PDP2010: Revision 3
June 2012
SUMMARY OF
THAILAND POWER DEVELOPMENT PLAN 2012 – 2030
(PDP2010: REVISION 3)
Contents
Page
- Introduction 1
- Summary 3
- Thailand Electricity Overview and Power Demand Forecast 4
- Thailand Power Development Plan 2012 – 2030 (PDP2010: Revision 3) 7
4.1 Key Assumptions for PDP2010: Revision 3 Formulation 7
4.2 Thailand Power Development Plan (PDP2010: Revision 3) 8
4.3 Renewable Energy Generation 15
4.4 CO2 Emission from Power Sector 16
List of Appendices
| Page |
Appendix 1 | Power Demand Statistic and Load Forecast | 21 |
Appendix 2 | Figures of Thailand Power Development Plan (PDP2010: Revision 3) | 24 |
Appendix 3 | Comparison of Thailand Power Development Plans | 26 |
Appendix 4 | Projection of Generating Capacity by Power Plant Types | 29 |
Appendix 5 | Projection of Energy Generation by Fuel Types | 30 |
- Introduction
Thailand Power Development Plan 2010 - 2030 (PDP2010) was approved by the Nation Energy Policy Council (NEPC) on 12 March 2011, and then was endorsed by the Cabinet on 23 March 2011. The themes of PDP2010 substantially focused on security and adequacy of power system along with the policies of the Ministry of Energy (MoEN) on the aspects of environment concern, energy efficiency and renewable energy promotion to be in line with the 15-Year Renewable Energy Development Plan (REDP 2008 - 20212). Parenthetically, cogeneration system was recognized to promote as the efficient electricity generation.
In 2010, the recorded actual power demand (peak) of the country increased significantly higher than the forecast and tended to grow continuously. Additionally, the new power plant construction of Independent Power Producers (IPP) as plan has been delayed causing power system security to fall at risk influencing power reserve margin (RM) into the level of lower than the setting criteria or standards. Accordingly, the MoEN set a framework for a short-term urgent relief (2012 – 2019) by revising the power development plan (the PDP 2010) to be the one so called PDP2010: Revision 1 subsequently approved by NEPC on 25 November 2010, and endorsed by the Cabinet on 30 November 2010.
On 11 March 2011, an earthquake and tsunami occurred to strike the east coast of Japan, leading to severe damages on nuclear reactors as well as radiation leak and contamination on the Fukushima Daiichi Nuclear Power Plant. This disaster lessened public acceptance and trust in the Thailand’s nuclear power project development, encouraging the MoEN to contemplated the postponement of scheduled commercial operation date (SCOD) of the first unit on nuclear power project. Consequently, the PDP2010: Revision 2 was prepared and submitted to the NEPC, and accordingly was approved by the NEPC on 27 April 2011, and endorsed by the Cabinet on 3 May 2011 to shift SCOD of the first unit on nuclear power project forward by 3 years from 2020 to 2023 for the reasons of safety measures review, legislation framework, regulatory framework and stakeholder involvement review as well as additional supporting plans.
By the way, on 27 December 2011, the Cabinet approved the resolution of NEPC proposed on 30 November 2011 calling for Alternative Energy Development Plan: AEDP 2012– 2021 (by 25 percent instead of fossil fuels within the next 10 years) and also 20-Year Energy Efficiency Development Plan 2011 – 2030 (EE Plan 2011 – 2030).
The scope of the new government policies and the variation of current economic situation induce changes and fluctuation in both power demand and power supply. Therefore, to have clear vision on power supply acquiring, Thailand Power Development Plan 2010 – 2030 (PDP2010: Revision 3) is developed with crucial issues as the following:
1) Forecasted power demand results approved by the Thailand Load Forecast Subcommittee (TLFS) on 30 May 2012 are adopted within frameworks as the following.
– Refer to the projected Thai Gross Domestic Products (GDP) and projected Gross Regional Products (GRP) estimated by the Office of National Economic and Social Development Board (NESDB), and issued on 29 November 2011, covering the economic stimulation policies and flooding effects at the end of 2011
– Refer to the approved 20-Year Energy Efficiency Development Plan 2011 – 2030 (EE Plan 2011 – 2030) proposed by the MoEN
2) Alternative Energy Development is regarded according to Alternative Energy Development Plan: AEDP 2012-2021 to use renewable energy and alternative energy by 25 percent instead of fossil fuels within the next 10 years.
3) Energy supply security is taken into consideration of fuel diversification and suitable power reserve margin level.
- Summary
The revised PDP or “Thailand Power Development Plan 2010 – 2030 (PDP2010: Revision 3)” is suggested within the scope of the new government’s energy policies frameworks as listed below.
1) The 20-Year Energy Efficiency Development Plan 2011 – 2030 (EE Plan 2011 – 2030): this policy is targeting on 25 percent reduction of energy intensity (ratio of energy consumption to GDP) of the country within 20 years (2011 – 2030), resulting in the decrease of country’s power demand projection on account of energy saving programs and energy efficiency promotions.
2) The 10-Year Alternative Energy Development Plan 2012 - 2021 (AEDP 2012 – 2021): this policy is targeting on increasing the share of renewable energy and alternative energy uses by 25 percent instead of fossil fuels within the next 10 years, resulting in replacement of some planned conventional (fossil fuels as coal-fired or gas-fired based) power plants by renewable power plants.
In addition, the government has set the new policies for economic stimulation, causing trajectory changes in GDP growth rate projection during the year 2012 – 2020. However, power demand forecast in terms of 2030 net peak demand is still stand at about 52,256 Megawatt (MW) lower than that of the previous version of the forecast around 3,494 MW (or 6.27 percent).
The total generating capacities during 2012 – 2030 can be summarized as the following:
– Total capacity (as of December 2011) 32,395 MW
– Total added capacity during 2012 – 2030 55,130 MW
– Total retired capacity during 2012 – 2030 -16,839 MW
– Grand total capacity (at the end of 2030) 70,686 MW
- Thailand Electricity Overview and Power Demand Forecast
3.1 Electricity Overview
In 2012, the country’s electricity demand grew at an a bit accelerating rate in tandem with the hot weather. Net peak generation requirement (on EGAT system) rose up to 26,121.1 MW on 26 April 2012 at 14.30 hours, higher than that of the preceding year (standing at 23,900.2 MW) by 2,220.9 MW or 9.24 percent.
Net energy generation requirement throughout the first five-month of the year 2012 (January – May 2012) grew in line with the peak demand growth rate, amounting to 71,698.4 GWh, higher than that of the prior year, month on month, (standing at 65,552.0 GWh) by 6,146.4 GWh or 9.38 percent.
3.2 Power Demand Forecast
The latest power demand forecast was approved by the Thailand Load Forecast Subcommittee (TLFS) on 30 May 2012 with considerable assumptions as the following.
- Set a timeframe of the 20-year power demand forecast of 2012 – 2030
- Implement the new model of load forecast developed by the Energy for Environmental Foundation (E for E) under the project of Energy Policy and Planning Office (EPPO) on “Thailand Future Load Forecast” submitted by April 2010
- Refer to the trajectory GDP growth rate projection during 2011 – 2030 estimated by the Office of National Economic and Social Development Board (NESDB), and issued on 29 November 2011, taking into account economic stimulation policies and flooding effects faced at the end of 2011 (shown as Table 3.1)
- Incorporate energy saving programs and energy efficiency promotions in accordance with the MoEN’s 20-Year Energy Efficiency Development Plan 2011 – 2030 (EE Plan 2011 – 2030) approved by the NEPC on 30 November 2011 on intense thrust targeting on 25 percent reduction of the country’s energy intensity (ratio of energy consumption to GDP) within 20 years (as the governmental policy statement declaration to the parliament on 23 August 2011 of the Prime Minister: Miss Yingluck Shinawatra)
Table 3.1 Trajectory GDP Growth Rate Projection (2011 – 2030)
Unit: Percent
Year | 2011 | 2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 |
GDP | 1.5 | 5.0 | 5.1 | 5.7 | 6.0 | 5.1 | 4.7 | 4.1 | 4.2 | 4.3 |
Year | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | 2030 |
GDP | 4.2 | 4.1 | 4.0 | 4.0 | 4.0 | 4.0 | 3.9 | 3.9 | 3.8 | 3.8 |
The two main purposes of Thailand power development plan formulation are to maintain power system security and to provide adequate and reliable electricity supply. Hence, in order to maintain power system security, avoid blackout risk and provide adequate electricity supply for future power demand growth (in line with economic stimulation policy), the Thailand PDP Review Subcommittee (Chaired by the Permanent Secretary of the MoEN) decided, as a risk adverse on EE Plan implementation, to adopt the high case of load forecast expected to achieve 20% of 20-Year EE Plan target called EE20% for PDP formulation.
As net peak generation requirement (on EGAT system) rose up to 26,121.1 MW on 26 April 2012 at 14.30 hours, the Load Forecast Working Group agreed to adjust load forecast by applying the actual power demand of the first 4-month as the starting point in the modeling of load forecast. The revised load forecast was approved by the TLFS on 30 May 2012 within 3 scenarios as the following:
– Base case (EE40%): expected to achieve the 40% of 20-Year EE Plan target
– High case (EE20%): expected to achieve the 20% of 20-Year EE Plan target
– Low case (EE60%): expected to achieve the 60% of 20-Year EE Plan target
As decided by the Thailand PDP Review Subcommittee to use the High case of EE20% for the revised PDP formulation, the High case of load forecast of the year 2030 net peak generation requirement is then adopted - about 52,256 MW, higher than that of the year 2011 by 1,483 MW or 4.16 percent per year. In terms of net energy generation
requirement, the High case reveals about 346,767 GWh of net energy generation requirement in 2030, higher than that of the year 2011 by 9,793 GWh or 4.13 percent per year.
