Meta Data
Проект документа: 
No
Пересмотр более раннего документа?: 
No
Год вступления в силу: 
2006
Виды актов по количеству участников: 
National
Тип документа: 
Standard, Other
Экономический сектор: 
Power
Виды энергоресурсов: 
Power
Подготовлен: 
Energy Market Authority
Ссылка на документ: 
Сводный обзор: 
This document provides a general overview of Singapore’s policy regarding and registration of onsite power generation plants for self-consumption, with a nameplate capacity of 1 MW or more.
Деятельность органов власти
Energy management principles: 
Policy Decision 5 After reviewing the current policy, the Government has decided the following: (a) Reserve charges: Embedded generators should continue to pay reserve charges (SR & RR) as per current treatment. (b) Non-reserve charges: Embedded generators will be granted net treatment on non-reserve charges (EMC, PSO, MEUC & MSS), provided that they will not export power to the grid.