Department of Energy
2012-2016 MISSIONARY ELECTRIFICATION DEVELOPMENT PLAN (2012 MEDP)
14 March 2012
1. Introduction
The 2012-2016 Missionary Electrification Development Plan (2012 MEDP) is an outline of the Government’s plans to improve the conditions prevailing in missionary areas1. The 2012 MEDP focuses specific plans and projects for the next five years.
With funding support from the World Bank (WB) and the Global Environment Facility (GEF) through the Philippine Rural Power Project, Trust Fund No. TF 52188, the Department of Energy (DOE) engaged Innovation Energie Développement (IED) to review the missionary electrification framework and its current status and thereafter initiate the preparation of the 2012 MEDP for the DOE. We thank IED for producing a report depicting a clear status of missionary electrification in the country, and WB and GEF for the Technical Assistance provided to further enhance and remove the barriers of renewable energy development in missionary areas. Data and insights presented by IED were discussed and studied by DOE in determining what needs to be done.
The 2012 MEDP is intended to serve as the blueprint on which missionary electrification policy actions in the next five years will be based, and will evolve as necessitated by circumstances. The intended audiences of this document are industry participants in Small Islands and Isolated Grids (SIIGs), specifically the National Power Corporation - Small Power Utilities Group (NPC-SPUG), potential New Power Providers (NPPs) and Qualified Third Parties (QTPs), Distribution Utilities (DUs), the National Electrification Administration (NEA), and the Energy Regulatory Commission (ERC).
1.1. Current Status of Missionary Electrification
1.1.1. Existing NPC-SPUG Services
NPC-SPUG remains the dominant generation service provider to SIIGs. In 2011, NPC-SPUG’s total generation stood at 463 GWh. Except for 5.8 GWh generated by Balongbong Hydroelectric Power Plant in Catanduanes, energy was produced entirely by diesel- and Bunker C-fueled generators.
For 2011, the overall fuel rate for NPC-SPUG is 0.283 L/kWh, while the overall plant use and losses are at 4.51% of gross generation. While the numbers imply overall efficiency, this is not the case on a plant-by- plant basis as shown in Table 1.
1 Those which cannot be served in the foreseeable future in a financially feasible way by the extension of TransCo’s transmission grid.
2011 Gross MWh | Plant Count | Fuel Rate | Plant Use and Losses |
Group Average | Weighted Average | Group Average | Weighted Average |
<120 | 192 | 0.508 | 0.450 | 0.69% | 3.16% |
(120, 600] | 45 | 0.324 | 0.321 | 3.24% | 3.56% |
(600, 1200] | 12 | 0.311 | 0.310 | 6.34% | 6.22% |
(1200, 12000] | 28 | 0.293 | 0.277 | 6.23% | 5.93% |
>12000 | 10 | 0.283 | 0.281 | 4.67% | 3.85% |
Table 1. Fuel Rates and Plant Use and Losses in 2011
NPC-SPUG operates numerous small power plants and a handful of large power plants. As a matter of fact, merely 15 power plants, all serving First Wave Areas (FWAs) account for more than 75% of the 2011 gross generation in NPC-SPUG areas.
Small SIIG operations are relatively more expensive. For example, as shown in Table 2, employee wages for Balabac, a small SIIG, are even higher than those for Rapu-Rapu, a medium-sized SIIG, but the potential revenues are only proportional to the gross generation. NPC- SPUG’s overextended deployment of materials and personnel is one reason why its operations are not optimized.
Plant | Employees | Labor Cost, kP | Gross Generation, MWh | Plant production Cost, P/kWh |
Total | Per employee | Total | Per employee |
Rapu-Rapu | 10 | 109 | 10.9 | 107.5 (Medium) | 10.75 | 14.4 |
Balabac | 8 | 146 | 18.25 | 27.6 (Small) | 3.45 | 23.9 |
Table 2. Comparison of the December 2011 Operations of Rapu-Rapu and Balabac Diesel Power Plants
In many areas, supply interruptions, mostly of long duration, are often experienced. Fuel shortage, generator failures and distribution side faults were the dominant reasons for the interruptions. Worse, NPC- SPUG does not monitor these outages and fails to produce SAIFI and SAIDI statistics2.
Based on NPC-SPUG’s requirements, the aggregated shortfall that is not covered by the Universal Charge for Missionary Electrification (UCME) for 2009-2011 amounted to Php6 Billion. However, the 2012 MEDP will not delve into this matter as this had been filed before ERC.
2 System average interruption frequency index (SAIFI) and System average interruption duration index (SAIDI) describe how often interruptions occur and how long they persist.
Also contributing to NPC-SPUG’s poor financial standing are DUs’ overdue accounts amounting to as much as Php3 Billion as of end- 2010.
1.1.2. NPPs
As of this writing, eight NPPs are supplying five of the 14 FWAs as shown in Table 3.