By comparison of the latest 30 May 2012 load forecast of PDP2010: Revision 3 and the previous load forecast of PDP2010: Revision 2, it indicates that peak demand of the latest version is lower than that of the previous one by 3,494 MW or 6,27 percent. For the energy demand, the latest version is lower than that of the previous one by 20,497 GWh or
5.58 percent. Decreasing in projection comes from the effect of EE Plan, and the details are presented in Appendix 1.
- Thailand Power Development Plan 2012 – 2030 (PDP2010: Revision 3)
4.1 Key Assumptions for PDP2010: Revision 3 Formulation
To formulate the revised PDP to be in line with the new government energy policies, several assumptions need to be reviewed and reconsidered. Key assumptions, made for PDP2010: Revision 3 formulation, are listed below.
1) The power demand forecast or load forecast: it is approved by the TLFS on 30 May 2012 to incorporate energy saving programs and energy efficiency promotions in accordance with the 20-Year Energy Efficiency Development Plan 2011 – 2030 (EE Plan 2011 – 2030) formulated by the MoEN, and approved by the NEPC on 30 November 2011.
2) Thailand power system security: Thailand should have the proper level of reserve margin to be not less than 15 percent of peak power demand. Moreover, to avoid the risk of the natural gas acquiring from sources in the western part of Thailand, in case of no natural gas supply, the appropriate level of reserve margin should be higher than 20 percent of the peak demand.
3) The future electricity acquiring: fuel type diversification in appropriate proportion is considered to reduce natural gas dependency in power generation.
4) Electricity acquiring from renewable energy: the MoEN targeted to increase the proportion of renewable energy for Thailand’s electricity generation by not less than 5% from that of the previous PDP2010: Revision 2 within 2030 by taking into account the 10-Year Alternative Energy Development Plan 2012 - 2021 (AEDP 2012 – 2021). And then in 2022 – 2030, the generation from renewable energy will be expanded in accordance with its potential and advanced technology development.
5) Electricity acquiring from nuclear power plant: with the scope of the government’s policy, a share of nuclear power generation should be not greater than
5 percent of total generating capacity. Additionally, the MoEN suggested shifting the scheduled commercial operation date (SCOD) of the first unit on nuclear power project forward by 3 years from 2020 to 2023.
6) Electricity acquiring from coal-fired power plant: the MoEN suggested considering coal-fired power plant development in an appropriate proportion as the necessity of Thailand power system except for considerations of other fuel types. Incidentally, for greenhouse gas emission reduction, CO2 in particular, clean coal technologies should be recommended.
7) Foreign power purchase: the suggested proportion of power purchase from neighboring countries should be not greater than 15 percent of total generating capacity by emphasizing only on the projects that having been signed Tariff MOU already.
8) Efficient power generation by cogeneration system: it is suggested to promote cogeneration and to increase the amount of power purchases from cogeneration system as the following:
– During 2010 – 2014: conforming to the projects that have been settled
– During 2014 – 2019: scheduling the power purchases of SPP projects with Firm contract amounting 3,500 MW as the NEPC approval on 24 August 2009 and 25 November 2010,
– After 2020: planning to purchase more electricity from SPP cogeneration with Firm contract totaling 1,350 MW.
9) CO2 emission from power sector: the target of CO2 emission reduction (ton CO2/kWh) of PDP2010: Revision 3 is still set to be not higher than that of the previous PDP2010.
4.2 Thailand Power Development Plan (PDP2010: Revision 3)
With the aforementioned key assumptions for PDP2010: Revision 3 formulation, Thailand Power Development Plan 2012 – 2030 (PDP2010: Revision 3) can be summarized as the following.
At the end of 2030, grand total capacity will be about 70,686 MW comprising total capacity (as of December 2011) amounting 32,395 MW, total added capacity of 55,130 MW and deduction of the retired capacity totaling 16,839 MW. The details of
generating capacity classified by power plant types are shown in Appendix 4; the details of estimation of energy generation by fuel types are presented in Appendix 5.
Total added capacity during 2012 – 2019 composes of all projects planned with commitment and agreement. The total added capacity will be about 23,325 MW detailed as the following:
– Power purchases from renewable energy 8,194 MW (both domestic and neighboring countries)
– Cogeneration 5,107 MW
– Combined cycle power plants 6,551 MW
– Thermal power plants (coal/lignite) 3,473 MW
Total added capacity during 2020 – 2030 comprises all projects planned for serving future power demand increasing annually and also replacement of the retired power plants. The total added capacity during this period will be about 31,805 MW summarized as the following:
– Power purchases from renewable energy 6,387 MW (both domestic and neighboring countries)
– Cogeneration 1,368 MW
– Gas turbine power plant (3 x 250 MW) 750 MW
– Combined cycle power plants (21 x 900 MW) 18,900 MW
– Thermal power plants (coal) (3 x 800 MW) 2,400 MW
– Thermal power plants (nuclear) (2 x 1,000 MW) 2,000 MW
The total capacities during 2012 – 2030 can be concluded as the following:
– Total capacity (as of December 2011) 32,395 MW
– Total added capacity during 2012 – 2030 55,130 MW
– Total retired capacity during 2012 – 2030 -16,839 MW
– Grand total capacity (at the end of 2030) 70,686 MW
The added capacity during 2012 – 2030 of 55,130 MW can be classified by power plant types as the following:
1. Renewable energy power plants | 14,580 | MW |
– Power purchase from domestic | 9,481 | MW |
– Power purchase from neighboring countries | 5,099 | MW |
2. Cogeneration | 6,476 | MW |
3. Combined cycle power plants | 25,451 | MW |
4. Thermal power plants | 8,623 | MW |
– Coal-fired power plants | 4,400 | MW |
– Nuclear power plants | 2,000 | MW |
– Gas turbine power plants | 750 | MW |
– Power purchase from neighboring countries | 1,473 | MW |
Total | 55,130 | MW |
Details of Thailand power development plan 2012 – 2030 (PDP2010: Rev.3) and names of power plants to be completed during the planning period are listed in Table 4.1.
Table 4.1
Thailand Power Development Plan 2012-2030
PDP2010: Revision 3
Year | Peak Demand (MW) | Projects | Fuel Types | Contract Capacity (MW) | Minimum Reserve Margin (%) |
2012 | 26,355 | SPP-Renewables | 498 | MW | - | | |
| | SPP-Cogeneration | 254 | MW | Gas | | |
| | VSPP-Renewables | 201 | MW | - | | |
| | VSPP-Cogeneration | 8 | MW | Gas | | |
| | GHECO-ONE Co.,Ltd. | 660 | MW | Coal | | |
| | Chao Phraya Dam #1-2 | 12 | MW | Hydro | | |
| | Naresuan Dam | 8 | MW | Hydro | | |
| | Khun Dan Prakarnchon Dam | 10 | MW | Hydro | | |
| | Power Purchase from Lao PDR (Theun Hinboun Ext.) (Jul) | 220 | MW | Hydro | 34,265 | 16.0 |
2013 | 27,443 | SPP-Renewables | 249 | MW | - | | |
| | SPP-Cogeneration | 1,170 | MW | Gas | | |
| | VSPP-Renewables | 772 | MW | - | | |
| | VSPP-Cogeneration | 16 | MW | Gas | | |
| | Mae Klong Dam #1-2 | 2x6 | MW | Hydro | | |
| | Pasak Jolasid Dam | 7 | MW | Hydro | 36,491 | 18.4 |
2014 | 28,790 | SPP-Renewables | 420 | MW | - | | |
| | SPP-Cogeneration | 270 | MW | Gas | | |
| | VSPP-Renewables | 181 | MW | - | | |
| | VSPP-Cogeneration | 16 | MW | Gas | | |
| | Renewable Energy (Additional) | 60 | MW | - | | |
| | Gulf JP NS Co.,Ltd. #1-2 (Jun, Dec) | 2x800 | MW | Gas | | |
| | Wang Noi CC #4 (Apr) | 769 | MW | Gas | | |
| | Chana CC #2 (Apr) | 782 | MW | Gas | | |
| | Thap Sakae Solar Cell | 5 | MW | Solar | | |
| | Sirindhorn Dam Solar Cell | 0.1 | MW | Solar | 39,542 | 17.7 |
2015 | 30,231 | SPP-Renewables | 369 | MW | - | | |
| | SPP-Cogeneration | 540 | MW | Gas | | |
| | VSPP-Renewables | 83 | MW | - | | |
| | VSPP-Cogeneration | 17 | MW | Gas | | |
| | Renewable Energy (Additional) | 230 | MW | - | | |
| | Gulf JP UT Co.,Ltd. #1-2 (Jun, Dec) | 2x800 | MW | Gas | | |
| | North Bangkok CC#2 (Oct) | 900 | MW | Gas | | |
| | Bang Lang Dam (Renovated) | 12 | MW | Hydro | | |
| | Kwae Noi Dam #1-2 | 2x15 | MW | Hydro | | |
| | Khao Yai Thiang Wind Turbine (North) | 18 | MW | Wind | | |
| | Chulabhorn Hydropower | 1 | MW | Hydro | | |
| | Klong Tron Hydropower | 3 | MW | Hydro | | |
| | Kiew Kohma Hydropower | 6 | MW | Hydro | | |
| | Mae Karm Solar Cell | 0.1 | MW | Solar | | |
| | Power Purchase from Lao PDR (Hongsa TH #1-2) (Jun, Nov) | 2x491 | MW | Lignite | 43,157 | 16.5 |
Table 4.1 (Continued)
Thailand Power Development Plan 2012-2030
PDP2010: Revision 3
Year | Peak Demand (MW) | Projects | Fuel Types | Contract Capacity (MW) | Minimum Reserve Margin(%) |
2016 | 31,808 | SPP-Renewables | 635 | MW | - | | |
| | SPP-Cogeneration | 450 | MW | Gas | | |
| | VSPP-Renewables | 79 | MW | - | | |
| | VSPP-Cogeneration | 21 | MW | Gas | | |
| | Renewable Energy (Additional) | 270 | MW | - | | |
