Meta Data
Draft: 
No
Revision of previous policy?: 
No
Draft Year: 
2009
Effective Start Year: 
2014
Scope: 
National
Document Type: 
Rule/Regulation
Economic Sector: 
Power, Other
Energy Types: 
Power, Other
Issued by: 
Government of New Zealand
Overall Summary: 
The National Environmental Standards for Electricity Transmission Activities (NES) are regulations made under the Resource Management Act 1991. The purpose of the NES is to minimise the cost to councils of implementing the National Policy Statement on Electricity Transmission (NPS); to ensure planning requirements are nationally consistent; to provide adequately for maintenance and upgrading of transmission lines to achieve the intention of the NPS minimise RMA processing costs and delays.---This is a reprint of the Resource Management (National Environmental Standards for Electricity Transmission Activities) Regulations 2009 that incorporates all the amendments to those regulations as at the date of the last amendment to them.
Environment
Pollution control action plans: 
A construction activity relating to an existing transmission line is a permitted activity if both of the conditions in subclauses (2) and (3) are complied with. Conditions (2)The noise from the construction activity must comply with New Zealand Standard NZS 6803:1999 Acoustics—Construction Noise. (3)The vibrations from the construction activity must comply with the peak particle velocity limits in table 1 of German Standard DIN 4150–3:1999 Structural Vibration—Effects of Vibration on Structures.
Land use change for energy production purposes: 
Trimming, felling, or removing any tree or vegetation, in relation to an existing transmission line, is a permitted activity if all of the applicable conditions in subclauses (2) to (6) are complied with. Conditions (2)Any tree or vegetation must not be trimmed, felled, or removed if— (a)a rule prohibits or restricts its trimming, felling, or removal (as the case may be); or (b)it is in a natural area. (3)Any tree or vegetation located on any land must not be felled or removed if a regional plan controls the use of the land for the purpose of—(a)soil conservation; or (b)avoiding or mitigating flooding. (4)Any tree or vegetation must not be trimmed, felled, or removed if it is on land administered by the Department of Conservation under the Conservation Act 1987 or an Act specified in Schedule 1 of that Act. (5)The felling or removal of any tree or vegetation must not create or contribute to— (a)instability of a slope or another land surface; or (b)erosion of the bed or bank of a water body or the coastal marine area. (6)Debris resulting from the trimming, felling, or removal must not enter a water body or the coastal marine area.---Trimming, felling, or removing any tree or vegetation, in relation to an existing transmission line, is a controlled activity if— (a)first,— (i)the condition in regulation 30(2) is breached because the tree or vegetation is in a natural area; but (ii)the trimming, felling, or removal is done to reduce the risk to a transmission line; and (b)second, all of the applicable conditions in regulation 30(3) to (6) are complied with.---Earthworks relating to an existing transmission line are a permitted activity if all of the conditions in subclauses (2) to (9) are complied with. [...] (3)Erosion sediment control must be applied and maintained at the site of earthworks, during and after the earthworks, to avoid the adverse effects of sediment on water bodies and the coastal marine area. (4)All areas of soil exposed by the earthworks must be stabilised against erosion as soon as practicable after the earthworks end to avoid the adverse effects of sediment on water bodies and the coastal marine area. (5)The earthworks must not create or contribute to—(a)instability or subsidence of a slope or another land surface; or (b)erosion of the bed or bank of a water body or the coastal marine area; or (c)drainage problems or flooding of overland flow paths. (6)Soil or debris from the earthworks must not be placed where it can enter a water body or the coastal marine area. (7)Earthworks must not be carried out on the bed of a lake or river or in the coastal marine area. (8)Earthworks must not be carried out in a historic heritage area unless they are carried out on an archaeological site in accordance with the Heritage New Zealand Pouhere Taonga Act 2014. (9)Earthworks must not be carried out on land that a local authority has identified as containing, or possibly containing, contaminants that pose a risk to the environment.