 4.40 | 4.90 | 5.35 | 5.80 | 6.30 | 6.0 | 7.50 | 8.20 | 8.80 | 9.40 |
|
4.00 | 4.50 | 4.95 | 5.40 | 5.85 | 6.40 | 6.95 | 7.55 | 8.25 | 8.85 | 9.50 | |
4.07 | 4.55 | 5.05 | 5.47 | 5.95 | 6.45 | 7.00 | 7.65 | 8.35 | 8.95 | 9.55 |
4.10 | 4.60 | 5.10 | 5.53 | 6.00 | 6.50 | 7.05 | 7.70 | 8.40 | 9.00 | 9.60 |
4.15 | 4.62 | 5.15 | 5.56 | 6.05 | 6.55 | 7.08 | 7.73 | 8.45 | 9.05 | 9.65 |
4.20 | 4.65 | 5.17 | 5.60 | 6.07 | 6.57 | 7.12 | 7.75 | 8.50 | 9.10 | 9.70 |
4.22 | 4.67 | 5.20 | 5.65 | 6.12 | 6.60 | 7.15 | 7.80 | 8.55 | 9.12 | 9.70 |
36
| 1.10 | 1.20 | 1.30 | 1.40 | 1.50 | 1.60 | 1.70 | 1.80 | 1.90 | 8.10 | 9.25 | 10.35 | 11.70 | 13.15 | 14.70 | 16.20 | - | - | 8.00 | 9.10 | 10.30 | 11.60 | 13.00 | 14.60 | 16.10 | - | - | 7.60 | 8.75 | 9.85 | 11.20 | 12.70 | 14.00 | 15.70 | - | - | 7.40 | 8.40 | 9.50 | 10.85 | 12.10 | 13.70 | 15.00 | - | - | 7.30 | 8.30 | 9.40 | 10.60 | 11.90 | 13.20 | 14.60 | 16.00 | - | | | 7.30 | 8.30 | 9.40 | 10.50 | 11.75 | 13.00 | 14.40 | 15.70 | - | 7.35 | 8.40 | 9.4 | 10.50 | 11.70 | 13.00 | 14.10 | 15.40 | - | 7.40 | 8.50 | 9.50 | 10.50 | 11.70 | 12.85 | 14.00 | 15.20 | - | 7.50 | 8.60 | 9.50 | 10.60 | 11.75 | 12.80 | 14.00 | 15.10 | - | 7.70 | 8.70 | 9.65 | 10.75 | 11.80 | 12.90 | 14.00 | 15.00 | 16.00 | | | 7.90 | 8.80 | 9.75 | 10.80 | 11.90 | 12.95 | 14.00 | 15.00 | 16.00 | 8.15 | 9.00 | 9.90 | 10.95 | 12.00 | 13.00 | 14.00 | 15.00 | 16.00 | 8.30 | 9.20 | 10.00 | 11.02 | 12.10 | 13.10 | 14.00 | 15.00 | 16.00 | 8.55 | 9.35 | 10.20 | 11.20 | 12.25 | 13.20 | 14.00 | 15.00 | 16.00 | 8.70 | 9.50 | 10.40 | 11.40 | 12.40 | 13.25 | 14.05 | 15.00 | 16.00 | | | 8.85 | 9.70 | 10.55 | 11.50 | 12.50 | 13.30 | 14.05 | 15.02 | 16.00 | 9.00 | 9.80 | 10.80 | 11.75 | 12.60 | 13.40 | 14.20 | 15.05 | 16.00 | 9.20 | 10.00 | 10.85 | 11.85 | 12.75 | 13.45 | 14.20 | 15.10 | 16.00 | 9.35 | 10.10 | 11.00 | 11.90 | 12.80 | 13.50 | 14.20 | 15.10 | 16.00 | 9.50 | 10.20 | 11.00 | 12.00 | 12.82 | 13.55 | 14.20 | 15.10 | 16.00 | | | 9.60 | 10.40 | 11.10 | 12.00 | 12.85 | 13.60 | 14.30 | 15.10 | 16.00 | 9.75 | 10.50 | 11.20 | 12.10 | 12.90 | 13.70 | 14.35 | 15.10 | 16.00 | 9.85 | 10.60 | 11.30 | 12.10 | 12.90 | 13.70 | 14.40 | 15.15 | 16.00 | 9.90 | 10.70 | 11.40 | 12.20 | 12.95 | 13.70 | 14.40 | 15.20 | 16.00 | 10.00 | 10.80 | 11.50 | 12.25 | 13.00 | 13.75 | 14.45 | 15.20 | 16.00 | | | 10.05 | 10.85 | 11.55 | 12.30 | 13.00 | 13.80 | 14.50 | 15.25 | 16.00 | 10.10 | 10.90 | 11.60 | 12.32 | 13.00 | 13.80 | 14.50 | 15.25 | 16.00 | 10.16 | 10.92 | 11.63 | 12.35 | 13.00 | 13.80 | 14.50 | 15.25 | 16.00 | 10.20 | 10.95 | 11.65 | 12.35 | 13.00 | 13.80 | 14.50 | 15.25 | 16.00 | 10.23 | 10.95 | 11.65 | 12.35 | 13.00 | 13.80 | 14.50 | 15.25 | 16.00 | 10.23 | 10.95 | 11.65 | 12.35 | 13.00 | 13.80 | 14.50 | 15.25 | 16.00 |
| |
Table 2.1.1A: Position Index Data
37
Table 2.10: Standard Maintained Illuminance