| | National Power Supply Co.,Ltd. TH #1-2 (Nov) | 270 | MW | Coal | | |
| | New Power Plant (South) (Jul) | 900 | MW | Gas | | |
| | Phayaman Hydropower | 2 | MW | Hydro | | |
| | Lam Pao Hydropower | 1 | MW | Hydro | | |
| | Lam Ta Khong Hydropower | 2 | MW | Hydro | | |
| | Bhumubol Dam Solar Cell | 0.1 | MW | Solar | | |
| | Power Purchase from Lao PDR (Hongsa TH #3) (Mar) | 491 | MW | Lignite | 45,530 | 24.3 |
2017 | 33,263 | SPP-Renewables | 153 | MW | - | | |
| | SPP-Cogeneration | 900 | MW | Gas | | |
| | VSPP-Renewables | 77 | MW | - | | |
| | Renewable Energy (Additional) | 280 | MW | - | | |
| | National Power Supply Co.,Ltd. TH #3-4 (Mar) | 270 | MW | Coal | | |
| | LamTa Khong Pumped Storage #3-4 (Jun) | 500 | MW | Hydro | | |
| | That Noi Hydropower | 2 | MW | Hydro | | |
| | Rawai Stadium Wind Turbine | 3 | MW | Wind | | |
| | Rajjaprabha Dam Solar Cell | 0.1 | MW | Solar | | |
| | Pha Chuk Hydropower | 20 | MW | Hydro | 47,240 | 21.4 |
2018 | 34,592 | SPP-Cogeneration | 720 | MW | Gas | | |
| | VSPP-Renewables | 86 | MW | - | | |
| | VSPP-Cogeneration | 1 | MW | Gas | | |
| | Renewable Energy (Additional) | 280 | MW | - | | |
| | Mae Moh TH #4-7 (Replaced) (600MW) | | | - | | |
| | Yaso Thorn - Phanom Prai Hydropower | 4 | MW | Hydro | | |
| | Khao Laem Hydropower # 1-2 | 2x9 | MW | Hydro | | |
| | Kra Seao Hydropower | 2 | MW | Hydro | | |
| | Power Purchase from Lao PDR (Nam-Ngiep 1) (Jan) | 269 | MW | Hydro | | |
| | Power Purchase from Lao PDR (Xe-Pian) (Aug) | 390 | MW | Hydro | 48,329 | 19.6 |
2019 | 35,869 | SPP-Renewables | 60 | MW | - | | |
| | SPP-Cogeneration | 720 | MW | Gas | | |
| | VSPP-Renewables | 72 | MW | - | | |
| | VSPP-Cogeneration | 5 | MW | Gas | | |
| | Renewable Energy (Additional) | 310 | MW | - | | |
| | EGAT Coal-Fired TH #1 (Jun) | 800 | MW | Coal | | |
| | Huai Sataw Hydropower | 1 | MW | Hydro | | |
| | Bang Pakong Hydropower | 2 | MW | Hydro | | |
| | Sirindhorn Dam Solar Cell | 1 | MW | Solar | | |
| | Khao Yai Thiang Wind Turbine (South) | 50 | MW | Wind | | |
| | Power Purchase from Lao PDR (Xaiyaburi) (Oct) | 1,220 | MW | Hydro | 51,386 | 18.7 |
2020 | 37,325 | SPP-Renewables | 45 | MW | - | | |
| | SPP-Cogeneration (Additional # 1) | 90 | MW | Gas | | |
| | VSPP-Renewables | 81 | MW | - | | |
| | Renewable Energy (Additional) | 310 | MW | - | | |
| | Mae Saruay Hydropower | 2 | MW | Hydro | | |
| | Thatako Solar Cell #1 | 1 | MW | Solar | | |
| | Klong See Yud Hydropower | 3 | MW | Hydro | 50,389 | 18.1 |
Table 4.1 (Continued)
Thailand Power Development Plan 2012-2030
PDP2010: Revision 3
Year | Peak Demand (MW) | Projects | Fuel Types | Contract Capacity (MW) | Minimum Reserve Margin (%) |
2021 | 38,726 | SPP-Cogeneration (Additional # 2-3) | 180 | MW | Gas | | |
| | VSPP-Renewables | 79 | MW | - | | |
| | VSPP-Cogeneration | 1 | MW | Gas | | |
| | Renewable Energy (Additional) | 360 | MW | - | | |
| | New Gas-fired Power Plant | 900 | MW | Gas | | |
| | Bang Pakong CC #1 (Replaced) | 900 | MW | Gas | | |
| | Chonnaboat Hydropower | 2 | MW | Hydro | | |
| | Thatako Solar Cell #2 | 1 | MW | Solar | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 52,912 | 17.8 |
2022 | 40,134 | SPP-Cogeneration (Additional # 4-5) | 180 | MW | Gas | | |
| | VSPP-Renewables | 67 | MW | - | | |
| | VSPP-Cogeneration | 5 | MW | Gas | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | New Gas-Fired Power Plant | 900 | MW | Gas | | |
| | Bang Pakong CC #2 (Replaced) | 900 | MW | Gas | | |
| | EGAT Coal-Fired TH #2 | 800 | MW | Coal | | |
| | Mahasarakam Hydropower | 1 | MW | Hydro | | |
| | Chulabhorn Dam Solar Cell | 0.1 | MW | Solar | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 56,135 | 16.9 |
2023 | 41,567 | SPP-Cogeneration (Additional # 6-7) | 180 | MW | Gas | | |
| | VSPP-Renewables | 47 | MW | - | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | New Gas-Fired Power Plant | 900 | MW | Gas | | |
| | South Bangkok CC #1-2 (Replaced) | 2x900 | MW | Gas | | |
| | Low Wind Speed Wind Turbine | 10 | MW | Wind | | |
| | Huai Nam Sai Hydropower | 2 | MW | Hydro | | |
| | Rasisalai Hydropower | 2 | MW | Hydro | | |
| | Ubonrat Dam Solar Cell | 0.1 | MW | Solar | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 56,732 | 16.4 |
2024 | 43,049 | SPP-Cogeneration (Additional # 8-9) | 180 | MW | Gas | | |
| | VSPP-Renewables | 53 | MW | - | | |
| | VSPP-Cogeneration | 1 | MW | Gas | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | New Gas-Fired Power Plant | 900 | MW | Gas | | |
| | South Bangkok CC #3 (Replaced) | 900 | MW | Gas | | |
| | Bang Pakong CC #3 (Replaced) | 900 | MW | Gas | | |
| | Hua Na Hydropower | 1 | MW | Hydro | | |
| | Lamtapearn Hydropower | 1 | MW | Hydro | | |
| | Sirikit Dam Solar Cell | 0.1 | MW | Solar | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 59,509 | 16.3 |
2025 | 44,521 | SPP-Cogeneration (Additional # 10-11) | 180 | MW | Gas | | |
| | VSPP-Renewables | 37 | MW | - | | |
| | VSPP-Cogeneration | 5 | MW | Gas | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | New Gas-Fired Power Plant | 900 | MW | Gas | | |
| | Bang Pakong CC #4 (Replaced) | 900 | MW | Gas | | |
| | EGAT Coal-Fired TH #3 | 800 | MW | Coal | | |
| | Pranburi Hydropower | 2 | MW | Hydro | | |
| | Tabsalao Hydropower | 2 | MW | Hydro | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 60,477 | 16.5 |
Table 4.1 (Continued)
Thailand Power Development Plan 2012-2030
PDP2010: Revision 3
Year | Peak Demand (MW) | Projects | Fuel Types | Contract Capacity (MW) | Minimum Reserve Margin (%) |
2026 | 46,002 | SPP-Cogeneration (Additional # 12-13) | 180 | MW | Gas | | |
| | VSPP-Renewables | 32 | MW | - | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | New Gas-Fired Power Plant | 900 | MW | Gas | | |
| | Bang Pakong CC #5 (Replaced) | 900 | MW | Gas | | |
| | EGAT Nuclear Power Plant #1 | 1,000 | MW | Uranium | | |
| | Kamalasai Hydropower | 1 | MW | Hydro | | |
| | Numpung Dam Solar Cell | 1 | MW | Solar | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 64,007 | 16.5 |
2027 | 47,545 | SPP-Cogeneration (Additional # 14-15) | 180 | MW | Gas | | |
| | VSPP-Renewables | 33 | MW | - | | |
| | VSPP-Cogeneration | 1 | MW | Gas | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | Wang Noi CC #1 (Replaced) | 900 | MW | Gas | | |
| | Bang Pakong CC #6 (Replaced) | 900 | MW | Gas | | |
| | EGAT Nuclear Power Plant #2 | 1,000 | MW | Uranium | | |
| | Mae Wong Hydropower | 12 | MW | Hydro | | |
| | Vajiralongkorn Dam Solar Cell | 0.1 | MW | Solar | | |
| | Chaiyaphum and Nakhon Ratchasima Wind Turbine | 50 | MW | Wind | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 64,979 | 16.2 |
2028 | 49,114 | VSPP-Renewables | 32 | MW | - | | |
| | VSPP-Cogeneration | 5 | MW | Gas | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | EGAT Coal-Fired TH #4 | 800 | MW | Coal | | |
| | Wang Noi CC #2-3 (Replaced) | 2x900 | MW | Gas | | |
| | Gas Turbine #1 | 250 | MW | Diesel | | |
| | Mae Khan Hydropower | 16 | MW | Hydro | | |
| | Huai Samong Hydropower | 1 | MW | Hydro | | |
| | Mae Moh Solar Cell | 1 | MW | Solar | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 67,012 | 16.4 |
2029 | 50,624 | VSPP-Renewables | 32 | MW | - | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | South Bangkok CC #4 (Replaced) | 900 | MW | Gas | | |
| | EGAT New Combined Cycle Power Plant | 900 | MW | Gas | | |
| | Gas Turbine #2 | 250 | MW | Diesel | | |
| | Ao Phai Wind Turbine | 10 | MW | Wind | | |
| | Lam Dome Yai Hydropower | 1 | MW | Hydro | | |
| | Kamphaeng Phet Solar Cell | 3 | MW | Solar | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 69,358 | 16.4 |
2030 | 52,256 | VSPP-Renewables | 33 | MW | - | | |
| | VSPP-Cogeneration | 1 | MW | Gas | | |
| | Renewable Energy (Additional) | 220 | MW | - | | |
| | EGAT New Combined Cycle Power Plant | 900 | MW | Gas | | |
| | Gas Turbine #3 | 250 | MW | Diesel | | |
| | Solar Cell , Southern Part of Thailand | 10 | MW | Solar | | |
| | Samut Sakhon Wind Turbine | 30 | MW | Wind | | |
| | Klong Luang Hydropower | 1 | MW | Hydro | | |
| | Power Purchase from Neighbouring Countries | 300 | MW | - | 70,686 | 16.2 |
| | Total Contract Capacity as of December 2011 | | | | 32,395 | MW |
Total Added Capacity | 55,130 | MW |
Total Retired Capacity | - 16,839 | MW |
Grand Total Capacity at the End of 2030 | 70,686 | MW |
4.3 Renewable Energy Generation
With the government policy targeting on increasing the share of renewable energy and alternative energy uses by 25 percent instead of fossil fuels within the next
10 years, new projects of renewable energy development are initiated into PDP2010: Revision 3. Hence, at the end of 2030, total capacity of renewable energy will be around 20,546.3 MW (or 29 percent of total generating capacity in the power system) comprising total existing capacity amounting 6,340.2 MW, total added capacity of renewable energy of 14,580.4 MW and deduction of the retired capacity of renewable energy totaling
374.3 MW. The 20,546.3 MW capacity of renewable energy can be classified into domestic renewable energy of 13,688 MW and renewable energy from neighboring countries of 6,858 MW as the following.
