No | Name of the action | Completion form | Responsible for execution | Timeline | Estimated costs, mln. tenge | Sources of financing |
1 | 2 | 3 | 4 | 5 | 6 | 7 |
1. Adoption of measures promoting the use of renewable energy sources |
1. | To ensure the development and implementation of measures which should raise extra investment for the renewable energy projects | Information in Ministry of Environment and water resources | Akims of regions, cities of Almaty and Astana | 2013 - 2020 | Not required |
|
2. | To conduct an audit of land plots allocated for construction of the renewable energy facilities without any construction activities | Information in Ministry of Environment and water resources | Akims of regions, cities of Almaty and Astana | September 2013 | Not required |
|
3. | Consider withdrawal of unused land plots allocated for the construction of the renewable energy facilities | Information in Ministry of Environment and water resources | Akims of regions, cities of Almaty and Astana | 4th quarter of 2013 | Not required |
|
4. | To develop technical requirements and criteria for the grid connection of renewable energy facilities | Information in the Government of Kazakhstan | Ministry of Industry and New Technologies of the Republic of Kazakhstan, JSC "KEGOC" (in coordination) | 4th quarter of 2013 | Not required |
|
5. | Identify promising areas for allocation of the renewable energy facilities | Information in Ministry of Environment and water resources | Akims of regions, cities of Almaty and Astana | June, 2013 | Not required |
|
6. | To improve the allocation plan for the renewable energy facilities | Information in the Government of Kazakhstan | Ministry of Environment and water resources, Ministry of Industry and New Technologies of the Republic of Kazakhstan | June, 2014 | Not required |
|
7. | Develop action plans promoting alternative and renewable energy of regions, cities of Astana and Almaty for 2013 - 2020 | Maslikhats’ decisions | Akims of regions, cities of Almaty and Astana | 3d quarter of 2013 | Not required |
|
2. Development of researches and experts in renewable energy |
8. | To carry over for consideration the issue of feasibility of the Center of electric power and energy efficiency | Information in the Government of Kazakhstan | Ministry of Industry and New Technologies of the Republic of Kazakhstan, the Ministry of Finance of the Republic of Kazakhstan, the Agency for Protection of Competition of the Republic of Kazakhstan | September,2013 | Not required |
|
9. | To suggest budgeting appointment for the development of interactive maps (atlas) of the Republic of Kazakhstan by types of renewable energy (solar, hydro, geothermal) | Information in the Government of Kazakhstan | Ministry of Environment and water resources, Ministry of Industry and New Technologies of the Republic of Kazakhstan, Republican State Enterprise "Kazhydromet" (in coordination), JSC "National Scientific and Technological Holding "Parasat" (in coordination) | June, 2014 | Not required |
|
10. | Train staff in the energy sector | Information in the Ministry of Industry and New Technologies of the Republic of Kazakhstan | Ministry of Education and Science of the Republic of Kazakhstan | October, annually | Not required |
|
3. Local Development |
11. | To carry over for consideration on the meetings of Technology Policy Council issues of projects aimed to develop the production of alternative and renewable energy sources on the basis of scientific developments | Minutes of the Technology Policy Council | Ministry of Industry and New Technologies of the Republic of Kazakhstan, Ministry of Education and Science of the Republic of Kazakhstan, JSC "National Scientific and Technological Holding "Parasat" (in coordination) | 4th quarter of 2013 | Not required |
|
12. | To establish mass production of wind power plants with a capacity of up to 2 kW in the West Kazakhstan region | production output | Akimat of the West Kazakhstan region, Limited Liability Partnership "Zapadenergoprom" (in coordination) | 2013 | 2 000 | Own funds and loans |
13. | Make proposals for the introduction of technology of advanced materials in the production and maintenance of equipment and components for power generating from the renewable energy sources in order to reduce the costs of their construction and enhance the efficiency of functioning | Information in the Government of Kazakhstan | Ministry of Environment and water resources, Ministry of Industry and New Technologies of the Republic of Kazakhstan, JSC "Zhasyl damu" (in coordination) | 4th quarter of 2013 | Not required |
|