SIIG | NPP | Installed Capacity | 2010 Generation, MWh | October 2011 Supply Cost, P/kWh |
Oriental Mindoro | Power One | 9-MW bunker- fueled diesel | N/A, stopped in 2009 | ≈ 12 |
Ormin Power | 6.4-MW bunker- fueled diesel | N/A, commenced 2011 | 12.69 |
Mainland Palawan | Palawan Power Generation (PPGI) | 19-MW bunker- fueled diesel | 60,277 | 10.686 |
Delta P | 16-MW bunker- fueled diesel | 57,412 | 12.1 |
Catanduanes | Catanduanes Power Generation (CPGI) | 3.6-MW bunker- fueled diesel | 14,901 | ≈ 12 |
Sunwest Water and Electric (SUWECO) | 3.6-MW hydro | 2,296 | 5.39 |
Bantayan Island | Bantayan Island Power Corp. (BIPCOR) | 8.3-MW bunker- fueled diesel | 17,309 | 10.5015 |
Masbate | DMCI | 24.4-MW bunker-fueled diesel | 29,323 since July 2010 | 15.4 |
Table 3. NPPs in 5 SIIGs
NPPs’ supply costs are significantly lower than NPC-SPUG’s average O&M costs in 2011 which are in the order of 15-16 P/kWh. That the NPPs have lower supply costs is partly due to the use of Bunker C as fuel for the diesel generators. Generators that were running on diesel when operated by NPC-SPUG were converted such that they are now running on Bunker C. Also, all NPPs provide 24-hour supply of electricity. These cost and performance benefits dictate that private sector participation (PSP) be pursued.
In areas other than Masbate and Bantayan Island, NPC-SPUG continues to perform as the power supplier because either the NPP’s generation capacity is not sufficient to meet the DU’s demand, or the NPP has not complied with its contractual obligations due to various
factors. As an example, in the areas of Marinduque, Tablas and Romblon, 3i Power Gen which was awarded the NPP contract through Competitive Selection Process (CSP), signed PSAs with the respective DUs but has not yet operated any power plant. Because of the alleged delays and failure of 3iPower Gen to deliver its obligations under the PSAs with the three DUs, there were moves to declare these PSAs null and void.
Table 4 shows the status of PSP in the nine other FWAs.
SIIG | NPP | Status |
Marinduque | 3i Power | With PSA but without any generating equipment installed. |
Tablas | 3i Power | With PSA but without any generating equipment installed. |
Romblon | 3i Power | With PSA but power plant is not operational due to internal problems within NPP consortium. |
Tawi-Tawi | | Not feasible for NPPs. |
Sulu (Jolo) | | Not feasible for NPPs. |
Siquijor | | CSP ongoing. |
Basilan | | With PSA but without any generating equipment installed. |
Camotes | | No CSP yet. |
Occidental Mindoro | | CSP to start. |
Table 4. PSP Status of 9 SIIGs
While PSP in the 14 FWAs did not progress as intended, there are areas where the private sector supplies at least a portion of the demand. In contrast, SIIGs with peak demand less than 1 MW may not be expected to be taken over by NPPs if CSP is conducted as usual.
1.1.3. QTPs
PowerSource Philippines, Inc. (PSPI), which operates in Rio Tuba, Bataraza, Palawan is the only recognized QTP following the policies and regulatory actions issued by DOE and ERC, respectively. PSPI provides 24-hour electricity service to 1,374 households. Its average monthly sales increased from 70 MWh in 2010 to 100 MWh in 2011. PSPI’s installed capacity is 420 kW, which it will augment with a 70-kW biomass gasifier fueled by coconut and wood chips by the first quarter of 2012.
Meanwhile, the Philippine Rural Electrification Service (PRES) Project in Masbate was financed by concessional and commercial loans through the Filipino-French Protocol. Said project accomplished electrification of 5,129 households in 108 barangays through PV systems and 12,183 households in 102 barangays through small diesel-fired mini-grid systems. Currently, NPC-SPUG acts as the interim QTP for the PRES areas. For the mini-grid component, the 2011 gross generation is 43.7 MWh, a mere 0.4% of the total NPC- SPUG production. The sustainability of the PRES Project is at risk due to continued non-appointment of a full time QTP or alternative service provider, or employment of a sustainable and cost-effective post- project operation and maintenance program.
Missionary areas account for a very minimal share of the national energy sales but have a large impact to the entire economy. Hence, in the interest of national development, DOE shall ensure that the conditions prevailing in missionary areas are improved, consistent with the objectives of Republic Act No. 9136, the Electric Power Industry Reform Act of 2001 (EPIRA).
1.2. Goals and Objectives
It is a declared policy of the State to ensure the quality, reliability, security, and affordability of the supply of electric power 3. Anchoring on this policy, the two strategic goals of the 2012 MEDP are 1) the minimization of nationwide UCME burden and 2) the improvement of supply reliability.