Renewable Energy Power Projects during 2012 – 2021
In this period, renewable energy power projects should be in line with the 10- Year Alternative Energy Development Plan: AEDP 2012-2021 of the MoEN detailed as the following:
– Solar power 1,806.4 MW
– Wind power 1,774.3 MW
– Hydro power 3,061.4 MW
– (both domestic and neighboring countries)
– Biomass 2,378.7 MW
– Biogas 22.1 MW
– Municipal solid waste (MSW) 334.5 MW
Total 9,377.4 MW
Renewable Energy Power Projects during 2022 – 2030
Renewable energy power project development during 2022 – 2030 will be considered in accordance with its potential detailed as the following:
– Solar power 1,995.7 MW
– Wind power 199.4 MW
– Hydro power 2,742.5 MW
(both domestic and neighboring countries)
– Biomass 223.5 MW
– Biogas 24.1 MW
– Municipal solid waste (MSW) 17.8 MW
Total 5,203.0 MW
The lists of power plant types to be completed during 2012 – 2030 are presented in Table 4.2.
4.4 CO2 Emission from Power Sector
In 2011, an average greenhouse gas (CO2) emission released from Power sector is about 0.505 kgCO2/kWh. In response to the MoEN policies on clean energy development promotion, the 2030 target of CO2 emission reduction (ton CO2/kWh) of PDP2010: Revision 3 is set to be not higher than that of the previous PDP2010: Revision 2 by rearranging generation mix appropriately.
Estimation of CO2 emission amounts on PDP2010: Revision 3 is calculated with reference to the international principles as the 2006 IPCC Guidelines for National Greenhouse Gas Inventories (Details as shown in Table 4.3).
Table 4.2 Annual Capacity of Renewable Energy by Fuel Types
(Unit: MW)
Year | Fuel Types |
Solar | Wind | Hydro | Biomass | Biogas | MSW | New energy form | Total |
Capacity as of 2011 | 138.0 | 3.0 | 5,322.5 | 747.3 | 106.0 | 21.4 | 2.0 | 6,340.2 |
New Renewable Contract Capacity
2012 | 164.9 | 246.9 | 250.5 | 280.5 | 4.2 | 1.0 | - | 948.1 |
2013 | 375.8 | 14.0 | 19.2 | 574.5 | - | 56.0 | - | 1,039.5 |
2014 | 181.1 | 263.6 | 0.5 | 206.8 | 1.2 | 12.8 | - | 666.0 |
2015 | 191.1 | 302.9 | 51.8 | 180.5 | 2.3 | 22.8 | - | 751.3 |
2016 | 130.1 | 641.8 | 5.2 | 176.8 | 2.3 | 32.8 | - | 989.0 |
2017 | 130.1 | 163.1 | 522.0 | 175.3 | 2.3 | 41.8 | - | 1,034.6 |
2018 | 130.0 | 7.4 | 682.6 | 184.5 | 2.4 | 41.8 | - | 1,048.8 |
2019 | 151.0 | 117.8 | 1,223.5 | 179.8 | 2.4 | 41.8 | - | 1,716.4 |
2020 | 151.0 | 8.2 | 4.7 | 234.0 | 2.5 | 41.9 | - | 442.2 |
2021 | 201.0 | 8.6 | 301.5 | 186.0 | 2.5 | 41.9 | - | 741.5 |
Total New Capacity 2012-2021 | 1,806.4 | 1,774.3 | 3,061.4 | 2,378.7 | 22.1 | 334.5 | - | 9,377.4 |
2022 | 220.1 | 9.0 | 301.3 | 53.7 | 2.5 | 1.9 | - | 588.5 |
2023 | 220.1 | 19.5 | 303.5 | 32.8 | 2.6 | 1.9 | - | 580.4 |
2024 | 220.1 | 9.9 | 302.2 | 38.6 | 2.6 | 1.9 | - | 575.4 |
2025 | 220.0 | 10.4 | 303.3 | 21.2 | 2.6 | 2.0 | - | 559.5 |
2026 | 221.0 | 11.0 | 301.0 | 16.8 | 2.7 | 2.0 | - | 554.4 |
2027 | 220.1 | 61.5 | 312.0 | 16.9 | 2.7 | 2.0 | - | 615.2 |
2028 | 221.0 | 12.1 | 317.3 | 14.4 | 2.8 | 2.0 | - | 569.5 |
2029 | 223.0 | 22.7 | 301.0 | 14.5 | 2.8 | 2.0 | - | 566.1 |
2030 | 230.0 | 43.3 | 301.0 | 14.7 | 2.8 | 2.1 | - | 594.0 |
Total New Capacity 2022-2030 | 1,995.4 | 199.4 | 2,742.6 | 223.6 | 24.1 | 17.8 | - | 5,203.0 |
Total New Capacity 2012-2030 | 3,802.0 | 1,973.7 | 5,804.0 | 2,602.2 | 46.2 | 352.3 | - | 14,580.4 |
Table 4.3 Estimation of CO2 Emission Amounts
(Unit: kgCO2/kWh)
Year | PDP2010: Revision 2 | PDP2010: Revision 3 |
Annual Amounts | Accumulative Amounts (Base Year: 2012) | Annual Amounts | Accumulative Amounts (Base Year: 2012) |
2012 | 0.488 | 0.488 | 0.478 | 0.478 |
2013 | 0.481 | 0.485 | 0.471 | 0.474 |
2014 | 0.467 | 0.479 | 0.468 | 0.472 |
2015 | 0.447 | 0.470 | 0.448 | 0.466 |
2016 | 0.422 | 0.460 | 0.430 | 0.458 |
2017 | 0.412 | 0.451 | 0.429 | 0.452 |
2018 | 0.401 | 0.443 | 0.413 | 0.446 |
2019 | 0.401 | 0.437 | 0.416 | 0.442 |
2020 | 0.405 | 0.433 | 0.412 | 0.438 |
2021 | 0.410 | 0.430 | 0.407 | 0.434 |
2022 | 0.404 | 0.427 | 0.410 | 0.432 |
2023 | 0.400 | 0.424 | 0.413 | 0.430 |
2024 | 0.382 | 0.420 | 0.406 | 0.427 |
2025 | 0.377 | 0.416 | 0.407 | 0.426 |
2026 | 0.391 | 0.414 | 0.403 | 0.424 |
2027 | 0.377 | 0.411 | 0.391 | 0.421 |
2028 | 0.382 | 0.409 | 0.395 | 0.419 |
2029 | 0.385 | 0.407 | 0.391 | 0.417 |
2030 | 0.386 | 0.405 | 0.385 | 0.415 |
Appendix 1
Page 1
Power Demand Statistic and Load Forecast for PDP (EGAT System and Purchase from VSPP)
Case : May 2012 (EE20%)
Remark : Power Purchase from VSPP is included.