14. | Make proposals for the development of technologies, expansion of production and the use of new fuels produced from various types of biomass and waste | Information in the Government of Kazakhstan | Ministry of Environment and water resources, Ministry of Industry and New Technologies of the Republic of Kazakhstan, JSC "Zhasyl damu" (in coordination) | 4th quarter of 2013 | Not required |
|
15. | Make proposals for a target public procurement for scientific and technical programs for renewable energy | Information in the Government of Kazakhstan | Ministry of Environment and water resources, Ministry of Industry and New Technologies of the Republic of Kazakhstan, JSC "Zhasyl damu" (in coordination) | 4th quarter of 2013 | Not required |
|
4. Information development of renewable energy sources |
16. | Monitor the achievement of the targets, including periodic updating based on the priorities of the economic, energy and environmental policies and development dynamics through the use of renewable energy sources | Information in the Government of Kazakhstan | Ministry of Environment and water resources, Ministry of Industry and New Technologies of the Republic of Kazakhstan, JSC "FNB "Samruk-Kazyna" (in coordination), JSC "KEGOC" (in coordination) | 2013 - 2020 | Not required |
|
17. | Provide information support on activities carried out within the framework of the development of renewable energy sources | Information in the Government of Kazakhstan | Ministry of Environment and water resources, Agency for Communication and Information of the Republic of Kazakhstan, Akims of regions, cities of Almaty and Astana | 2013 - 2020 | Not required |
|
18. | Develop regional information illustrated guides for investors with potential allocation of objects using renewable energy sources (updated regularly) | Guide | Akims of regions, cities of Almaty and Astana, JSC "FNB "Samruk-Kazyna" (in coordination) | September, 2013 | requires clarification | MB |
19. | Develop an informational guide for investors | Guide | Ministry of Environment and water resources, Ministry of Industry and New Technologies of the Republic of Kazakhstan | 2014 | Not required |
|
20. | Submit proposals ensuring the spread of knowledge on the use of renewable energy sources and training of specialists in construction and operation of renewable energy power plants | Information in the Government of Kazakhstan | Ministry of Education and Science of the Republic of Kazakhstan, Ministry of Environment and water resources, Ministry of Industry and New Technologies of the Republic of Kazakhstan | 2013-2020 | Not required |
|
21. | Submit proposals on technical maintenance of all stations of Republican State Enterprise "Kazgidromet" with the measurers of solar radiation and wind speed meters, as well as the with the communication facilities for data transmitting | Information in the Government of Kazakhstan | Ministry of Environment and water resources | 3d quarter of 2013 | Not required |
|
22. | Submit proposals on the establishment of the Center of monitoring and analysis of data from meteorological stations for the purpose of updating the maps/atlases of wind and solar energy | Information in the Government of Kazakhstan | Ministry of Environment and water resources | 3d quarter of 2013 | Not required |
|
5. Renewable Energy Projects |
By 2020 it is planned to put into operation about 106 renewable energy facilities with a total capacity of 3054.55 MW, including: 34 wind farms - 1787 MW; 41 hydropower stations - 539 MW; 28 solar power stations - 713.5 MW; 3 biofuel stations - 15,05 MW |
23. | Construction of a wind farm near Ereymentau – a town in Ereymentau District of Akmola Region with the capacity of 45 MW | put into operation | Akim of Akmola Region, JSC "Samruk Energo" (in coordination) | 2014 | 17 709 | Investor’s own funds and loans |
24. | Construction of a wind farm near Ereymentau – a town in Ereymentau District of Akmola Region with the capacity of 50 MW | put into operation | Akim of Akmola Region, Limited Liability Partnership "Samruk Green Energy" (in coordination) | 2016 | 19 700 | Investor’s own funds and loans |
25. | Construction of a wind farm near Ereymentau – a town in Ereymentau District of Akmola Region with the capacity of 50 MW | put into operation | Akim of Akmola Region, "Chevron Munaigas Inc" (in coordination) | 2017 | 30 000 | Investor’s own funds and loans |
26. | Construction of a wind farm in the village Badamsha in Kargaly District of Aktobe Region with the capacity of 48 MW | put into operation | Akim of Aktobe Region, Limited Liability Partnership "Arm wind" (in coordination) | 2018 | 16 000 | Investor’s own funds and loans |