Standardmaintainedilluminance (lux) | Characteristics of activity/ interior | Representativeactivities/interiors |
50 | Interiors used rarely with visualtasks confined to movement andcasual seeing without perception ofdetail. | Cable tunnels, indoors storage tanks,walkway |
100 | Interiors used occasionally withvisual tasks confined tomovement and casual seeingcalling for only limited perceptionof detail | Corridors, changing rooms, bulk stores,auditoria |
150 | Interiors used occasionally or withvisual tasks not requiring perception ofdetail but involving some risk topeople, plant or product | Loading bays,medical stores, plantrooms |
200 | Interiors occupied for longperiods, or for visual tasksrequiring some perception ofdetail | Foyers andentrances, monitoringautomatic processes,casting concrete,turbine halls, diningrooms |
300+ | Interiors occupied for longer periods, or when visual tasks are moderately easy, i.e. large details > 10 minarc and/ or high contrast. | Libraries, sportsand assemblyhalls, teachingspaces, lecturetheatres, packing |
500† | Visual tasks moderately difficult, i.e.details to be seen are of moderate size (95 – 10 min arc) and may be of lowcontrast; also colour judgment may berequired. | General offices,engine assembly,painting andspraying, kitchens,laboratories, retailshops |
750† | Visual tasks difficult, i.e. details to beseen are small (3 – 5 min arc) and oflow contrast; also good colourjudgment or the creation of a well lit,inviting interior may be required | Drawing offices,ceramicdecoration, meatinspection, chainstores |
1000† | Visual tasks very difficult, i.e. detailsto be seen are very small (2 – 3 minarc) and of low contrast; alsoaccurate colour judgments or thecreation of well lit, inviting interior may be required | Generalinspection,electronicassembly, gaugeand tool rooms,retouchingpaintwork, cabinetmaking,supermarkets |
1500† | Visual tasks extremely difficult; i.e.details to be seen extremely small(1 – 2 min arc) and of low contrast;optical aids and local lighting maybe of advantage | Fine work andinspection, handtailoring, precisionassembly |
2000† | Visual tasks exceptionally difficult, i.e.details to be seen exceptionally small (<1min arc) with very low contrast; opticalaids and local lighting will be of advantage | Assembly of minutemechanisms, finishedfabric inspection |
† 1 minute of arc (min arc) is 1/60 of a degree. This is the angle of which the tangent is given by thedimension of the task detail to be seen divided by the viewing distance. Courtesy: CIBSE Code of InteriorLighting – 1994)
Design Maintained Illuminance
However, depending on the task size and contrast, task duration and the risk, serious consequences shallbe taken into account in designing lighting systems for specific applications. The methodology that may be adopted for arriving at final illumination levels, which is known as “Design Maintained Illuminance”, is given inhere.