Appendix 1
Page 2
Comparison of Load Forecast (Including Power Purchase from VSPP)
YEAR | CASE : February (Adjusted) (1) | CASE : May 2012 EE20% (2) | Difference (2)-(1) |
MW | GWh | MW | GWh | MW | % | GWh | % |
2011 | 25,952 | 169,444 | 24,070 | 160,706 | -1,882 | -7.25 | -8,738 | -5.16 |
2012 | 27,367 | 177,584 | 26,355 | 175,089 | -1,012 | -3.70 | -2,495 | -1.41 |
2013 | 28,707 | 185,561 | 27,443 | 183,283 | -1,264 | -4.40 | -2,278 | -1.23 |
2014 | 29,917 | 193,803 | 28,790 | 191,630 | -1,127 | -3.77 | -2,173 | -1.12 |
2015 | 31,096 | 201,998 | 30,231 | 200,726 | -865 | -2.78 | -1,272 | -0.63 |
2016 | 32,451 | 211,248 | 31,809 | 210,619 | -643 | -1.98 | -629 | -0.30 |
2017 | 33,996 | 221,066 | 33,264 | 219,616 | -732 | -2.15 | -1,450 | -0.66 |
2018 | 35,536 | 231,079 | 34,593 | 227,760 | -943 | -2.65 | -3,319 | -1.44 |
2019 | 36,903 | 240,341 | 35,869 | 236,408 | -1,034 | -2.80 | -3,933 | -1.64 |
2020 | 38,320 | 250,210 | 37,326 | 246,164 | -994 | -2.60 | -4,046 | -1.62 |
2021 | 39,921 | 260,526 | 38,726 | 255,591 | -1,195 | -2.99 | -4,935 | -1.89 |
2022 | 41,443 | 270,776 | 40,134 | 265,039 | -1,309 | -3.16 | -5,737 | -2.12 |
2023 | 42,995 | 281,330 | 41,567 | 274,672 | -1,428 | -3.32 | -6,658 | -2.37 |
2024 | 44,527 | 292,214 | 43,049 | 284,640 | -1,478 | -3.32 | -7,574 | -2.59 |
2025 | 46,345 | 303,587 | 44,521 | 294,508 | -1,824 | -3.94 | -9,079 | -2.99 |
2026 | 48,093 | 315,392 | 46,003 | 304,548 | -2,091 | -4.35 | -10,844 | -3.44 |
2027 | 49,908 | 327,638 | 47,545 | 314,925 | -2,363 | -4.73 | -12,713 | -3.88 |
2028 | 51,693 | 340,340 | 49,115 | 325,470 | -2,578 | -4.99 | -14,870 | -4.37 |
2029 | 53,716 | 353,520 | 50,624 | 335,787 | -3,092 | -5.76 | -17,733 | -5.02 |
2030 | 55,750 | 367,264 | 52,256 | 346,767 | -3,494 | -6.27 | -20,497 | -5.58 |
Power Demand Statistic and Load Forecast (EGAT System)
Case : May 2012 (EE20%)
Appendix 1
Page 3
Year | Peak | Energy | Load Factor % |
MW | Increase | GWh | Increase |
MW | % | GWh | % |
Actual : NET | Generation |
2008 | 22,018.0 | 8.8 | 0.04 | 145,227.5 | 1,486.5 | 1.03 | 75.09 |
2009 | 22,044.9 | 26.9 | 0.12 | 145,297.3 | 69.8 | 0.05 | 75.24 |
2010 | 24,009.9 | 1,965.0 | 8.91 | 160,189.5 | 14,892.2 | 10.25 | 76.16 |
2011 | 23,900.2 | -109.7 | -0.46 | 158,963.3 | -1,226.2 | -0.77 | 75.93 |
Forecast : NET Generation |
2012 | 26,121 | 2,221 | 9.29 | 172,895 | 13,932 | 8.76 | 75.56 |
2013 | 26,950 | 829 | 3.17 | 178,962 | 6,067 | 3.51 | 75.81 |
2014 | 28,236 | 1,286 | 4.77 | 186,745 | 7,783 | 4.35 | 75.50 |
2015 | 29,641 | 1,405 | 4.98 | 195,482 | 8,737 | 4.68 | 75.29 |
2016 | 31,182 | 1,541 | 5.20 | 205,020 | 9,538 | 4.88 | 75.06 |
2017 | 32,613 | 1,431 | 4.59 | 213,717 | 8,697 | 4.24 | 74.81 |
2018 | 33,914 | 1,301 | 3.99 | 221,485 | 7,768 | 3.63 | 74.55 |
2019 | 35,165 | 1,251 | 3.69 | 229,806 | 8,321 | 3.76 | 74.60 |
2020 | 36,596 | 1,431 | 4.07 | 239,291 | 9,485 | 4.13 | 74.64 |
2021 | 37,971 | 1,375 | 3.76 | 248,456 | 9,165 | 3.83 | 74.70 |
2022 | 39,357 | 1,386 | 3.65 | 257,676 | 9,220 | 3.71 | 74.74 |
2023 | 40,777 | 1,420 | 3.61 | 267,166 | 9,490 | 3.68 | 74.79 |
2024 | 42,244 | 1,467 | 3.60 | 276,967 | 9,801 | 3.67 | 74.84 |
2025 | 43,704 | 1,460 | 3.46 | 286,722 | 9,755 | 3.52 | 74.89 |
2026 | 45,179 | 1,475 | 3.37 | 296,674 | 9,952 | 3.47 | 74.96 |
2027 | 46,714 | 1,535 | 3.40 | 306,960 | 10,286 | 3.47 | 75.01 |
2028 | 48,275 | 1,561 | 3.34 | 317,413 | 10,453 | 3.41 | 75.06 |
2029 | 49,778 | 1,503 | 3.11 | 327,648 | 10,235 | 3.22 | 75.14 |
2030 | 51,403 | 1,625 | 3.26 | 338,541 | 10,893 | 3.32 | 75.18 |
Average Growth | 667 1,126 1,391 1,422 1,540 | 2.94 4.30 4.31 3.61 3.30 | - - - - - | 5,483 7,058 8,762 9,486 10,364 | 3.68 4.06 4.13 3.68 3.38 | - - - - - |
2008-2010 | - |
2011-2015 | - |
2016-2020 | - |
2021-2025 | - |
2026-2030 | - |
2012-2030 | - | 1,448 | 4.11 | - | 9,451 | 4.06 | - |
Figure of Thailand Power Development Plan (PDP2010: Revision 3)
Peak and Capacity (MW)
Appendix 2
Page 1
10,000 20,000
30,000
40,000
50,000
0,000 70,000 80,000
Renewables Cogeneration
728.1 MW 262 MW
GHECO-ONE Co.,Ltd. 660 MW
Theun Hinboun Ext. 220 MW
2012
Renewables 1,039.5 MW
Cogeneration 1,186 MW
2013
Renewables Cogeneration
666 MW
286 MW
Gulf JP NS Co.,Ltd. #1-2 1600 MW
W ng Noi CC #4 Chana CC #2
768.7 MW
782.5 MW
Renewables Co eneration
751.3 MW 557 MW
Gulf JP UT Co.,Ltd. #1-2 1600 MW
North Bangkok CC#2 900 MW
Ho gsa TH #1-2 982 MW
2015
Renewables Cogenerati n
989 MW
470.8 MW
National Power Supply TH #1-2 270 MW
New Power Plant (South) Hongsa TH #3
900 MW
491 MW
Renewables Cogeneration
534.6 MW 900 MW
National Power Supply TH #3-4 270 M
LamTa Khong #3-4 500 MW
2017
Cogeneration 720.9 MW
Mae Moh TH #4-7 (Replaced 600 MW)
Nam-Ngiep 1 Xe-Pian
390 MW
269 MW
Renewables Cogeneration
496.4 MW
724.8 MW
EGAT Coal-Fired TH #1 800 MW
Xaiyaburi 1,220 MW
2019
Peak Generation
Peak Generation + 15% Dependable
apacity Contracted Capacity
24
class="Section53">
Figure of Thailand Power Development Plan (PDP2010: Revision 3)
Peak and Capacity (MW)
Appendix 2
Page 2
20,000 30,000
40,000
50,000
60,000 70,000 80,000 90,000
Renewables Cogeneration
42.2 MW 90 MW
Renewables Cogeneration
441. MW
180.9 MW
New Gas-fired Power Plant 90 MW Bang Pakong CC #1 (Replaced) 90 MW
2021
Power Purchase
Renewables Cogeneration
300 MW
288.5 MW
184.8 MW
New Gas-fired Power Plant 900 MW
Bang Pakong C #2 (Replaced) 900 MW
EGAT Coal-Fir d TH #2 800 MW
2022 Power Purchase
Renewables Cogeneration
300 MW
280.4 MW 180 MW
New Gas-fired Power Plant 90 MW
South Bangkok CC #1-2 1800 MW
2023
Power Purchase
Renewables Cogeneration
300 MW
275.4 MW
180.9 MW
New Gas-fired Power Plant 900 MW
South Bangkok CC #3 (Replaced) 900 MW Bang Pa ong CC #3 (Replaced) 900 MW
2024 Power P rchase
Renew bles Cogeneration
300 MW
259.4 MW
184.8 MW
New Gas-fired Power Pla t 900 MW Bang Pakong CC #4 (Replaced) 900 MW
2025
EGAT Coal-Fired TH #3 Power Purchase
Renewables Cogeneration
800 MW
300 MW
254.4 MW 180 MW
New Gas-fired Power Plant 900 MW Bang Pakong CC #5 (Replaced) 900 MW EGAT Nuclear Power Plant #1 1000 MW
2026 Power Purchase