27. | Construction of a wind farm in Kargaly District of Aktobe Region with the capacity of 100 MW | put into operation | Akim of Aktobe Region, Limited Liability Partnership "SB Capital" (in coordination) | 2018 | 36 400 | Investor’s own funds and loans |
28. | Construction of a wind farm in Shelek corridor of Almaty Region, with the capacity of 51 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Green Energy Almaty" (in coordination) | 2015 | 12 881 | Investor’s own funds and loans |
29. | Construction of a wind farm in Shelek District of Almaty Region, with the capacity of 60 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Samruk Green Energy" (in coordination) | 2017 | 27 000 | Investor’s own funds and loans |
30. | Construction of a wind farm in Dzungarian Gate of Almaty Region, with the capacity of 72 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Ak Kuat" (in coordination) | 2018 | 15 000 | Investor’s own funds and loans |
31. | Construction of a wind farm in Dzungarian Gate в in Alakol District of Almaty Region with the capacity of 19,5 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "VES-Saykan" (in coordination) | 2015 | 5 725 | Investor’s own funds and loans |
32. | Construction of a wind farm in Atyrau Region with the capacity of 30 MW | put into operation | Akim of Atyrau Region, Limited Liability Partnership "ANTARES PLATINUM" (in coordination) | 2016 | 17 290 | Investor’s own funds and loans |
33. | Construction of a wind farm in settlement Karabatan of Atyrau Region with the capacity of 50 MW | put into operation | Akim of Atyrau Region, Greenfortis GmbH (in coordination) | 2016 | 24 035 | Investor’s own funds and loans |
34. | Construction of a windpark on Umysh mountain pass near the village Tainty of East Kazakhstan Region with the capacity of 24 MW | put into operation | Akim of East Kazakhstan Region, Limited Liability Partnership "SpainConsulting" (in coordination) | 2016 | 8 084 | Investor’s own funds and loans |
35. | Construction of Korday wind farm in Jambyl Region with the capacity of 21 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Vista International" (in coordination) | 2016 | 5 451 | Investor’s own funds and loans |
36. | Construction of Janatas wind farm in Sarysu District of Jambyl Region with the capacity of 100 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Central Asia Green Power" (in coordination) | 2017 | 28 500 | Investor’s own funds and loans |
37. | Upgrade of the existing wind farm "К-1" expanding capacity from 1,5 MW in Korday District of Jambyl Region up to 18 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Izen-Su" (in coordination) | 2017 | 4 912 | Investor’s own funds and loans |
38. | Construction of Shoklar 2 wind farm in Jambyl Region with the capacity of 250 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Windhan" (in coordination) | 2017 | 56 056 | Investor’s own funds and loans |
39. | Construction of "Baydibek-1" wind farm with the capacity of 120 MW in Jambyl Region | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Creative and Production Company "NAR" (in coordination) | 2017 | 68 765 | Investor’s own funds and loans |
40. | Construction of a wind farm in the village Gulshat in Aktogay District of Karaganda Region with the capacity of 50 MW | put into operation | Akim of Karaganda Region | 2016 | 20 000 | private investments |
41. | Construction of a wind farm in the site near the town Arkalyk of Kostanay Region with the capacity of 48 MW | put into operation | Akim of Kostanay Region, Limited Liability Partnership "KazWind Energy" (in coordination) | 2018 | 15 800 | Investor’s own funds and loans |
42. | Construction of a wind farm in the settlement Borovskoy of Mendykara is a District of Kostanay Region with the capacity of 30 MW | put into operation | Akim of Kostanay Region, Limited Liability Partnership "EcoWind Ltd" (in coordination) | 2016 | 16 088 | Investor’s own funds and loans |
43. | Construction of a wind farm in Aral District of Kyzylorda Region with the capacity of 10 MW | put into operation | Akim of Kyzylorda Region, Limited Liability Partnership "Global Energy Company" (in coordination) | 2015 | Under development and analysis | Investor’s own funds and loans |
44. | Construction of a wind farm in the town of Fort-Shevchenko of Mangistau Region with the capacity of 19,5 MW | put into operation | Akim of Mangistau Region, JSC "NK SPK "Kaspiy" (in coordination), Limited Liability Partnership "DMK-Ko" (in coordination) | 2016 | 5 625 | Investor’s own funds and loans |