Table 2.11: Design Maintained Illuminance
(Courtesy: CIBSE Code of Interior Lighting – 1994)
| Task size and contrast | Task duration | Erro | risk |
| Are task | Are task | Is task | Is task | Do errors have | |
| details | details | undertaken | undertaken | unusually | |
Standardmaintainedilluminance(lux) | unusuallydifficult tosee? | unusuallyeasy tosee? | forunusuallylong time? | forunusuallyshort time? | seriousconsequencesfor people,plant orproduct? | Designmaintainedilluminance(lux) |
standardmaintainedilluminance(lux) | Task size andcontrast | Task durarion | Error risk |
Are taskdetailsunusuallydifficult tosee ? | Are task detailsunusually easy tosee ? | Is taskundertakenfor unusually long time? | Is task undertakenforunusuallyshort time? | Do errors haveunusuallyseriousconsequencesfor people,plant orproduct? | Designmaintainedilluminance(lux) |
200 | Yes | 200 | | 200 | Yes | 200 | Yes YesYes YesYesYesYes | 200 | YesYesYesYesYesYes YesYesYes | 200 250 300 400 500 600 750 900 1000 1300 1500 | 200 |
| | 250 | | 250 | Yes | 250 | 250 | 250 |
300 | Yes | 300 400 | Yes | 300 400 | YesYes | 300 400 | 300 400 | 300 400 |
500 | Yes | 500 | Yes | 500 | Yes | 500 | 500 | 500 |
| 600 | | 600 | Yes | 600 | 600 | 600 |
750 | Yes | 750 900 | Yes | 750 900 | Yes | 750 900 | 750 900 | 750 900 |
| | 1000 | | 1000 | Yes Yes | 1000 | 1000 | 1000 |
| | | | | | 1300 | | 1300 |
| | | | | | 1300 | | 1500 |
Limiting Glare Index
Generally, two types of glares are encountered in lighting applications and they are known as ‘Discomfort Glare’ and ‘Disability Glare’ (Please see the Annex 1 for definitions, Abbreviations and Acronyms)
Discomfort Glare is likely to be experienced when some part of the interior has much higher luminance/ brightness thanthat of the rest of the interior. This type of Glare can be estimated by ‘Glare Indices’ for which limiting values are given as ‘Limiting Glare Indices’ in the CIBSE Code of Interior Lighting – 1994. The contributory factor to such Glare is averageluminance/ brightness in the field of view, position of the glare source and subtended angle of the glare source from the lineof vision.
Disability Glare is generally experienced where a source of high luminance, brightness lies close to a task. In this case, the light from the source will be scattered in the eye across the retinal image of the task. The effect of this scattered
light is to reduce the contrast of the task and to change the local state of adaptation of the retina. Furthermore, the retinal imageof the source with high Luminance/ brightness will induce changes in the operating state of the surrounding retinal area. Thenet effect of these changes is to reduce the visibility of the task which is known as ‘Disability Glare’.
Good general practices in selection of appropriate illuminance levels, luminaires and window blinds, correct positioningof light sources and minimising of shiny colours/ surfaces in the interior can generally eliminate both forms of glare.
The detail method for calculating Glare Indices is given in ‘Annex – 02 section 2 (Courtesy: CIBSE Guide TM 10)
For specific applications where particular illumination level to be achieved will be critical, target ranges given for InstalledPower density in the CIBSE Code of Interior Lighting- 1994 shall be used.