Renewables Cogeneration
300 MW
315.2 MW
180.9 MW
Wang Noi CC #1(Replaced) 900 MW Bang Pakong CC #6 (Replaced) 900 MW EGAT Nuclear Power Plant #2 1000 MW
2027
Power Purchase
Renewables Cogeneration
300 MW
269.5 MW
.8 MW
EGAT Coal-Fi ed TH #4 800 MW
2028
Wang Noi CC Gas Turbine #1 Power Purchas
Renewables
2-3(Replaced) 1800 MW
250 MW
300 MW
266.1 MW
South Bangkok CC #4 (Replaced) 00 MW
EGAT New Combined Cycle 900 MW
Gas Turbine #2
2029 Power Purchase
Renewables Cogeneration EGAT New
250 MW
300 MW
294 MW
0.9 MW ombined Cycle 900 MW
2030
Gas Turbine #3 250 MW
Power Purch se 300 MW
Peak Generation
Peak Generation + 15% Dependable
apacity Contracted Capacity
25
class="Section81">
Appendix 3
Page 1
Comparison of Thailand Power Development Plans
(2012-2019)
Year | PDP2010 Revision 2 (NPEC 27 Apr 2011) | PDP2010 Revision 3 (NPEC 8 Jun 2012) |
Projects | MW | Projects | MW |
2012 | Renewables | 183.3 | Renewables | 728.1 |
| Cogeneration | 434 | Cogeneration | 262 |
| | | GHECO-ONE Co.,Ltd. | 660 |
| Theun Hinboun Ext. | 220 | Theun Hinboun Ext. | 220 |
2013 | Renewables Cogeneration | 212.7 996 | Renewables Cogeneration | 1,039.5 1,186 |
2014 | Renewables | 330.3 | Renewables | 666 |
| Cogeneration | 361 | Cogeneration | 286 |
| Wang Noi CC #4 (Apr) | 800 | Wang Noi CC #4 (Apr) | 768.7 |
| Chana CC #2 (Apr) | 800 | Chana CC #2 (Apr) | 782.2 |
| Power Generation.#1-2(Jun-Dec) | 2x800 | Gulf JP NS Co.,Ltd. #1-2 (Jun, Dec) | 2x800 |
2015 | Renewables | 181.5 | Renewables | 751.3 |
| Cogeneration | 632 | Cogeneration | 557 |
| North Bangkok CC#2 (Apr) | 800 | North Bangkok CC#2 (Oct) | 900 |
| Siam Energy #1-2 (Jun, Dec) | 2x800 | Gulf JP UT Co.,Ltd. #1-2 (Jun, Dec) | 2x800 |
| Hongsa TH #1-2 (May, Oct) | 2x491 | Hongsa TH #1-2 (Jun, Nov) | 2x491 |
2016 | Renewables Cogeneration New Power Plant (South) (Jul) National Power Supply TH #1-2 (Nov) My Khot TH #1-3 (Jan, Apr, Jul) Hongsa TH #3 (Mar) | 228.3 726 800 2x135 3x123 491 | Renewables | 989 |
| Cogeneration | 470.8 |
| New Power Plant (South) (Jul) | 900 |
| National Power Supply TH #1-2 (Nov) | 2x135 |
| Hongsa TH #3 (Mar) | 491 |
2017 | Renewables Cogeneration National Power Supply TH #3-4 (Mar) LamTa Khong Pumped Storage #3-4 Nam-Ngum 3 (Jan) | 299.1 721 2x135 500 440 | Renewables | 534.6 |
| Cogeneration | 900 |
| National Power Supply TH #3-4 (Mar) | 2x135 |
| LamTa Khong Pumped Storage #3-4 | 500 |
2018 | Renewables | 186.5 | Renewables | 389.8 |
| Cogeneration | 723 | Cogeneration | 720.9 |
| | | Mae Moh TH #4-7 (Replaced) (600MW) | |
| Nam-Ngiep 1 (Jan) | 269 | Nam-Ngiep 1 (Jan) | 269 |
| Xe-Pian (Jan) | 390 | Xe-Pian (Aug) | 390 |
2019 | Renewables Cogeneration EGAT Coal-Fired TH #1 (Jun) Xaiyaburi (Jan) | 183 457 800 1,220 | Renewables | 496.4 |
| Cogeneration | 724.8 |
| EGAT Coal-Fired TH #1 (Jun) | 800 |
| Xaiyaburi (Oct) | 1,220 |
Appendix 3
Page 2
Comparison of Thailand Power Development Plans
(2020-2026)
Year | PDP2010 Revision 2 (NPEC 27 Apr 2011) | PDP2010 Revision 3 (NPEC 8 Jun 2012) |
Projects | MW | Projects | MW |
2020 | Renewables | 193 | Renewables | 442.2 |
| Cogeneration | 2 | Cogeneration | 90 |
| New Gas-fired Power Plant #1 | 800 | | |
| Power Purchase | 600 | | |
2021 | Renewables | 134 | Renewables | 441.5 |
| Cogeneration | 2 | Cogeneration | 180.9 |
| | | New Gas-fired Power Plant | 900 |
| EGAT Coal-Fired TH #2 | 800 | Bang Pakong CC #1 (Replaced) | 900 |
| Power Purchase | 600 | Power Purchase | 300 |
2022 | Renewables | 309.5 | Renewables | 288.5 |
| Cogeneration | 367 | Cogeneration | 184.8 |
| New Gas-fired Power Plant #2-3 | 2x800 | New Gas-fired Power Plant | 900 |
| | | Bang Pakong CC #2 (Replaced) | 900 |
| | | EGAT Coal-Fired TH #2 | 800 |
| Power Purchase | 600 | Power Purchase | 300 |
2023 | Renewables | 148 | Renewables | 280.4 |
| Cogeneration | 361 | Cogeneration | 180 |
| New Gas-fired Power Plant # 4-7 | 4x800 | New Gas-fired Power Plant | 900 |
| EGAT Coal-Fired TH #3 | 800 | South Bangkok CC #1-2 (Replaced) | 2x900 |
| EGAT Nuclear Power Plant #1 | 1,000 | | |
| Power Purchase | 600 | Power Purchase | 300 |
2024 | Renewables | 158 | Renewables | 275.4 |
| Cogeneration | 362 | Cogeneration | 180.9 |
| EGAT Nuclear Power Plant #2 | 1,000 | New Gas-fired Power Plant | 900 |
| | | South Bangkok CC #3 (Replaced) | 900 |
| | | Bang Pakong CC #3 (Replaced) | 900 |
| Power Purchase | 600 | Power Purchase | 300 |
2025 | Renewables | 165 | Renewables | 259.5 |
| Cogeneration | 367 | Cogeneration | 184.8 |
| New Gas-fired Power Plant # 8-9 | 2x800 | New Gas-fired Power Plant | 900 |
| | | EGAT Coal-Fired TH #3 | 800 |
| | | Bang Pakong CC #4 (Replaced) | 900 |
| Power Purchase | 600 | Power Purchase | 300 |
2026 | Renewables | 160 | Renewables | 254.4 |
| Cogeneration | 362 | Cogeneration | 180 |
| New Gas-fired Power Plant #10-11 | 2x800 | New Gas-fired Power Plant | 900 |
| EGAT Coal-Fired TH #4-5 | 2x800 | EGAT Nuclear Power Plant #1 | 1,000 |
| | | Bang Pakong CC #5 (Replaced) | 900 |
| Power Purchase | 600 | Power Purchase | 300 |
Appendix 3
Page 3
Comparison of Thailand Power Development Plans
(2027-2030)
Year | PDP2010 Revision 2 (NPEC 27 Apr 2011) | PDP2010 Revision 3 (NPEC 8 Jun 2012) |
Projects | MW | Projects | MW |
2027 | Renewables | 241 | Renewables | 315.2 |
| Cogeneration | 361 | Cogeneration | 180.9 |
| EGAT Nuclear Power Plant #3 | 1,000 | EGAT Nuclear Power Plant #2 | 1,000 |
| | | Wang Noi CC #1 (Replaced) | 900 |
| | | Bang Pakong CC #6 (Replaced) | 900 |
| Power Purchase | 600 | Power Purchase | 300 |
2028 | Renewables | 184 | Renewables | 269.5 |
| Cogeneration | 365 | Cogeneration | 4.8 |
| EGAT Coal-Fired TH #6-7 | 2x800 | EGAT Coal-Fired TH #4 | 800 |
| New Gas-fired Power Plant #12-13 | 2x800 | Wang Noi CC #2-3 (Replaced) | 2x900 |
| EGAT Nuclear Power Plant #4 | 1,000 | Gas Turbine #1 | 250 |
| Power Purchase | 600 | Power Purchase | 300 |
2029 | Renewables | 209 | Renewables | 266.1 |
| Cogeneration | 360 | South Bangkok CC #4 (Replaced) | 900 |
| EGAT Coal-Fired TH #8 | 800 | EGAT New Combined Cycle Power Plant | 900 |