45. | Construction of a wind farm in the town of Fort-Shevchenko of Mangistau Region with the capacity of 42 MW | put into operation | Akim of Mangistau Region, Limited Liability Partnership "South Wind Power" (in coordination) | 2015 | 15 000 | Investor’s own funds and loans |
46. | Construction of a wind farm in the town of Fort-Shevchenko of Mangistau Region with the capacity of 50 MW | put into operation | Akim of Mangistau Region, Limited Liability Partnership "Bogart" (in coordination) | 2017 | 18 000 | Investor’s own funds and loans |
47. | Construction of a wind farm in the village of Kuryk in Karakiya District of Mangistau Region with the capacity of 50 MW | put into operation | Akim of Mangistau Region, Limited Liability Partnership "Invest Green" (in coordination) | 2017 | Under development and analysis | Investor’s own funds and loans |
48. | Construction of a wind farm in Tupkaragan District of Mangistau Region with the capacity of 42 MW | put into operation | Akim of Mangistau Region, Limited Liability Partnership "SP "KT Redkometalnaya Kompaniya" (in coordination) | 2018 | Under development and analysis | Investor’s own funds and loans |
49. | Construction of a wind farm in the village of Novonikolskoye in Kyzylzhar District of North Kazakhstan Region with the capacity of 1,5 MW | put into operation | Akim of North Kazakhstan Region, КТ "Zenchenko & Co" (in coordination) | 2013 | 185 | Investor’s own funds and loans |
50. | Construction of a wind farm in the village of Novonikolskoye in Kyzylzhar District of North Kazakhstan Region with the capacity of 2 MW | put into operation | Akim of North Kazakhstan Region, КТ "Zenchenko & Co" (in coordination) | 2014 | 402,9 | Investor’s own funds and loans |
51. | Construction of a wind farm in Esil District of North Kazakhstan Region with the capacity of 50 MW | put into operation | Akim of North Kazakhstan Region, Limited Liability Partnership "KGCM Service" (in coordination) | 2017 | 16 000 | Investor’s own funds and loans |
52. | Construction of a wind farm in Taiynsha District of North Kazakhstan Region with the capacity of 35 MW | put into operation | Akim of North Kazakhstan Region, Limited Liability Partnership "MGP-UK" (in coordination) | 2017 | 11 950 | Investor’s own funds and loans |
53. | Construction of a wind farm in Baydibek District of South Kazakhstan Region with the capacity of 40 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Kazakhstan Utility Systems" (in coordination) | 2015 | Under development and analysis | Investor’s own funds and loans |
54. | Construction of a wind farm in Baydibek District of South Kazakhstan Region with the capacity of 50 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "SOVITEK Kazakhstan" (in coordination) | 2017 | Under development and analysis | Investor’s own funds and loans |
55. | Construction of a wind farm in the town of Kentau in South Kazakhstan Region with the capacity of 60 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Yuzhshakhtostroy" (in coordination) | 2017 | Under development and analysis | Investor’s own funds and loans |
56. | Construction of a wind farm in Saryagash District of South Kazakhstan Region with the capacity of 100 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "SB Capital" (in coordination) | 2017 | 36 400 | Investor’s own funds and loans |
57. | Construction of a hydropower station 1, 2 on the river Uzyn in Zhambyl District of Almaty Region with the total capacity of 9 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Aksuhydro" (in coordination) | 2014-2015 | 4 554 | Investor’s own funds and loans |
58. | Construction of a hydropower station 1, 2 on the river Koksu in Kerbulak District of Almaty Region with the total capacity of 42 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Datang-TT-Energy" (in coordination) | 2016 | 11 324 | Investor’s own funds and loans |
59. | Construction of a hydropower station on the river Aksu in Aksu District of Almaty Region with the capacity of 3,6 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Aksuhydro" (in coordination) | 2016 | 2 214 | Investor’s own funds and loans |
60. | Construction of a hydropower station-5 on the river Karatal in Eskeldi District of Almaty Region with the capacity of 5 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "ASPMK-519" (in coordination) | 2014 | 4 650 | Investor’s own funds and loans |
61. | Construction of Upper-Baskan hydropower station in Sarkand District of Almaty Region with the capacity of 4,35 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Alakol Power" (in coordination) | 2015 | 1 410 | Investor’s own funds and loans |