Table 2.12: Installed Power Density
(Courtesy: CIBSE Code of Interior Lighting – 1994)
Lamp type | Wattagerange usedto calculatetarget ranges | CIEcolourrenderinggroup | Luminairemaintenancecategories(see Table4.5, page 153, and section 3.3.2) | Workingplane powerdensityrange(W/m2/100lux) |
Room index |
K=1 | K=2.5 | K=5 |
(a) High bay industrial –reflectance C,W,F= 0.5,0.5,0.2 to 0.3,0.3,0.1 |
Metal halide | | | | | | |
clear orcoated | 250-400 | 2 | B,C,E | 2.6-4.5 | 2.1-3.6 | 2.0-3.4 |
Highpressuremercury-coated | 250-400 | 3 | B,C,E | 4.2-6.2 | 3.5-5.1 | 3.3-4.8 |
Highpressure sodiumimprovedcolour | -250-400 | 3 | B,C,E | 2.4-3.6 | 2.0-2.9 | 1.9-2.8 |
Standard or highefficiency | -250-1000 | 4 | B,C,E | 1.4-2.7 | 1.2-2.2 | 1.1-2.1 |
(b) Industrial – reflectance C,W,F= 0.7,0.5,0.2 to 0.3,0.5,0.2
Fluorescent |
triphosper | 32-100 | 1b | B,C,E | 2.5-4.9 | 1.9-3.5 | 1.6-2.9 |
halophospate | 32-100 | 2-3 | B,C,E | 3.2-6.3 | 2.4-4.5 | 2.1-3.7 |
Metalhalide clearor coated | 150-400 | 2 | B,C,E | 2.9-6.8 | 2.3-4.4 | 2.1-3.9 |
High pressure mercury-coated | 125-400 | 3 | B,C,E | 4.8-9.4 | 3.7-6.1 | 3.5-5.5 |
High pressure sodiumimprovedcolour | 150-400 | 3 | B,C,E | 2.7-5.5 | 2.1-3.5 | 2.0-3.2 |
standard or high efficiency | 100-400 | 4 | B,C,E | 1.8-4.7 | 1.3-3.0 | 1.3-2.7 |
( c) Commercial- reflectance C,W,F= 0.7,0.5,0.2 to 0.5,0.5,0.2
Fluorescent |
-triphosper | 32-100 | 1b | A,B,C,D,E | 2.7-5.4 | 2.2-4.2 | 2.1-3.7 |
-halophospate | 32-100 | 2-3 | A,B,C,D,E | 3.4-7.0 | 2.8-5.4 | 2.6-4.8 |
-compact Metal halide | 36-55 | 1b | A,B,C,D,E | 3.3-6.4 | 2.8-4.9 | 2.6-4.4 |
-clear orcoated | 150-400 | 2 | B,C | 4.4-7.1 | 3.6-5.7 | 3.4-5.3 |
High pressure mercury-coated | 125-400 | 3 | B,C | 6.6-9.9 | 5.4-7.9 | 5.1-7.3 |
Highpressuresodium | | | | | | |
improvedcolour | 150-400 | 3 | B,C | 3.8-5.8 | 3.1-4.6 | 2.9-4.3 |
standard or high efficiency | 100-400 | 4 | B,C | 2.4-4.9 | 2.0-3.9 | 1.9-3.6 |
5 Lighting Control Credits
To encourage the use of lighting controls beyond the mandatory switching requirements of Section 2.21.2, the connectedlighting power within a building may be adjusted to take credit for the benefits of certain types of automatic lighting controls.The lighting control credit is a multiplier that reduces the amount of energy used for lighting, giving a lower adjusted lighting power. In order to qualify for a lighting power density reduction, the control device must control all of the fixtures for which the credit is claimed.At least 50 % of the light output of the controlled luminaire must fall within the applicable type of space listed in Table 2.13.The list of the type of lightingcontrols that qualify for these credits is shown in Table 2.14.
