Meta Data
Draft: 
No
Revision of previous policy?: 
No
Effective Start Year: 
2011
Effective End Year: 
2015
Scope: 
National
Document Type: 
Programme, Government Report
Economic Sector: 
Power
Energy Types: 
Power, Renewable, Hydropower, Solar, Other
Issued by: 
Global Environment Facility (GEF) and Electricité du Laos
Overall Summary: 
The objectives of the second phase of the Global Environment Facility (GEF) Rural Electrification Project (REP II) for Lao People's Democratic Republic are to: a) increase access to electricity of rural households in villages of project provinces; and b) further improve the financial performance of Electricite du Laos. The activities for GEF support include improving Energy Efficiency (EE) in both the electricity supply and consumption, promoting adoption of renewable energy in the government's Rural Electrification (RE) program, and supporting project implementation.
Access
Bi-, multi-lateral mechanisms to expand access: 
While REP II was prepared as a blend of IDA and GEF finance, each was processed separately due to a delay in GEF allocations. The IDA US$20 million grant agreement was signed in February 2010, and the GEF US$1.818 million additional grant was signed in May 2011. A total of US$15.8 million in cofinancing from the consumers, the EdL, Energy Sector Management Assistance Program (ESMAP), International Finance Corporation (IFC), Norwegian Agency for Development Cooperation (NORAD), and the MEM was estimated at appraisal.
Energy access targets: 
A grid target of 37,000 households was subsequently approved with IFC co-financing, so 47,000 total connections (37,000 grid and 10,000 off-grid) were expected by completion. At completion, the number of connections was 47,255, corresponding to an estimated 248,000 people with access to electricity.11 A total of 37,614 households (196,000 people) were connected to the grid—including 16,010 households (75,000 people) through the P2P—and 9,641 households (52,000 people) were connected to off-grid sources. The P2P connection target was exceeded twofold. --- Attribution of grid connections to the project is supported by the intermediate indicator of distribution lines constructed, which was exceeded 85 percent (target: 1,209 km, actual value: 2,232 km). The total number of grid connections achieved through the project is equivalent to around 13 percent of all new grid connections in Lao PDR from 2010 to 2014. [...] REP II thus represents a major contribution to the early achievement of Lao PDR’s goal to electrify 80 percent of all households by 2015—a rate already met in 2012. The further goal to electrify 90 percent by 2020 is on track to be met in 2015.
Efficiency
EE priorities: 
The global environment objectives (GEOs), [...], were to (a) increase efficiency of energy supply by the EdL and consumption by consumers [...]
EE targets: 
GEO (a) to increase efficiency of energy supply by the EdL and consumption by consumers, was partially achieved, as demonstrated by the following two indicators [...]  ‘Measurable increase in awareness and adoption of EE technologies and practices by consumers’ (GEO Indicator 1) was achieved, with a narrower scope of outcome for awareness activities and a broader scope for adoption of EE technology and practices than the approved target values. Retrofitting of public buildings and distribution of efficient lamps to households and small businesses led to an estimated 9.2 GWh/year in energy savings (~0.3 percent of the 3,275 GWh sold to EdL customers in 2013).  ‘Reduction of the EdL’s distribution system loss’ (GEO Indicator 2) was not yet achieved by completion. The value at completion (measured per year) was 13.1 percent. This is higher than the original 13 percent maximum target value and the 11 percent target value subsequently approved with the GEF additional grant. The value at completion, however, is largely attributable to factors outside project activities.
Renewable Energy
RE priorities: 
The global environment objectives (GEOs), [...], were to [...] and (b) adopt substantial renewable energy in the government’s rural electrification program.
RE targets: 
Off-grid connections include the following:  SHSs [Solar Photovoltaic Home System] for 9,601 households (52,000 people) in use or being installed as of June 2015. About 10,000 SHSs were purchased and up to 100 percent installed during the project lifetime. The number in use or being installed was 96 percent at completion as some users returned systems once the grid arrived or due to O&M [operation and maintenance] issues. [..]  Village hydropower for about 40 households (226 people) in Houaphanh Province. Two 25 kW pico hydro stations, commissioned in June 2015, serve two villages (Pao Neua and Pao Tai) which have 5.7 people/house on average. --- GEO (b) to adopt substantial renewable energy in RE was exceeded, as demonstrated by ‘newly installed generation capacity’ (GEO Indicator 3). The value at completion was 310 kW, which exceeds the target value of 300 kW by 3 percent. The value at completion includes the single 260 kW biogas turbine on a pig farm in Vientiane Province and two 25 kW hydro stations for villages in Houaphanh Province.
Environment
GHG emissions reduction targets: 
Cumulative GHG emissions reductions (GEO Indicator 4) are not used to evaluate outcome ratings. This is because emissions reductions are a corollary outcome of achieving the GEOs to increase EE and adopt renewable energy. The reduction target of about 30,000 kt CO2e was not fully achieved, based on the available evidence, though significant emissions reductions can nevertheless be attributed to project activities, [...]