The specific objectives to meet these goals in five years are as follows:
- Minimize UCME Burden
a. Introduce PSP in large areas and some medium areas
- Amend/establish PSP Department Circulars (DCs)
- Create an Inter-Agency Technical Working Group
- Create Steering Committee
b. Promote 1 MW peak demand in some medium areas
- Establish PSP template DC
- Pilot El Nido PSP using business franchise model
- Coordinate with local stakeholders
- Coordinate with ERC for regulatory support
c. Pull out NPC-SPUG from some small areas
- Market to QTPs
- Revert to DUs, establish BAPAs
- Coordinate with local stakeholders
- Coordinate with ERC for regulatory support
- Coordinate with NPC-SPUG and NEA for capacity- building
d. Promote power plant efficiency in NPC-SPUG's plants
- Establish comprehensive technical policy
- Establish DC for fuel rates and plant use and losses
3 EPIRA Section 2(b).
e. Monitor NPC-SPUG’s technical performance
- Enforce timely submission of data
- Establish grading system
f. Implement subsidy graduation and inter-class subsidy
- Coordinate with local stakeholders
- Coordinate with ERC for regulatory support
- Coordinate with NEDA for a detailed economic study
g. Establish NPC-SPUG's future roles
h. Create integrated power development plan for each SIIG
2. Increase Supply Reliability
a. Establish comprehensive technical policy
- Establish DC for generation and distribution reliability
- Closely monitor fuel deliveries
- Coordinate with ERC for regulatory support for capital expenditures
- Establish NPC-SPUG's future roles
These specific objectives of the 2012 MEDP are subdivided into five headings: 1) private sector participation, 2) technical efficiency, 3) UCME rationalization, 4) NPC-SPUG’s future roles, and 5) expectations from stakeholders. In addition, this simple document serves to reaffirm DOE’s commitment to develop missionary areas by providing clear policy directions.
- Private Sector Participation
EPIRA IRR Rule 13 mandates DOE to issue specific guidelines on how to encourage the inflow of private capital and the manner whereby other parties can participate in missionary electrification projects. In compliance, DOE issued DC 2004-01-001 prescribing the rules and procedures for PSP in existing NPC-SPUG areas.
The appendix lists all of NPC-SPUG’s power plants and the classification of their respective areas.
1.1. Large NPC-SPUG Areas
For the purposes of the 2012 MEDP, the term “large NPC-SPUG areas” refers to the 14 FWAs and Busuanga Island. Said areas account for 82% of NPC-SPUG’s 2011 gross generation.
The 14 FWAs are allocated around 80% of UCME and are thus prioritized in the PSP Program. However, there are hindrances to successful implementation of PSP. To accelerate PSP implementation in the 14 FWAs, DOE, NEA and NPC entered into a Memorandum of Agreement (MOA) entitled “Enhanced Private Sector Participation Program in Existing NPC- SPUG Areas” on 21 October 2011
Toward this end, DC 2004-01-001, the principal policy instrument which prescribes the rules and procedures for PSP, will be amended or superseded by another circular by end-2012 to consider the following points:
- Definition of the elements or determinants of CSP to include the recognition of (1) pioneer bids4 that will be subjected to the Swiss Challenge method, and (2) bids of RE generators with true cost of generation (TCGR) less than the subsidized/approved generation rate (SAGR) and with sufficient capability to operate as base load plant or provide full service.
- Competency building of DUs on power supply contracting with the private sector and strategic planning for least cost and technology- neutral generation development.
To accomplish the above tasks, an Inter-Agency Technical Working Group will be formed by the PSP Steering Committee. Once the above policy measures are in place, CSP shall be conducted for large areas based on the rules.
4 More popularly known as unsolicited bids.
1.2. Medium NPC-SPUG Areas
For the purposes of the 2012 MEDP, the term “medium NPC-SPUG areas” refers to SIIGs with 2011 gross generation significantly higher than 1 GWh. These are listed in Table 5.
# | SIIG | 2011 Gross GWh | December 2011 Peak, MW |
1 | Rapu-Rapu | 1.24 | 0.420 |
2 | Tingloy | 1.38 | 0.600 |
3 | Taytay | 1.49 | 0.579 |
4 | San Vicente | 1.62 | 0.490 |
5 | Siasi | 2.62 | 0.560 |
6 | El Nido | 2.71 | 0.874 |
7 | Lubang | 2.83 | 0.684 |
8 | Casiguran | 2.96 | 1.000 |
9 | Polilio | 3.41 | 1.026 |
10 | Cuyo | 4.05 | 1.135 |
11 | Basco | 4.46 | 0.839 |
12 | Roxas | 4.95 | 1.080 |
13 | Ticao | 5.37 | 1.200 |
14 | Dinagat | 8.01 | 2.456 |
15 | Kalamansig5 | 8.98 | 2.059 |
Table 5. Medium NPC-SPUG Areas
These are DOE’s 15 Second Wave Areas (SWAs) to be opened for PSP. Areas numbered 8 to 15 in Table 5, having a strong demand profile, are expected to be taken over by NPPs in the same manner as large NPC-SPUG areas.