62. | Construction of Lower-Baskan hydropower station 1-3 in Sarkand District of Almaty Region with the capacity of 15 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Alt Energy" (in coordination) | 2015 | 5 589 | Investor’s own funds and loans |
63. | Construction of a hydropower station on the river Issyk in Enbekshikazakh District of Almaty Region with the capacity of 4,8 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Energiya Alemi" (in coordination) | 2015 | 876 | Investor’s own funds and loans |
64. | Construction of a hydropower station 2 on the river Lepsy in Sarkand District of Almaty Region with the capacity of 4,8 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Amanat-A" (in coordination) | 2015 | 1 029 | Investor’s own funds and loans |
65. | Construction of hydropower station 1, 2 on the Grand Almaty Chanel of Almaty Region with the total capacity of 12 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Kazhydrotechenergo" (in coordination) | 2015 | Under development and analysis | Investor’s own funds and loans |
66. | Construction of a hydropower station 19-22 on the river Shelek in Enbekshikazakh District of Almaty Region with the total capacity of 60,8 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Kazhydrotechenergo" (in coordination) | 2015 | Under development and analysis | Investor’s own funds and loans |
67. | Construction of a Tekess hydropower station 2 on the river Tekess in Raiymbek District of Almaty Region with the capacity of 3,3 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "KazHydroKaskad" (in coordination) | 2015 | 1 193,5 | Investor’s own funds and loans |
68. | Construction of Upper-Baskan hydropower station 2 on the river Baskan in Sarkand District of Almaty Region with the capacity of 4,35 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Baskan Power" (in coordination) | 2016 | 1 317,5 | Investor’s own funds and loans |
69. | Construction of Kerbulak hydropower station on the river Ile in Ile District of Almaty Region with the capacity of 33 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Samruk Green Energy" (in coordination) | 2016 | 10 850 | Investor’s own funds and loans |
70. | Construction of Tekess hydropower station 1,3 and 4 on the river Tekess in Raiymbek District of Almaty Region with the total capacity of 10,2 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "KazHydroKaskad" (in coordination) | 2016 | 3 394,5 | Investor’s own funds and loans |
71. | Construction of Bartogay hydropower station 27 and 28 on the river Shelek in Enbekshikazakh District of Almaty Region with the total capacity of 33,1 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Zharyk Su LTD" (in coordination) | 2016 | 11 036 | Investor’s own funds and loans |
72. | Construction of cascades hydropower station 1-5 on Kaskelen waterway of Almaty Region with the total capacity of 25 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Kazelectrosetstroy" (in coordination) | 2016 | 9 720 | Investor’s own funds and loans |
73. | Construction of Upper-Baskan hydropower station 3 on the river Baskan in Sarkand District of Almaty Region with the capacity of 5,2 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Baskan Power" (in coordination) | 2017 | 1 317,5 | Investor’s own funds and loans |
74. | Construction of Shelek hydropower station 29 on the river Shelek in Enbekshikazakh District of Almaty Region with the total capacity of 34,8 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Kazhydrotechenergo" (in coordination) | 2017 | 10 865,5 | Investor’s own funds and loans |
75. | Construction of Tekess hydropower station 5,6 and 7 on the river Tekess in Raiymbek District of Almaty Region with the total capacity of 11,3 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "KazHydroKaskad" (in coordination) | 2017 | 3 766,5 | Investor’s own funds and loans |
76. | Construction of Panfilov hydropower station 1-4 on the river Usek in Panfilov District of Almaty Region with the total capacity of 25,6 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "National Energy Company "Zharyk Energo" (in coordination) | 2018 | 7 750 | Investor’s own funds and loans |
77. | Construction of Turgusun hydropower station on the river Turgusun in Zyryan District of East Kazakhstan Region with the capacity of 24,9 MW | put into operation | Akim of East Kazakhstan Region, Limited Liability Partnership "Turgusun-1" (in coordination) | 2016 | 7 719 | Investor’s own funds and loans |
78. | Construction of a hydropower station in Katonkaragay and Zyryan Districts of East Kazakhstan Region with the capacity of 27,1 MW | put into operation | Akim of East Kazakhstan Region, Limited Liability Partnership "EcoEnergy" (in coordination) | 2018 | 10 119 | Investor’s own funds and loans |