Table 2.13: Power Credits for Certain Types of Lighting Controls
Type of Control | Type of Space | Factor |
OccupantSensor (withseparatesensor foreach space) | Any space < or = 23 m2enclosed by ceiling to floorpartitions: any sizeclassroom, corridor,conference or waiting room | 0.20 |
Rooms of any size that are used exclusively for storage 0.60 |
Rooms > 23 m2 | | 0.10 |
Automatic TimeSwitch ControlDevice | Room < or = 23 m2 andwith a timed manualoverride at each switchlocation and controllingonly the lights in the areaenclosed by ceiling-heightpartitions | 0.05 |
Table 2.14: Power Credits for Automatic Daylighting Controls
GlazingProperties | Stepped DimmingControls | Continuous Dimming Controls |
WWR < 20% | WWR 20% to40% | WWR > 40% | WWR < 20% | WWR 20% to 40% | WWR > 40% |
VLT 60% | 0.20 | 0.30 | 0.40 | 0.30 | 0.40 | 0.40 |
VLT 35 and <60% | 0 | 0.20 | 0.30 | 0 | 0.30 | 0.40 |
VLT< 35% | 0 | 0 | 0.20 | 0 | 0 | 0.40 |
The lighting control credits listed in Tables
2.13 and 2.14 have the effect of reducing the actual lighting power for those portions of the building where the credit applies by the amount listed in the respective tables. The credits therefore make it easier to meet the allowed lightingpower requirement.
In order to qualify power savings adjustments, the control system or device must control all of the fixtures in the areas for which the credit is claimed. At least 50 % of the light output of the controlled luminaire must fall within the applicable space listed in the table. Credits should not be combined.
Annex 3: Ventilation & Air Conditioning
Piping Insulation
PipingSystemType | Fluid TempRange (°C) | Insulation Thickness for Nominal Pipe Sizes (mm) |
Run outs Up to 50 mm | 25 mmand less | 32 mm to 50 mm | 63 mm&above |
ChilledWater | 4.5-13 | 13 | 13 | 25 | 38 |
Refrigerantor Brine | Below 4.5 | 25 | 25 | 38 | 50 |
Notes: 1. The insulation thickness is based on insulation having thermal resistance inthe range of 28 to 32 m² K/W per metre of thickness on a flat surface at a meantemperature of 24° C. See 3.8.2 and 3.8.3 for insulation materials with thermal resistance outside thisrange. 2. These thicknesses are based on energy efficiency considerations only.Issues such as water vapor permeability or surface condensation mayrequire vapor retarders or additional insulation. |
Chilled Water Piping. For material with thermal resistance greater than 32 m² K/W per metre of thickness, the minimum insulation thickness, t (mm), is given by:
28 X Thickness in Table 3-1
t =
Actual R Value
Chilled Water Piping. For material with thermal resistance less than 28 m² K/W per metre of thickness, the minimum insulation thickness, t (mm), is given by:
32 X Thickness in Table 3-1
t = Actual R Value
Air Handling System Insulation and Ducts
Thermal Resistance Requirement. The minimum thermal resistance, R (m2K/W), of the insulation, excluding filmresistance shall be:
5T
R = 47.3
wherein 5T = design temperature differential between the air in the duct and the surrounding air, measured in Kelvin.
Air Handling System Ducts
Table 3.2: Minimum Duct Seal Level
Duct Location | DuctType | |
| Supply | Exhaust | Return |
< 500 Paa | ≥500 Paa |
Outside Conditioned Space | 1 | 1 | none | 1 |
Unconditioned Spaces | 2 | 1 | none | 3 |
Indirectly ConditionedSpacesb | 3 | 2 | 3 | none |
Cooled Spaces | None | 3c | 3c | none |
a Duct design static pressure classification. Unless otherwise shown indesign documents, ductwork between the supply fan and variable air volumeboxes shall be considered 500 Pa pressure classification, while all otherductwork of any application shall be considered 250 Pa pressureclassification. b Includes return-air plenums. c Ducts within the conditioned space to which they supply air or from whichthey exhaust air need not be sealed. |
Seal levels: - All joints, longitudinal seams, and at all duct wallpenetrations. Pressure-sensitive tape shall not beused as the primary sealant.
- All joints and longitudinal seams. Pressure-sensitive tape shall not be used as the primary sealant.