Owing to their different nature, a business model specific to areas numbered 1 to 7 in Table 6 will be crafted. The goal is to raise the viability level by promoting attainment of 1 MW peak load to enhance marketability to NPPs.
El Nido, having the highest peak demand among areas 1 to 7, will serve as the pilot area for implementation. DOE is looking into adopting the business franchising model6 to SWAs. Other goals of this venture are to provide a quick response to El Nido’s energy problems and formulate a template for PSP in medium NPC-SPUG areas. It will also be determined which one between bundled and individual packaging of medium SIIGs is more feasible.
5 Excluding the contributions of PB 111.
6 The model is such that NPC-SPUG is to the business owner as the NPP is to the franchisee. DOE aims to introduce even small businessmen to the generation business.
1.3. Small NPC-SPUG Areas
Areas that do not satisfy the definition of large and medium SIIGs in this document are referred to as small NPC-SPUG areas. A distinction will be made between small A, small B, and PRES mini-grids.
1.3.1. Small A Areas
For the purposes of the 2012 MEDP, the term “small A areas” refers to small areas with 2011 gross generation above 50 MWh, including Palanan7. Numbering 61, the demand in, these areas is large enough to be supplied by NPC-SPUG with some degree of economy yet may not be large enough to merit NPP interest. It is reasonable to expect no NPP takeover of small A areas in the next five years.
1.3.2. Small B Areas
For the purposes of the 2012 MEDP, the term “small B areas” refers to small areas with 2011 gross generation below 50 MWh, excluding Palanan and the PRES mini-grids. Numbering 29, these are either mini-grids or transferred areas8. Small B areas will be marketed to potential QTPs as appropriate. Those that will not merit private sector interest by January 2013 will be reverted to parent DUs through BAPAs in line with their franchise obligation.
1.3.3. PRES Mini-grids
Basing on the gross generation share alone, it appears that the PRES problem requires massive effort but promises little gain. However, the success of the project is a matter of national interest as it will affect the Government’s reputation with donor countries, especially France and the rest of the European Union.
The problems with the PRES areas include high fuel rates, poor metering, poor maintenance, and low collection efficiency. These will be addressed by DOE in formulating plans to emplace QTP take-over by June 2013.
7 Palanan DPP was not operational from January to October 2011 so its 2011 gross generation is only 31 MWh.
8 Areas where the generation function was taken over by NPC-SPUG from DUs or local government units (LGUs).
- Technical Efficiency
NPC-SPUG runs primarily on UCME. Therefore, any inefficiency incurred by NPC-SPUG amounts to wastage of government resources. NPC-SPUG also depends on collections from DUs. Therefore, to increase collection efficiency, generation and distribution of energy must be reliable.
It has been an issue in the past that there is a lack of technical standards, whether internal to NPC or industry-wide, regarding efficiency. To ensure the good performance of the industry participants in SIIGs, DOE shall take the initiatives to provide directions to NPC-SPUG and SIIG DUs regarding technical efficiency. These initiatives are detailed in the succeeding parts of this 2012 MEDP.
2.1. Improvement of Performance
Requiring simple analyses, a transitory policy will be useful in the meantime to improve performance. Two such circulars will be emplaced by end-2012:
- A DOE circular prescribing transitory guidelines on allowable fuel rates and plant use and losses of NPC-SPUG power plants will be released by March 2012. Covering 50 power plants, its projected savings are in the order of 170 MP.
- A DOE circular prescribing transitory guidelines for generation and distribution reliability will be released by July 2012.
By 2013, a comprehensive technical policy will be emplaced. It will be based on careful and deliberate study by DOE and its attached agencies of NPC- SPUG’s operations data and the developments arising from the transitory circulars.
2.2. Monitoring of NPC-SPUG’s Performance
DOE will continuously monitor NPC-SPUG’s technical performance. A set of parameters required by DOE on a monthly basis was already forwarded to NPC-SPUG. From data to be submitted, quantities such as energy sales variations, running hours, fuel and lube component of loss and lube-fuel ratio will be determined. The results will be compared to benchmarks and interpreted accordingly. DOE will report its findings to the Secretary for incorporation to NPC-SPUG’s “scoreboard”.
Further, DOE will monitor fuel supply in NPC-SPUG areas on a weekly basis.
- UCME Rationalization
3.1. NPC-SPUG’s UCME Requirements
Except those in the mini-grids, the operating hours of some NPC-SPUG power plants will increase through 2012-2016, enabling the availability of power supply for at least 16 hours on the average (Table 6).
Planned hours | Percent of grids |
Year | 2010 | 2012 | 2013 | 2014 | 2015 | 2016 |
24 | 31% | 35% | 39% | 37% | 44% | 44% |
18-20 | 9% | 8% | 4% | 5% | 8% | 12% |
12-16 | 21% | 30% | 33% | 41% | 42% | 42% |
8-10 | 28% | 20% | 20% | 15% | 6% | 3% |
6 | 12% | 8% | 5% | 1% | - | - |
Average (hours) | 13.5 | 16.0 | 16.4 | 16.7 | 18.4 | 18.9 |
Table 6. Planned Operating Hours
While being responsive to the development needs of the areas, such an increase in the operating hours must ensure an improvement of plant performance (as discussed in the preceding section on Technical Efficiency) on two points:
- higher efficiency of power supply in terms of optimization of fuel consumption, and
- higher quality of power supply in terms of reduction of frequency and duration of supply interruptions.