79. | Construction of a hydropower station on the river Kalzhir in Kurshim District of East Kazakhstan Region with the capacity of 19 MW | put into operation | Akim of East Kazakhstan Region, Limited Liability Partnership "Kalzhyrhydro" (in coordination) | 2016 | 16 380 | Investor’s own funds and loans |
80. | Construction of a hydropower station on the river Kedrovka in the town of Ridder of East Kazakhstan Region with the capacity of 24,8 MW | put into operation | Akim of East Kazakhstan Region, JSC "LIK" Group of Companies" (in coordination) | 2018 | 3 570 | Investor’s own funds and loans |
81. | Construction of a hydropower station in Zyryan District of East Kazakhstan Region with the capacity of 25,4 MW | put into operation | Akim of East Kazakhstan Region, Limited Liability Partnership "EcoEnergy" (in coordination) | 2019 | 10 628 | Investor’s own funds and loans |
82. | Construction of a hydropower station in Ulan District on the river Ablaketka of East Kazakhstan Region with the capacity of 3 MW | put into operation | Akim of East Kazakhstan Region, Limited Liability Partnership "AltayEnergoStroy" (in coordination) | 2018 | Under development and analysis | Investor’s own funds and loans |
83. | Construction of a hydropower station in Kurshim District on the river Kurshim of East Kazakhstan Region with the capacity of 3 MW | put into operation | Akim of East Kazakhstan Region, Limited Liability Partnership "AltayEnergoStroy" (in coordination) | 2016 | Under development and analysis | Investor’s own funds and loans |
84. | Construction of Karakystak hydropower station in Turar Ryskulov District of Jambyl Region with the capacity of 2,1 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Energo Story Project" (in coordination) | 2013 | 1018 | Investor’s own funds and loans |
85. | Construction of Tas-Otkel hydropower station in Shu District of Jambyl Region with the capacity of 9,2 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "A&T-Energo" (in coordination) | 2013 | 1 050 | Investor’s own funds and loans |
86. | Construction of cascades of Merki hydropower stations in Merki District of Jambyl Region with the capacity of 18 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Taraz Green Power Genco" (in coordination) | 2016 | 7 391 | Investor’s own funds and loans |
87. | Construction of Aksu hydropower station in Tole Bi District of South Kazakhstan Region with the capacity of 10 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Discovery-Energy" (in coordination) | 2014 | 6 820 | Investor’s own funds and loans |
88. | Construction of Mankent hydropower station in Sayram District of South Kazakhstan Region with the capacity of 2,5 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Aksu-Energo" (in coordination) | 2014 | 745 | Investor’s own funds and loans |
89. | Construction of a hydropower station in Ordabasy District of South Kazakhstan Region with the capacity of 0,5 MW | put into operation | Akim of South Kazakhstan Region, Owner-operated farm "Adilkhan" (in coordination) | 2014 | 100 | Investor’s own funds and loans |
90. | Construction of Ryszhan hydropower station on the river Keles in Saryagash District of South Kazakhstan Region with the capacity of 2 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Keleshydrostroy" (in coordination) | 2015 | 193 | Investor’s own funds and loans |
91. | Construction of Azamat hydropower station on the river Keles in Saryagash District of South Kazakhstan Region with the capacity of 3 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Keleshydrostroy" (in coordination) | 2016 | 315 | Investor’s own funds and loans |
92. | Construction of Darkhan hydropower station on the river Keles in Saryagash District of South Kazakhstan Region with the capacity of 2 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Keleshydrostroy" (in coordination) | 2015 | 200 | Investor’s own funds and loans |
93. | Construction of Shanyshkaly hydropower station on the river Keles in Saryagash District of South Kazakhstan Region with the capacity of 3 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Keleshydrostroy" (in coordination) | 2017 | Under development and analysis | Investor’s own funds and loans |
94. | Construction of Mamyt hydropower station on the river Keles in Saryagash District of South Kazakhstan Region with the capacity of 1,8 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Keleshydrostroy" (in coordination) | 2018 | Under development and analysis | Investor’s own funds and loans |