| New Gas-fired Power Plant #14 | 800 | Gas Turbine #2 | 250 |
| Power Purchase | 600 | Power Purchase | 300 |
2030 | Renewables | 226.5 | Renewables | 294 |
| Cogeneration | 360 | Cogeneration | 0.9 |
| EGAT Coal-Fired TH #9 | 800 | EGAT New Combined Cycle Power Plant | 900 |
| New Gas-fired Power Plant #15 | 800 | Gas Turbine #3 | 250 |
| Power Purchase | 600 | Power Purchase | 300 |
Projection of Generating Capacity by Power Plant Types
PDP 2010 : Revision 3
Plant Types | Unit | Year |
2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | 2030 |
Renewable Energy - EGAT - SPP - VSPP - Plan RE - Import Subtotal | MW % | 3,459 10.1 | 3,477 9.5 | 3,483 8.8 | 3,552 8.2 | 3,557 7.8 | 4,082 8.6 | 4,105 8.5 | 4,159 8.1 | 4,165 8.3 | 4,168 7.9 | 4,169 7.4 | 4,182 7.4 | 4,185 7.0 | 4,188 6.9 | 4,190 6.6 | 4,252 6.5 | 4,270 6.4 | 4,284 6.2 | 4,325 6.1 |
MW % | 966 2.8 | 1,215 3.3 | 1,634 4.1 | 2,003 4.6 | 2,638 5.8 | 2,791 5.9 | 2,791 5.8 | 2,851 5.6 | 2,888 5.7 | 2,888 5.5 | 2,888 5.1 | 2,888 5.1 | 2,838 4.8 | 2,782 4.6 | 2,777 4.3 | 2,770 4.3 | 2,667 4.0 | 2,667 3.9 | 2,647 3.8 |
MW % | 759 2.2 | 1,531 4.2 | 1,712 4.3 | 1,795 4.2 | 1,875 4.1 | 1,951 4.1 | 2,038 4.2 | 2,110 4.1 | 2,191 4.4 | 2,270 4.3 | 2,338 4.2 | 2,384 4.2 | 2,438 4.1 | 2,474 4.1 | 2,507 3.9 | 2,540 3.9 | 2,571 3.8 | 2,603 3.8 | 2,636 3.7 |
MW % | - - | - - | 60 0.2 | 290 0.7 | 560 1.2 | 840 1.8 | 1,120 2.3 | 1,430 2.8 | 1,740 3.5 | 2,100 4.0 | 2,320 4.1 | 2,540 4.5 | 2,760 4.6 | 2,980 4.9 | 3,200 5.0 | 3,420 5.3 | 3,640 5.4 | 3,860 5.6 | 4,080 5.8 |
MW % | 2,105 6.1 | 2,105 5.8 | 2,105 5.3 | 2,105 4.9 | 2,105 4.6 | 2,105 4.5 | 2,764 5.7 | 3,984 7.8 | 3,984 7.9 | 4,284 8.1 | 4,584 8.2 | 4,884 8.6 | 5,184 8.7 | 5,484 9.1 | 5,784 9.0 | 6,084 9.4 | 6,384 9.5 | 6,684 9.6 | 6,858 9.7 |
MW % | 7,288 21 | 8,327 23 | 8,993 23 | 9,745 23 | 10,734 24 | 11,768 25 | 12,817 27 | 14,534 28 | 14,968 30 | 15,709 30 | 16,298 29 | 16,878 30 | 17,404 29 | 17,907 30 | 18,457 29 | 19,065 29 | 19,532 29 | 20,098 29 | 20,546 29 |
Combined Cycle - EGAT - IPP Subtotal | MW % | 6,866 20.0 | 6,866 18.8 | 8,417 21.3 | 9,317 21.6 | 9,317 20.5 | 9,003 19.1 | 8,364 17.3 | 8,364 16.3 | 7,723 15.3 | 8,623 16.3 | 9,523 17.0 | 8,851 15.6 | 10,651 17.9 | 11,551 19.1 | 12,451 19.5 | 14,251 21.9 | 16,051 24.0 | 17,851 25.7 | 18,751 26.5 |
MW % | 9,225 26.9 | 9,225 25.3 | 10,825 27.4 | 11,250 26.1 | 11,472 25.2 | 11,472 24.3 | 11,472 23.7 | 11,472 22.3 | 10,772 21.4 | 11,672 22.1 | 12,572 22.4 | 13,122 23.1 | 14,022 23.6 | 14,222 23.5 | 15,122 23.6 | 13,081 20.1 | 12,368 18.5 | 12,368 17.8 | 12,368 17.5 |
MW % | 16,091 47 | 16,091 44 | 19,242 49 | 20,567 48 | 20,789 46 | 20,475 43 | 19,836 41 | 19,836 39 | 18,495 37 | 20,295 38 | 22,095 39 | 21,973 39 | 24,673 41 | 25,773 43 | 27,573 43 | 27,332 42 | 28,419 42 | 30,219 44 | 31,119 44 |
Cogeneration - SPP - VSPP Subtotal | MW % | 2,340 6.8 | 3,510 9.6 | 3,780 9.6 | 4,320 10.0 | 4,770 10.5 | 5,490 11.6 | 6,169 12.8 | 6,704 13.1 | 6,614 13.1 | 6,594 12.5 | 6,624 11.8 | 6,763 11.9 | 6,313 10.6 | 6,313 10.4 | 6,493 10.1 | 6,673 10.3 | 6,673 10.0 | 6,673 9.6 | 6,673 9.4 |
MW % | 27 0.1 | 43 0.1 | 59 0.2 | 76 0.2 | 96 0.2 | 96 0.2 | 97 0.2 | 102 0.2 | 102 0.2 | 103 0.2 | 108 0.2 | 108 0.2 | 109 0.2 | 113 0.2 | 113 0.2 | 114 0.2 | 119 0.2 | 119 0.2 | 120 0.2 |
MW % | 2,367 7 | 3,553 10 | 3,839 10 | 4,396 10 | 4,866 11 | 5,586 12 | 6,266 13 | 6,806 13 | 6,716 13 | 6,697 13 | 6,732 12 | 6,871 12 | 6,422 11 | 6,426 11 | 6,606 10 | 6,787 10 | 6,792 10 | 6,792 10 | 6,793 10 |
Thermal Gas Turbine/Diesel Heavy Oil Heavy Oil/Natural Gas Lignite Coal Nuclear | - EGAT | MW % | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 4 0.0 | 254 0.4 | 504 0.7 | 754 1.1 |
- EGAT | MW % | 315 0.9 | 315 0.9 | 315 0.8 | 315 0.7 | 315 0.7 | 315 0.7 | 315 0.7 | 315 0.6 | 315 0.6 | 315 0.6 | 315 0.6 | 315 0.6 | 315 0.5 | 315 0.5 | 315 0.5 | 315 0.5 | 315 0.5 | 315 0.5 | 315 0.5 |
- EGAT - IPP | MW % | 2,204 6.4 | 2,204 6.0 | 1,152 2.9 | 1,152 2.7 | 1,152 2.5 | 1,152 2.4 | 1,152 2.4 | 1,152 2.2 | 1,152 2.3 | 1,152 2.2 | 1,152 2.1 | 1,152 2.0 | 1,152 1.9 | 1,152 1.9 | 1,152 1.8 | 576 0.9 | - - | - - | - - |
MW % | 1,510 4.4 | 1,510 4.1 | 1,510 3.8 | 1,510 3.5 | 1,440 3.2 | 1,440 3.1 | 1,440 3.0 | 1,440 2.8 | 1,440 2.9 | 1,440 2.7 | 1,440 2.6 | 1,440 2.5 | 1,440 2.4 | - - | - - | - - | - - | - - | - - |
- EGAT - Lao PDR | MW % | 2,180 6.4 | 2,180 6.0 | 2,180 5.5 | 2,180 5.1 | 2,180 4.8 | 2,180 4.6 | 2,180 4.5 | 2,180 4.2 | 2,180 4.3 | 2,180 4.1 | 2,180 3.9 | 2,180 3.8 | 2,180 3.7 | 2,180 3.6 | 2,180 3.4 | 2,180 3.4 | 2,180 3.3 | 1,910 2.8 | 1,640 2.3 |
MW % | - - | - - | - - | 982 2.3 | 1,473 3.2 | 1,473 3.1 | 1,473 3.1 | 1,473 2.9 | 1,473 2.9 | 1,473 2.8 | 1,473 2.6 | 1,473 2.6 | 1,473 2.5 | 1,473 2.4 | 1,473 2.3 | 1,473 2.3 | 1,473 2.2 | 1,473 2.1 | 1,473 2.1 |
- EGAT - IPP | MW % | - - | - - | - - | - - | - - | - - | - - | 800 1.6 | 800 1.6 | 800 1.5 | 1,600 2.9 | 1,600 2.8 | 1,600 2.7 | 2,400 4.0 | 2,400 3.8 | 2,400 3.7 | 3,200 4.8 | 3,200 4.6 | 3,200 4.5 |
MW % | 2,007 5.9 | 2,007 5.5 | 2,007 5.1 | 2,007 4.7 | 2,277 5.0 | 2,547 5.4 | 2,547 5.3 | 2,547 5.0 | 2,547 5.1 | 2,547 4.8 | 2,547 4.5 | 2,547 4.5 | 2,547 4.3 | 2,547 4.2 | 2,547 4.0 | 2,547 3.9 | 2,547 3.8 | 2,547 3.7 | 2,547 3.6 |
- EGAT | MW % | - - | - - | - - | - - | - - | - - | - - | - - | - - | - - | - - | - - | - - | - - | 1,000 1.6 | 2,000 3.1 | 2,000 3.0 | 2,000 2.9 | 2,000 2.8 |
Subtotal | MW % | 8,220 24 | 8,220 23 | 7,168 18 | 8,150 19 | 8,841 19 | 9,111 19 | 9,111 19 | 9,911 19 | 9,911 20 | 9,911 19 | 10,711 19 | 10,711 19 | 10,711 18 | 10,071 17 | 11,071 17 | 11,495 18 | 11,969 18 | 11,949 17 | 11,929 17 |
EGAT - TNB , HVDC | MW % | 300 0.9 | 300 0.8 | 300 0.8 | 300 0.7 | 300 0.7 | 300 0.6 | 300 0.6 | 300 0.6 | 300 0.6 | 300 0.6 | 300 0.5 | 300 0.5 | 300 0.5 | 300 0.5 | 300 0.5 | 300 0.5 | 300 0.5 | 300 0.4 | 300 0.4 |
Total | MW % | 34,265 100 | 36,491 100 | 39,542 100 | 43,157 100 | 45,530 100 | 47,240 100 | 48,329 100 | 51,386 100 | 50,389 100 | 52,912 100 | 56,135 100 | 56,732 100 | 59,509 100 | 60,477 100 | 64,007 100 | 64,979 100 | 67,012 100 | 69,358 100 | 70,686 100 |