In the mini-grids, NPC-SPUG, as the interim service provider, will maintain its service level to facilitate assumption of the concerned DUs or QTPs.
On the other hand, two transmission projects are emphasized for prioritization because they are urgent and critical to support the private investment in generation capacities by the NPPs in Catanduanes and Masbate: construction of the 69-kV Condon–Virac–Viga line (82 ckm), rehabilitation of the 69-kV Mobo–Aroroy line (49 ckm) and construction of the 69 kV Mobo– Cataingan line (75 ckm).
The corresponding UCME requirements for 2012-2016 for NPC-SPUG’s cost of generation including the increase in operating hours are shown in Table 7. Fuel cost accounts for 75% of NPC-SPUG’s cost of generation. This means that a substantial shortfall in UCME approval would lead to curtailment of service hours.
Item, BP | 2012 | 2013 | 2014 | 2015 | 2016 |
A | Fuel Cost | 6.72 | 7.93 | 9.53 | 11.03 | 13.07 |
B | Payroll | 0.76 | 0.93 | 0.93 | 0.93 | 0.93 |
C | Maintenance and Other Operating Expenses | 1.67 | 1.95 | 2.05 | 2.15 | 2.26 |
D=A+B+C | Subtotal Operating Expenses | 9.15 | 10.82 | 12.51 | 14.11 | 16.25 |
E | Depreciation | 0.35 | 0.34 | 0.34 | 0.34 | 0.34 |
F=D+E | Cost of Generation | 9.50 | 11.15 | 12.84 | 14.45 | 16.59 |
G | Estimated Revenue | 2.98 | 3.48 | 3.60 | 3.80 | 4.02 |
H=F-G | UCME Subsidy | 6.52 | 7.68 | 9.24 | 10.65 | 12.57 |
P/kWh Equivalent | 0.1007 | 0.1185 | 0.1427 | 0.1644 | 0.1941 |
Table 7. UCME Requirements of NPC-SPUG for 2012-2016
The total UCME requirements are shown in Table 8. Capital subsidy for both generation and transmission accounts for 19% of the total requirements. This means that a substantial shortfall in UCME approval would lead to delays in rehabilitation and/or repair of aging generation facilities and construction of transmission lines.
Item, BP | 2012 | 2013 | 2014 | 2015 | 2016 |
NPC-SPUG Operations | 6.52 | 7.68 | 9.24 | 10.65 | 12.57 |
NPP and QTP Subsidy | 1.52 | 2.21 | 2.36 | 2.48 | 2.58 |
Capital Subsidy | 1.92 | 2.44 | 2.86 | 3.74 | 2.37 |
Total UCME | 9.96 | 12.33 | 14.46 | 16.87 | 17.52 |
P/kWh Equivalent | 0.1538 | 0.1903 | 0.2232 | 0.2605 | 0.2706 |
Table 8. Total UCME Requirements for 2012-2016
3.2. Regulatory Support
For transparency and better management of UCME funds, it is highly recommended that ERC itemize its approval of UCME as follows: (1) existing NPC-SPUG operations, (2) capital subsidy, (3) NPP subsidy, and (4) QTP subsidy. It is important that ERC approve of critical CapEx projects in order to implement in a timely basis those projects that will result in a more reliable and adequate electricity supply.
3.3. Other Initiatives to Rationalize the UCME
In consultation with the ERC, the DOE plans to implement some enhancements in the existing policies to rationalize the UCME and while providing better electricity services in missionary areas. These are as follows:
3.3.1 Implementation of Subsidy Graduation Program
DOE will initiate graduation from UCME subsidy as prescribed in DC 2004-01-001, in coordination with ERC. Higher rates will merit complaints from end-users but not so much when coupled with increased reliability. This was evident from DOE’s field inspection of barangay-operated diesel generators in Cagbalete Island, Mauban, Quezon where residents pay as much as 55 P/kWh for a mere seven hours of service. Therefore, this program will go hand in hand with technical policies on reliability and require utmost study and even coordination with the National Economic and Development Authority.
Most importantly, the consumers themselves, through DUs and LGUs, will be educated on the difficult realities inherent to SIIG generation. They will be made to understand that NPC-SPUG runs on limited funds and that non-graduation from subsidy will continue to impact the economy as a whole.
3.3.2 Implementation of Inter-class Subsidy Within the Same SIIG
Subsidy graduation will not be abruptly felt by residential consumers with low consumption in SIIGs. They will be subsidized by consumers with high electricity consumption through the implementation of inter- class subsidy. DOE envisions studying the rates to be applied as a function of monthly consumption and initiate implementation in coordination with the consumers.