- Transverse joints only.
|
Definitions: Longitudinal seams are joints oriented in the direction of theairflow. Transverse joints are connections of two duct sections oriented perpendicular to theairflow. Duct wall penetrations are openings made by any screw or fastener.Spiral lock joints in round and flat- oval ducts need not be sealed. All otherconnections are considered joints, including but not limited to spin-ins,lateral taps and other branch connections, access door frames and jambs,duct connections to equipment, etc. |
Comfort Zone Diagram
Dew point/T diagram showing the comfort zone according to ASHRAE 55-1992
20 15
15
10
10
5
5
0
-5
-10
0
15 20 25 30
DRY BULB TEMPERATURE 0C
Annex 4: Building Envelope
- Appendix 4a
Where the terms are defined as:
OTTVi = overall thermal
transmittance value for the
ith specific wall orientation and construction combination, (W/m2)
Teq = equivalent indoor-outdoor
temperature difference
through the opaque wall section, (19.3°C)
= solar absorptance of the exterior opaque wall (dimensionless)
WWR = window-to-wall ratio, using
the gross wall area in the denominator, (dimensionless).
Uw = thermal transmittance of opaque wall
T | = | temperature difference | | | through the window | Uf | = | section, (3.6°C) thermal transmittance of |
| |
section, (W/m
2°C)
window section, (W/ m2°C)
SF = solar factor, defined as the average hourly value of solar energy incident on vertical windows, (186 W/m2)
SC = shading coefficient of the fenestration system as given in Section Annex
4d, (dimensionless)
CF = solar correction factor for the orientation of the fenestration
- Appendix 4b
Table of Thermal Properties of Typical Construction Material for Estimating U-values for facades. (Source: ASHRAE Fundamentals Handbook)
- Appendix 4c
Solar Correction Factor for Fenestrations (CF)
Table 4.1: Solar Correction Factors (CF) (dimensionless)
South | North | East | West | SE | NE | SW | NW |
0.95 | 0.79 | 1.34 | 0.90 | 1.15 | 1.07 | 0.93 | 0.85 |
| | | | | | | | | |
46
- Appendix 4d
Combined Shading Coefficients (SC)
Table 4.2: Shading Coefficient (SC) for Horizontal Overhang Projections
| Orientation |
R1 | South | North | East | West | SE | NE | SW | N W |
0.2 | 0.69 | 0.77 | 0.80 | 0.76 | 0.75 | 0.79 | 0.72 | 0.76 |
0.4 | 0.53 | 0.68 | 0.68 | 0.59 | 0.61 | 0.68 | 0.56 | 0.64 |
0.6 | 0.45 | 0.63 | 0.58 | 0.50 | 0.52 | 0.61 | 0.47 | 0.56 |
0.8 | 0.39 | 0.59 | 0.50 | 0.43 | 0.45 | 0.54 | 0.41 | 0.51 |
1.0 | 0.37 | 0.56 | 0.43 | 0.40 | 0.40 | 0.50 | 0.38 | 0.48 |
1.2 | 0.36 | 0.54 | 0.39 | 0.37 | 0.37 | 0.46 | 0.36 | 0.46 |
1.4 | 0.35 | 0.53 | 0.35 | 0.36 | 0.35 | 0.44 | 0.35 | 0.44 |
1.6 | 0.34 | 0.52 | 0.32 | 0.35 | 0.33 | 0.42 | 0.34 | 0.43 |