Projection of Energy Generation by Fuel Types
PDP 2010 : Revision 3
Fuel Types | Unit | Year |
2012 | 2013 | 2014 | 2015 | 2016 | 2017 | 2018 | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | 2025 | 2026 | 2027 | 2028 | 2029 | 2030 |
Renewable Energy | - Domestic - Import Subtotal | GWh | 13,843 | 14,823 | 14,709 | 16,322 | 17,620 | 20,080 | 21,284 | 22,378 | 23,472 | 24,441 | 24,937 | 25,367 | 25,587 | 25,685 | 25,814 | 26,184 | 26,343 | 26,298 | 26,673 |
% | 7.9 | 8.1 | 7.7 | 8.1 | 8.4 | 9.1 | 9.3 | 9.5 | 9.5 | 9.6 | 9.4 | 9.2 | 9.0 | 8.7 | 8.5 | 8.3 | 8.1 | 7.8 | 7.7 |
GWh | 12,605 | 12,306 | 11,527 | 11,073 | 12,346 | 11,120 | 13,269 | 15,959 | 19,990 | 21,530 | 23,070 | 24,040 | 26,150 | 27,689 | 29,229 | 30,769 | 32,309 | 33,279 | 34,205 |
% | 7.2 | 6.7 | 6.0 | 5.5 | 5.9 | 5.1 | 5.8 | 6.8 | 8.1 | 8.4 | 8.7 | 8.8 | 9.2 | 9.4 | 9.6 | 9.8 | 9.9 | 9.9 | 9.9 |
GWh | 26,448 | 27,130 | 26,237 | 27,395 | 29,967 | 31,200 | 34,553 | 38,337 | 43,463 | 45,971 | 48,007 | 49,407 | 51,737 | 53,374 | 55,043 | 56,953 | 58,652 | 59,577 | 60,878 |
% | 15.1 | 14.8 | 13.7 | 13.7 | 14.2 | 14.2 | 15.2 | 16.2 | 17.7 | 18.0 | 18.1 | 18.0 | 18.2 | 18.1 | 18.1 | 18.1 | 18.0 | 17.7 | 17.6 |
Natural Gas / LNG | - EGAT/IPP | GWh % | 102,387 58.5 | 103,846 56.7 | 108,810 56.8 | 109,754 54.7 | 106,569 50.6 | 104,598 47.6 | 104,573 45.9 | 101,125 42.8 | 101,624 41.3 | 108,483 42.4 | 112,351 42.4 | 118,087 43.0 | 126,606 44.5 | 132,603 45.0 | 133,073 43.7 | 132,997 42.2 | 131,500 40.4 | 143,147 42.6 | 154,873 44.7 |
| | MMCFD | 2,166 | 2,178 | 2,217 | 2,211 | 2,102 | 2,051 | 2,039 | 1,978 | 1,974 | 2,096 | 2,173 | 2,279 | 2,435 | 2,551 | 2,568 | 2,576 | 2,539 | 2,763 | 2,975 |
| - SPP/VSPP | GWh | 10,627 | 17,350 | 21,250 | 24,823 | 28,756 | 32,859 | 37,475 | 42,475 | 43,789 | 43,971 | 44,115 | 43,917 | 43,865 | 44,225 | 45,013 | 45,751 | 46,286 | 46,286 | 46,288 |
| | % | 6.1 | 9.5 | 11.1 | 12.4 | 13.7 | 15.0 | 16.5 | 18.0 | 17.8 | 17.2 | 16.6 | 16.0 | 15.4 | 15.0 | 14.8 | 14.5 | 14.2 | 13.8 | 13.4 |
| | GWh | 113,013 | 121,197 | 130,060 | 134,577 | 135,325 | 137,456 | 142,048 | 143,600 | 145,412 | 152,454 | 156,466 | 162,004 | 170,470 | 176,828 | 178,086 | 178,748 | 177,786 | 189,434 | 201,161 |
| Subtotal | % | 64.6 | 66.1 | 67.9 | 67.1 | 64.3 | 62.6 | 62.4 | 60.8 | 59.1 | 59.6 | 59.0 | 59.0 | 59.9 | 60.1 | 58.5 | 56.8 | 54.6 | 56.4 | 58.0 |
| | MMCFD | 2,166 | 2,178 | 2,217 | 2,211 | 2,102 | 2,051 | 2,039 | 1,978 | 1,974 | 2,096 | 2,173 | 2,279 | 2,435 | 2,551 | 2,568 | 2,576 | 2,539 | 2,763 | 2,975 |
Import Coal | - EGAT/IPP - SPP Subtotal | GWh | 14,429 | 14,350 | 15,274 | 15,004 | 15,936 | 19,002 | 19,356 | 22,699 | 25,446 | 25,403 | 28,804 | 31,492 | 31,625 | 34,893 | 37,570 | 37,389 | 43,623 | 43,616 | 43,693 |
% | 8.2 | 7.8 | 8.0 | 7.5 | 7.6 | 8.7 | 8.5 | 9.6 | 10.3 | 9.9 | 10.9 | 11.5 | 11.1 | 11.9 | 12.3 | 11.9 | 13.4 | 13.0 | 12.6 |
MTons | 6 | 6 | 6 | 6 | 6 | 7 | 7 | 9 | 10 | 10 | 11 | 12 | 12 | 13 | 14 | 14 | 17 | 17 | 17 |
GWh | 2,168 | 2,123 | 2,055 | 2,027 | 2,132 | 2,589 | 2,528 | 2,523 | 2,523 | 2,523 | 2,523 | 2,523 | 1,472 | 158 | - | - | - | - | - |
% | 1.2 | 1.2 | 1.1 | 1.0 | 1.0 | 1.2 | 1.1 | 1.1 | 1.0 | 1.0 | 1.0 | 0.9 | 0.5 | 0.1 | - | - | - | - | - |
GWh | 16,596 | 16,473 | 17,328 | 17,032 | 18,068 | 21,591 | 21,884 | 25,221 | 27,969 | 27,926 | 31,326 | 34,015 | 33,097 | 35,051 | 37,570 | 37,389 | 43,623 | 43,616 | 43,693 |
% | 9.5 | 9.0 | 9.0 | 8.5 | 8.6 | 9.8 | 9.6 | 10.7 | 11.4 | 10.9 | 11.8 | 12.4 | 11.6 | 11.9 | 12.3 | 11.9 | 13.4 | 13.0 | 12.6 |
MTons | 5.66 | 5.63 | 6.07 | 5.89 | 6.32 | 7.35 | 7.49 | 8.74 | 9.77 | 9.75 | 11.02 | 12.03 | 12.08 | 13.31 | 14.31 | 14.24 | 16.57 | 16.57 | 16.60 |
Lignite | - EGAT - Lao PDR Subtotal | GWh | 16,749 | 16,696 | 16,736 | 16,738 | 16,614 | 17,120 | 17,030 | 17,024 | 17,077 | 17,031 | 17,031 | 17,039 | 17,090 | 17,041 | 17,037 | 17,019 | 17,078 | 14,910 | 12,786 |
% | 9.6 | 9.1 | 8.7 | 8.3 | 7.9 | 7.8 | 7.5 | 7.2 | 6.9 | 6.7 | 6.4 | 6.2 | 6.0 | 5.8 | 5.6 | 5.4 | 5.3 | 4.4 | 3.7 |
MTons | 16 | 16 | 16 | 16 | 16 | 16 | 14 | 14 | 14 | 14 | 14 | 14 | 14 | 14 | 14 | 14 | 14 | 12 | 10 |
GWh | - | - | - | 4,612 | 10,292 | 11,253 | 11,252 | 11,248 | 11,281 | 11,249 | 11,249 | 11,247 | 11,283 | 11,254 | 11,252 | 11,236 | 11,278 | 11,249 | 11,245 |
% | - | - | - | 2.3 | 4.9 | 5.1 | 4.9 | 4.8 | 4.6 | 4.4 | 4.2 | 4.1 | 4.0 | 3.8 | 3.7 | 3.6 | 3.5 | 3.4 | 3.2 |
GWh | 16,749 | 16,696 | 16,736 | 21,349 | 26,906 | 28,373 | 28,282 | 28,273 | 28,358 | 28,280 | 28,281 | 28,286 | 28,374 | 28,296 | 28,289 | 28,255 | 28,356 | 26,159 | 24,031 |
% | 9.6 | 9.1 | 8.7 | 10.6 | 12.8 | 12.9 | 12.4 | 12.0 | 11.5 | 11.1 | 10.7 | 10.3 | 10.0 | 9.6 | 9.3 | 9.0 | 8.7 | 7.8 | 6.9 |
MTons | 16.04 | 15.99 | 16.03 | 16.03 | 15.92 | 16.00 | 13.81 | 14.02 | 14.16 | 14.12 | 14.12 | 14.13 | 13.87 | 13.74 | 13.62 | 13.61 | 13.66 | 11.84 | 9.78 |
Nuclear | - EGAT | GWh % Tons | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | 4,600 1.5 9 | 12,620 4.0 25 | 16,090 4.9 32 | 16,042 4.8 32 | 16,046 4.6 32 |
Heavy Oil | GWh % MLiters | 1,944 1.11 499.43 | 1,366 0.75 353.32 | 876 0.46 222.08 | 168 0.08 36.18 | 166 0.08 36.06 | 32 0.01 - | 32 0.01 - | 16 0.01 - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - | - - - |
Diesel | - EGAT | GWh % MLiters | 130 0.1 29.10 | 133 0.1 31.86 | 172 0.1 40.60 | 75 0.0 20.92 | 55 0.0 13.47 | 26 0.0 7.00 | 23 0.0 6.30 | 23 0.0 6.30 | 21 0.0 5.61 | 21 0.0 5.60 | 21 0.0 5.60 | 21 0.0 5.60 | 21 0.0 5.61 | 21 0.0 5.60 | 21 0.0 5.60 | 21 0.0 5.60 | 21 0.0 5.61 | 21 0.0 5.60 | 21 0.0 5.60 |
EGAT - TNB , HVDC | GWh % | 209 0.1 | 290 0.2 | 221 0.1 | 131 0.1 | 132 0.1 | 939 0.4 | 939 0.4 | 939 0.4 | 941 0.4 | 939 0.4 | 939 0.4 | 939 0.3 | 941 0.3 | 939 0.3 | 939 0.3 | 938 0.3 | 941 0.3 | 938 0.3 | 938 0.3 |
Total | GWh | 175,089 | 183,283 | 191,630 | 200,726 | 210,619 | 219,616 | 227,760 | 236,408 | 246,164 | 255,591 | 265,039 | 274,672 | 284,640 | 294,508 | 304,548 | 314,925 | 325,470 | 335,787 | 346,767 |