3.3.3 Incentives for Renewable Energy in SIIGs
Republic Act No. 9513, the Renewable Energy (RE) Law, mandates that RE developers in missionary areas shall be entitled to a cash generation-based incentive chargeable against UCME. In line with this, on 22 August 2011, ERC passed Resolution No. 2011-21 where it amended the guidelines for the setting and approval of rates and subsidies for missionary areas. ERC prescribed that NPC-SPUG should include cash incentives to its UCME petitions.
The formula for cash incentive is given by,
50% of (TCGR - SAGR) x generated kWh.
In the interest of rationalizing UCME, DOE provides the following policy directions to guide ERC on the manner of implementation:
- Backed up by a concrete study, a BNE rate that will serve as cap for TCGR shall be established for each RE type and installed capacity to prevent abuse of cash incentive. If possible, this should be done before RE developers participate in CSP.
- SAGR for all SIIGs that will employ RE resources with TCGR > SAGR shall automatically increase by a certain rate to be determined by ERC from start of operations. This is to lessen the impact of cash incentives to the national consumer base.
- The “generated kWh” factor in the formula shall refer to the energy sales, not the gross generation. This is to ensure that RE developers operate in the most effective manner.
- Future Roles of NPC-SPUG
This is to provide clarity to NPC-SPUG’s future roles, taking into account that generation in some SIIGs will be assumed by the private sector. NPC-SPUG may then plan ahead with less uncertainty especially regarding its human resource management.
4.1. Financial
NPC-SPUG shall remain the UCME petitioner to ERC. As applicable, NPC- SPUG shall adjust its TCGR to more accurately reflect the generation cost.
NPC-SPUG shall remain the disburser of UCME to NPPs and QTPs. In accordance with Section 3.2, it is recommended that separate trust funds be created for the following specific uses: (1) existing NPC-SPUG operations, (2) NPP subsidies, and (3) QTP subsidies. This is to ensure greater transparency and clear accounting of public funds, i.e., UCME subsidy.
4.2. Large NPC-SPUG Areas
NPC-SPUG is expected to cease generation functions in dispatchable9 FWAs. However, in accordance with the Small Grid Guidelines being drafted by DMC as of this writing, NPC-SPUG will only be the System Operator in large SIIGs, especially as there will be multiple generators. This is in view of the legal and ownership issues in many NPC-SPUG areas where DUs own and operate the electricity distribution system.
4.3. Medium NPC-SPUG Areas
For SIIGs Casiguran, Polilio, Cuyo, Basco, Roxas, Ticao, Dinagat, and Kalamansig which form the first half of the 15 SWAs, NPC-SPUG is expected to cease generation functions within the next five years as these have a high probability of being taken over by NPPs in the same manner as large areas.
As adopting the business franchising model is being explored by DOE for some medium SIIGs, NPC-SPUG may reasonably expect to provide technical support to incoming NPPs which will probably be small players. SIIGs Rapu- Rapu, Tingloy, Taytay, San Vicente, Siasi, El Nido, and Lubang which form the second half of the SWAs, will most likely be under the private sector for the next five years under the business franchising scheme. NPC-SPUG will provide management and operations training to NPP personnel for at most a year after NPP takeover.
9 Not all FWAs are reasonably expected to be taken over by NPPs, specifically the Tawi-Tawi and Sulu (Jolo) SIIGs.
4.4. Small NPC-SPUG Areas
Within the next five years, it is envisioned that NPC-SPUG will have no more participation in Small B Areas, while continuing to provide generation service to Small A Areas. Further, it is best that NPC-SPUG should no longer assume responsibilities in or take over areas where it does not currently operate.
In the case of the PRES Project, NPC-SPUG is enjoined to accelerate the appointment of a QTP and limit itself in the monitoring of the QTP performance in the areas as well as eventual payments of loans under the Filipino-French Protocol.
- Expectations from Stakeholders
The mandate provided by EPIRA to NPC-SPUG as the government-owned and controlled corporation that will perform the missionary electrification function entails it to be the principal implementer of the MEDP. However, NPC-SPUG cannot perform in isolation and will need the cooperation and support of the ERC, NEA and DOE.
The 2012 MEDP recognizes the contribution of these agencies in meeting its goals and objectives.
5.1. ERC
As the rate-making authority, ERC is expected to rationalize UCME subsidy through the following:
- Approval of an adequate amount of subsidy to ensure sustainable and cost-effective NPC-SPUG operations.
- Transparent allocation of subsidy for each SIIG with equitable treatment to NPC-SPUG, NPPs, and QTPs.
- Regulatory support to subsidy graduation and inter-class subsidy through programmed increases in SAGR.
- Reconsideration on the provision of incentives to RE developers from UCME to preserve the integrity of CSP and minimize UCME burden.
5.2. NEA
In line with its mandate to modernize DUs in the milieu of the restructured electric power industry, NEA’s participation is expected on the following:
- DUs’ competency building on power supply contracting with the private sector and strategic planning for least cost and technology-neutral generation development.