1.8 | 0.33 | 0.51 | 0.29 | 0.34 | 0.31 | 0.40 | 0.34 | 0.42 |
2.0 | 0.33 | 0.50 | 0.27 | 0.33 | 0.30 | 0.38 | 0.33 | 0.42 |
Table 4.3: Shading Coefficient (SC) for Vertical Side-Fin Projections
| Orientation |
R2 | South | North | East | West | SE | NE | SW | NW |
0.2 | 0.80 | 0.80 | 0.87 | 0.84 | 0.83 | 0.83 | 0.82 | 0.82 |
0.4 | 0.75 | 0.75 | 0.83 | 0.79 | 0.79 | 0.79 | 0.77 | 0.77 |
0.6 | 0.71 | 0.70 | 0.79 | 0.75 | 0.75 | 0.75 | 0.73 | 0.73 |
0.8 | 0.69 | 0.68 | 0.77 | 0.73 | 0.73 | 0.73 | 0.71 | 0.71 |
1.0 | 0.67 | 0.66 | 0.75 | 0.71 | 0.71 | 0.71 | 0.69 | 0.68 |
1.2 | 0.67 | 0.66 | 0.75 | 0.71 | 0.71 | 0.70 | 0.69 | 0.68 |
1.4 | 0.66 | 0.64 | 0.74 | 0.70 | 0.70 | 0.69 | 0.68 | 0.67 |
1.6 | 0.66 | 0.64 | 0.73 | 0.70 | 0.70 | 0.69 | 0.68 | 0.67 |
1.8 | 0.66 | 0.64 | 0.73 | 0.69 | 0.69 | 0.68 | 0.67 | 0.67 |
2.0 | 0.65 | 0.63 | 0.72 | 0.69 | 0.69 | 0.68 | 0.67 | 0.66 |
47
Table 4.4: Shading Coefficient (SC) for Horizontal & Vertical “Egg-Crate” Projections
| Orientation |
R1 | R2 | South | North | East | West | SE | NE | SW | NW |
0.2 | 0.2 | 0.52 | 0.60 | 0.72 | 0.62 | 0.62 | 0.66 | 0.57 | 0.61 |
0.2 | 0.4 | 0.31 | 0.46 | 0.53 | 0.41 | 0.42 | 0.49 | 0.36 | 0.44 |
0.2 | 0.6 | 0.21 | 0.36 | 0.40 | 0.27 | 0.31 | 0.38 | 0.24 | 0.32 |
0.2 | 0.8 | 0.17 | 0.30 | 0.28 | 0.18 | 0.23 | 0.29 | 0.18 | 0.24 |
0.2 | 1.0 | 0.13 | 0.25 | 0.18 | 0.13 | 0.15 | 0.22 | 0.13 | 0.19 |
0.4 | 0.2 | 0.48 | 0.55 | 0.65 | 0.58 | 0.56 | 0.60 | 0.53 | 0.56 |
0.4 | 0.4 | 0.27 | 0.42 | 0.50 | 0.37 | 0.38 | 0.46 | 0.32 | 0.39 |
0.4 | 0.6 | 0.20 | 0.34 | 0.37 | 0.25 | 0.28 | 0.36 | 0.23 | 0.30 |
0.4 | 0.8 | 0.15 | 0.28 | 0.26 | 0.16 | 0.20 | 0.27 | 0.15 | 0.22 |
0.4 | 1.0 | 0.22 | 0.37 | 0.30 | 0.23 | 0.26 | 0.34 | 0.23 | 0.30 |
0.6 | 0.2 | 0.43 | 0.50 | 0.62 | 0.53 | 0.53 | 0.56 | 0.48 | 0.52 |
0.6 | 0.4 | 0.25 | 0.40 | 0.47 | 0.35 | 0.36 | 0.43 | 0.30 | 0.37 |
0.6 | 0.6 | 0.18 | 0.31 | 0.35 | 0.23 | 0.26 | 0.33 | 0.20 | 0.27 |
0.6 | 0.8 | 0.24 | 0.39 | 0.34 | 0.26 | 0.29 | 0.37 | 0.25 | 0.32 |
0.6 | 1.0 | 0.18 | 0.32 | 0.23 | 0.19 | 0.21 | 0.28 | 0.19 | 0.26 |
0.8 | 0.2 | 0.42 | 0.48 | 0.60 | 0.52 | 0.51 | 0.54 | 0.47 | 0.50 |
0.8 | 0.4 | 0.23 | 0.37 | 0.44 | 0.33 | 0.34 | 0.41 | 0.28 | 0.35 |
0.8 | 0.6 | 0.26 | 0.42 | 0.41 | 0.28 | 0.34 | 0.42 | 0.27 | 0.35 |
0.8 | 0.8 | 0.20 | 0.34 | 0.28 | 0.21 | 0.24 | 0.31 | 0.21 | 0.28 |
0.8 | 1.0 | 0.15 | 0.27 | 0.20 | 0.15 | 0.17 | 0.24 | 0.15 | 0.21 |
1.0 | 0.2 | 0.40 | 0.45 | 0.58 | 0.49 | 0.49 | 0.52 | 0.44 | 0.47 |
1.0 | 0.4 | 0.29 | 0.46 | 0.50 | 0.35 | 0.39 | 0.48 | 0.32 | 0.40 |
1.0 | 0.6 | 0.22 | 0.37 | 0.35 | 0.24 | 0.28 | 0.36 | 0.23 | 0.31 |
1.0 | 0.8 | 0.16 | 0.29 | 0.24 | 0.17 | 0.20 | 0.27 | 0.17 | 0.23 |
1.0 | 1.0 | 0.13 | 0.25 | 0.17 | 0.13 | 0.15 | 0.21 | 0.13 | 0.19 |