95. | Construction of Kiyat hydropower station on the river Keles in Saryagash District of South Kazakhstan Region with the capacity of 1,5 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Keleshydrostroy" (in coordination) | 2019 | Under development and analysis | Investor’s own funds and loans |
96. | Construction of Kelte-Mashat hydropower station in Tulkibas District of South Kazakhstan Region with the capacity of 3 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Seikhun" (in coordination) | 2019 | Under development and analysis | Investor’s own funds and loans |
97. | Construction of Sayram-su hydropower station in Tulkibas District of South Kazakhstan Region with the capacity of 6 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Seikhun" (in coordination) | 2019 | Under development and analysis | Investor’s own funds and loans |
98. | Construction of a solar power station in the town Kapchagay of Almaty Region with the capacity of 2 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Samruk Green Energy" (in coordination) | 2014 | 1 700 | Investor’s own funds and loans |
99. | Construction of a solar power station in Kapchagay District of Almaty Region with the capacity of 5 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Kun Kuaty" (in coordination) | 2016 | Under development and analysis | Investor’s own funds and loans |
100. | Construction of a solar power station in the town Kapchagay of Almaty Region with the capacity of 80 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "SE WS SOLAR KAZAKHSTAN" (in coordination) | 2018 | 33 000 | Investor’s own funds and loans |
101. | Construction of a solar power station in the village of Kazybek of Zhambyl District of Almaty Region with the capacity of 25 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Promondis Kazakhstan" (in coordination), JSC "NK "SPK "Zhetysu" (in coordination) | 2015 | Under development and analysis | Investor’s own funds and loans |
102. | Construction of a solar power station in the village of Kairat of Talgar District of Almaty Region with the capacity of 5 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Zhetisu Solar Power", JSC "NK "SPK "Zhetysu" (in coordination) | 2015 | 4 620 | Investor’s own funds and loans |
103. | Construction of a solar power station in Uygur District of Almaty Region with the capacity of 5 MW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Energiya Alemi" (in coordination) | 2016 | 4 320 | Investor’s own funds and loans |
104. | Construction of a solar power station in Atyrau Region with the capacity of 35 MW | put into operation | Akim of Atyrau Region, Limited Liability Partnership "Solar Kurylys" (in coordination) | 2015 | 12 740 | Investor’s own funds and loans |
105. | Construction of a solar power station in Atyrau Region with the capacity of 10 MW | put into operation | Akim of Atyrau Region, Limited Liability Partnership "Ekoprotek - Kulsary" (in coordination) | 2016 | Under development and analysis | Investor’s own funds and loans |
106 | Construction of a solar power station in Jambyl District of Jambyl Region with the capacity of 24 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Aquila Solar" (in coordination) | 2016 | 9 250 | Investor’s own funds and loans |
107 | Construction and expanding the existing solar power station Otar in мощностью 0,5 МВт in Korday District of Jambyl Region up to 7 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "KazEkoWatt" (in coordination) | 2015 | 2 002 | Investor’s own funds and loans |
108 | Construction of a solar power station in Shu District of Jambyl Region with the capacity of 10 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "A&T-Energo" (in coordination) | 2015 | Under development and analysis | Investor’s own funds and loans |
109 | Construction of a solar power station in Shu District of Jambyl Region with the capacity of 50 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Sun Solutions Kazakhstan" (in coordination) | 2017 | 18 000 | Investor’s own funds and loans |
110 | Construction of a solar power station "Taraz" in Jambyl Region with the capacity of 100 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Cogenhan" (in coordination) | 2017 | 20 000 | Investor’s own funds and loans |
111 | Construction of a solar power station "Burnoye" in Zhualy District of Jambyl Region with the capacity of 50 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Samruk-Kazyna Invest" (in coordination), United Green Company (in coordination), JSC "NK SPK "Taraz" (in coordination) | 2015 | 23 650 | Investor’s own funds and loans |
112 | Construction of a solar power station in the village of Gulshat in Aktogay District of Karaganda Region with the capacity of 40 MW | put into operation | Akim of Karaganda Region, Limited Liability Partnership "KPM-Delta" (in coordination) | 2016 | 15 000 | Private investments |