- Crafting of technical guidelines on distribution reliability with DOE.
- Establishment and strengthening of BAPAs by providing technical and financial assistance to enable them to take over small B areas.
- Promotion of the subsidy graduation and inter-class subsidy programs.
5.3. DOE
DOE is mandated by EPIRA to supervise the restructuring of the electricity industry and to ensure adequate supply of electricity. In the interest of national development, DOE shall ensure that the conditions prevailing in missionary areas are improved.
Therefore, let this MEDP serve to reaffirm DOE’s commitment to develop missionary areas by providing clear policy directions, promoting transparency, and ensuring good governance in the provision of missionary electrification services. DOE is appreciative of and highly encourages constructive criticism from industry participants but expects utmost cooperation from all stakeholders of missionary electrification.
Appendix
List of NPC-SPUG’s Power Plants
Sector | Plant | 2011 Gross MWh | Class |
Occidental Mindoro | PB 106 | 29181.39 | LARGE |
| PULANG LUPA DPP | 15764.37 | LARGE |
Oriental Mindoro | CALAPAN RENTAL | 111189.4 | LARGE |
| MAMBURAO DPP | 13593.86 | LARGE |
Palawan | EL NIDO DPP | 2713.617 | MEDIUM |
| IRAWAN 15MW MODULAR | 13876.46 | LARGE |
| RIZAL DPP | 486.814 | SMALL |
| ROXAS DPP | 4948.664 | MEDIUM |
| SAN VICENTE DPP | 1618.151 | MEDIUM |
| TAYTAY DPP | 1488.185 | MEDIUM |
Catanduanes | BALONGBONG HEPP | 5810.112 | LARGE |
| MARINAWA DPP | 9570.077 | LARGE |
| PB 110 | 385.06 | LARGE |
| VIGA DPP | 248.599 | LARGE |
Masbate | MASBATE DPP | 35.655 | LARGE |
Marinduque | BOAC DPP | 13107.73 | LARGE |
| PB 120 | 22700.36 | LARGE |
| TORRIJOS DPP | 61.001 | LARGE |
Tablas | TABLAS DPP | 19610.39 | LARGE |
Romblon | PB 109 | 2361.423 | LARGE |
| PB 114 | 4034.474 | LARGE |
| ROMBLON DPP | 1518.884 | LARGE |
Camotes | CAMOTES DPP | 7293.494 | LARGE |
Siquijor | PB 113 | 3643.188 | LARGE |
| PB 116 | 1339.052 | LARGE |
| SIQUIJOR DPP | 10005.13 | LARGE |
Tawi-Tawi | BONGAO DPP | 2569.519 | LARGE |
| PB 108 | 11836.64 | LARGE |
Basilan | BASILAN DPP | 11776.25 | LARGE |
| PB 119 | 21001.29 | LARGE |
Sulu | JOLO DPP | 38777.45 | LARGE |
Catanduanes / Masbate | BATAN DPP | 440.778 | SMALL |
| RAPU-RAPU DPP | 1243.359 | MEDIUM |
| TICAO DPP | 5370.137 | MEDIUM |
Marinduque / Quezon / N. Luzon | BASCO DPP | 4463.424 | MEDIUM |
| CALAYAN DPP | 247.614 | SMALL A |
| CASIGURAN DPP | 2961.825 | MEDIUM |
| ITBAYAT DPP | 345.732 | SMALL A |
| JOMALIG DPP | 208.002 | SMALL A |
| KABUGAO DPP | 614.518 | SMALL A |
| LUBUAGAN DPP | 306.059 | SMALL A |
| PALANAN DPP | 30.988 | SMALL A |
| PATNANUNGAN DPP | 424.819 | SMALL A |
| POLILIO DPP | 3412.033 | MEDIUM |
| SABTANG DPP | 295.621 | SMALL A |
Mindoro / Romblon | BANTON DPP | 283.565 | SMALL A |
| CABRA DPP | 47.791 | SMALL B |
Sector | Plant | 2011 Gross MWh | Class |
| CONCEPCION DPP | 331.674 | SMALL A |
| CORCUERA DPP | 659.846 | SMALL A |
| LUBANG DPP | 2828.623 | MEDIUM |
| PALUAN DPP | 802.887 | SMALL A |
| SAN JOSE DPP | 512.269 | SMALL A |
| SIBUYAN DPP | 833.439 | SMALL A |
| TINGLOY DPP | 1376.55 | MEDIUM |
Palawan Area | AGUTAYA DPP | 147.851 | SMALL A |
