Meta Data
Draft: 
No
Revision of previous policy?: 
No
Effective Start Year: 
2017
Scope: 
National
Document Type: 
Rule/Regulation
Economic Sector: 
Power
Energy Types: 
All, Power, Renewable, Bioenergy, Hydropower
Issued by: 
Ministry of Energy and Mineral Resources
Notes: 
No official English version available. Google translate
Overall Summary: 
The Government Regulation No. 10/2017 on the Principles of Power Purchase Agreements (PPAs) outlines the principles of the PPAs, and the legal basis for the agreement between the State Utility (PT Perusahaan Listrik Negara (Persero) (PLN)) and Independent Power Producers (IPPs), covering three key areas: (a) the implementation of the BOOT (Build-Own-Operate-Transfer) business scheme; (b) a new risk sharing and allocation concept; (c) penalty mechanisms.
Renewable Energy
RE action plans: 
Article 2 [...] (2) Principles stipulated in the PPA to call (alternating) (1) Facilities for power generation, hydroelectric power plants, and biomass power plants. (3) For the points regulated in the PPA for intermittent new energy and renewable energy power plants, hydroelectric power plants under 10 MW (ten megawatts), biogas power plants, and municipal waste-based power stations are regulated under a Separate Ministerial Regulation.
Governance
Energy management principles: 
Article 4 (1) The PPA is carried out for a maximum period of 30 (thirty) years from the date of implementation of the COD. --- (3) PPA 9...] uses a cooperative pattern "Build, Own, Operate and Transfer" (Build, Own, Operate and Transfer / BOOT).