1.2 | 0.2 | 0.36 | 0.51 | 0.60 | 0.45 | 0.48 | 0.55 | 0.41 | 0.48 |
1.2 | 0.4 | 0.25 | 0.41 | 0.43 | 0.31 | 0.34 | 0.42 | 0.28 | 0.36 |
1.2 | 0.6 | 0.18 | 0.32 | 0.32 | 0.20 | 0.25 | 0.32 | 0.19 | 0.26 |
1.2 | 0.8 | 0.15 | 0.28 | 0.21 | 0.16 | 0.18 | 0.24 | 0.15 | 0.22 |
1.2 | 1.0 | 0.11 | 0.22 | 0.13 | 0.11 | 0.12 | 0.18 | 0.11 | 0.17 |
48
Annex 5: Electrical Power and Distribution
5.4.6 Motor Rewinding: Motor users should insist on proper rewinding practices for rewound motors. If the following practices cannot be assured, the damaged motor should be replaced with a new, efficient one rather than suffer the significant efficiency penalty associated with typical rewind practices. Wherever possible, the following practices (taken from“Guidelines for Maintaining Motor Efficiency During Rebuilding”, Electrical Apparatus Service Association, St. Louis, MO,USA) should be followed for rewinding:
(a) Conduct a stator-core loss test before and after stripping.
(b) Repair or replace defective laminations.
(c) Calibrate all test equipment and measuring devices at least annually against standards traceable to the NationalStandard.
(d) Measure and record winding resistance and room temperature.
(e) Measure and record no-load amps and voltage during the final test to measure efficiency.
(f) ) Have a quality assurance program.
(g) Haveanduse,ataminimum,thefollowing test equipment; ammeter, voltmeter, wattmeter, ohmmeter, megohmmeter, and high potential tester.
(h) Have a three-phase power supply for running motors at rated voltage.
(i) Balance the rotor.
(j) Do not heat stators above 3500C.
(k) Do not sandblast the iron core.
(l) Do not knurl, peen, or paint bearing fits.
(m) Do not use an open flame for stripping.
(n) Do not grind the laminations or file the slots.
(o) Do not increase the air gap.
(p) Do not increase the resistance of the windings.
(q) Do not make mechanical modifications without the customer’s prior approval.
This includes but is not limited to changing fans, types of bearings, shaft material, and seals.
(r) Do not change the winding design.
Annex 6: Service Water Heating
Table 6.1: Minimum Pipe Insulation Thicknesses for Service Hot Water Systems
| Minimum Pipe Insulation Thickness (in.) |
Conductivity at 100 ° F 0.24 to 0.28 [Btu-in/(h-ft2- ° F)](type of closed-cell foam or high performance rigid preshapedfiberglass) |
Nominal Pipe Diameter Runouts up to 2 in. (<12 ft length) | 0.5 |
2 in. and less | 1.0 |
2.5 in. and larger | 1.5 |
49
Sri Lanka Sustainable Energy Authority 3G-4A,BMICH, Bauddahloka Mawatha,
Colombo 07, Sri Lanka.
E-mail: [email protected] / web: www.energy.gov.lk TP: +94(0)112677445 / Fax: +94(0)11 2682534