113 | Construction of a solar power station in Kyzylorda Region with the capacity of 50 MW | put into operation | Akim of Kyzylorda Region, Limited Liability Partnership "Samruk-Kazyna Invest" (in coordination), Social-Entrepreneurial Corporation SPK "Kyzyl-Orda" (in coordination) | 2016 | 20 905 | Investor’s own funds and loans |
114 | Construction of a solar power station in Zhalagash District of Kyzylorda Region with the capacity of 30 MW | put into operation | Akim of Kyzylorda Region, Limited Liability Partnership "Nomad Solar" (in coordination) | 2017 | Under development and analysis | Investor’s own funds and loans |
115 | Construction of a solar power station in the town of Aktau of Mangistau Region with the capacity of 5 MW | put into operation | Akim of Mangistau Region, Limited Liability Partnership "Best-Group NS" (in coordination) | 2016 | 4 620 | Investor’s own funds and loans |
116 | Construction of a solar power station in the town of Aktau of Mangistau Region with the capacity of 2 MW | put into operation | Akim of Mangistau Region, Limited Liability Partnership "Group Independent" (in coordination) | 2016 | Under development and analysis | Investor’s own funds and loans |
117 | Construction of a solar power station in Tupkaragan District of Mangistau Region with the capacity of 50 MW | put into operation | Akim of Mangistau Region, JSC "NK SPK "Kaspiy" (in coordination), "Pataki-Cahill Group" (in coordination) | 2018 | Under development and analysis | Investor’s own funds and loans |
118 | Construction of a solar power station in the town of Shymkent of South Kazakhstan Region with the capacity of 1 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Aksu-Energo" (in coordination) | 2014 | 1 200 | Investor’s own funds and loans |
119 | Construction of a solar power station near the village of Badam of Ordabasy District of South Kazakhstan Region with the capacity of 15 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Arman Engineering" (in coordination) | 2016 | 9 000 | Investor’s own funds and loans |
120 | Construction of a solar power station near the village of Zhuldyz of South Kazakhstan Region with the capacity of 28 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Arman Engineering" (in coordination) | 2016 | 11 000 | Investor’s own funds and loans |
121 | Construction of a solar power station in Baydibek District of South Kazakhstan Region with the capacity of 10 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Promondis Kazakhstan" (in coordination) | 2015 | 4 500 | Investor’s own funds and loans |
122 | Construction of a solar power station in Sayram District of South Kazakhstan Region with the capacity of 2,5 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Promondis Kazakhstan" (in coordination) | 2016 | 14 000 | Investor’s own funds and loans |
123 | Construction of a solar power station in Otyrar District of South Kazakhstan Region with the capacity of 20 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Promondis Kazakhstan" (in coordination) | 2016 | 9 000 | Investor’s own funds and loans |
124 | Construction of a solar power station in Tole Bi District of South Kazakhstan Region with the capacity of 10 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "DSTO Solar" (in coordination) | 2015 | 4 500 | Investor’s own funds and loans |
125 | Construction of a solar power station in Otyrar District of South Kazakhstan Region with the capacity of 15 MW | put into operation | Akim of South Kazakhstan Region, Limited Liability Partnership "Promondis Kazakhstan" (in coordination) | 2017 | 7 250 | Investor’s own funds and loans |
126 | Construction of the station of the combined production of electricity and thermal energy from biomass in the town of Kokshetau of Akmola Region with the capacity of 10 MW | put into operation | Akim of Akmola Region, Limited Liability Partnership "Samruk Green Energy" (in coordination) | 2017 | Under development and analysis | Investor’s own funds and loans |
127 | Construction of a bio power station in Enbekshikazakh District of Almaty Region with the capacity of 50 kW | put into operation | Akim of Almaty Region, Limited Liability Partnership "Energiya Alemi" (in coordination) | 2014 | 3, 85 | Investor’s own funds and loans |
128 | Gas utilization project from solid household waste in Jambyl Region with the capacity of 5 MW | put into operation | Akim of Jambyl Region, Limited Liability Partnership "Recowaste" (in coordination) | 2016 | 4 163 | private investments |