| ARACELI DPP | 342.184 | SMALL A |
| BALABAC DPP | 297.791 | SMALL A |
| BUSUANGA DPP | 9427.039 | LARGE |
| CAGAYANCILLO DPP | 184.85 | SMALL A |
| CULION DPP | 964.495 | SMALL A |
| CUYO DPP | 4051.197 | MEDIUM |
| LINAPACAN DPP | 160.247 | SMALL A |
E. Visayas | ALMAGRO DPP | 140.324 | SMALL A |
| BIRI DPP | 588.912 | SMALL A |
| CAPUL DPP | 361.643 | SMALL A |
| LIMASAWA DPP | 310.996 | SMALL A |
| MARIPIPI DPP | 485.422 | SMALL A |
| PILAR DPP | 869.264 | SMALL A |
| SAN ANTONIO DPP | 795.447 | SMALL A |
| SAN VICENTE DPP | 128.654 | SMALL A |
| STO. NINO DPP | 135.386 | SMALL A |
| TAGAPUL-AN DPP | 125.04 | SMALL A |
| ZUMARRAGA DPP | 982.897 | SMALL A |
W. Visayas | CALUYA DPP | 889.598 | SMALL A |
| DOONG DPP | 245.753 | SMALL A |
| GIGANTES DPP | 180.264 | SMALL A |
| GUINTARCAN DPP | 160.452 | SMALL A |
E. Mindanao | ABAD SANTOS DPP | 527.96 | SMALL A |
| BALUT DPP | 315.512 | SMALL A |
| DINAGAT DPP | 8009.735 | MEDIUM |
| HIKDOP DPP | 169.264 | SMALL A |
| KALAMANSIG DPP | 8981.809 | MEDIUM |
| LORETO DPP | 1003.892 | SMALL A |
| NINOY AQUINO DPP | 853.959 | SMALL A |
| PB 111 | 1189.352 | MEDIUM |
| TALICUD DPP | 472.438 | SMALL A |
W. Mindanao | BALIMBING DPP | 277.166 | SMALL A |
| CAG.DE TAWI0TAWI DPP | 528.014 | SMALL A |
| LUUK DPP | 444.881 | SMALL A |
| MANUK MANKAW DPP | 140.84 | SMALL A |
| SIASI DPP | 2619.651 | MEDIUM |
| SIBUTU DPP | 355.56 | SMALL A |
| SITANGKAY DPP | 437.634 | SMALL A |
| TANDUBANAK DPP | 279.547 | SMALL A |
| TANDUBAS DPP | 171.511 | SMALL A |
| WEST SIMUNUL DPP | 426.091 | SMALL A |
Masbate Mini-grids | BURIAS DPP | 248.609 | SMALL A |
Sector | Plant | 2011 Gross MWh | Class |
| CHICO DPP | 32.918 | SMALL B |
| GILOTONGAN DPP | 93.948 | SMALL A |
| GINAWAYAN DPP | 30.14 | SMALL B |
| HAPONAN DPP | 22.749 | SMALL B |
| LAHUY DPP | 63.215 | SMALL A |
| NABUCTOT DPP | 21.397 | SMALL B |
| PENA DPP | 38.052 | SMALL B |
| QUINALASAG DPP | 90.663 | SMALL A |
Camiguin Mini-grids | BALATUBAT DPP | 44.328 | SMALL B |
| MINABEL DPP | 14.857 | SMALL B |
Marinduque Islets | MANIWAYA DPP | 35.534 | SMALL B |
| MONGPONG DPP | 40.068 | SMALL B |
| POLO DPP | 24.538 | SMALL B |
E. Visayas Mini-grids | BIASONG DPP | 20.591 | SMALL B |
| CABUNGAAN DPP | 29.708 | SMALL B |
| COSTA RICA DPP | 23.455 | SMALL B |
| ILIJAN DPP | 18.992 | SMALL B |
| LUNANG DPP | 26.048 | SMALL B |
| TAKUT DPP | 75.543 | SMALL A |
W. Visayas Mini-grids | BAGONGBANWA DPP | 22.739 | SMALL B |
| BALICASAG DPP | 37.404 | SMALL B |
| BATASAN DPP | 26.697 | SMALL B |
| BILANGBILANGAN DPP | 7.883 | SMALL B |
| CABILAO DPP | 167.68 | SMALL A |
| CUAMING DPP | 58.84 | SMALL A |
| HAMBONGAN DPP | 12.228 | SMALL B |
| MANTATAO DPP | 21.307 | SMALL B |
| MOCABOC DPP | 12.411 | SMALL B |
| PAMILACAN DPP | 36.628 | SMALL B |
| PANGAPASAN DPP | 14.05 | SMALL B |
| UBAY DPP | 6.454 | SMALL B |
Antique Mini-grids | BATBATAN DPP | 17.94 | SMALL B |
| GUIWANON DPP | 23.335 | SMALL B |
| SIBOLO DPP | 14.677 | SMALL B |
E. Mindanao Mini-grid | PALIMBANG DPP | 155.7026 | SMALL A |
W. Mindanao Mini-grid | SACOL DPP | 102.038 | SMALL A |
PRES Mini-grids | AGUADA | 12.746 | PRES |
| ALTA VISTA | 4.676 | PRES |
| AMUTAG MGE1 | 10.103 | PRES |
| AMUTAG MGE2 | 6.504 | PRES |
| BAANG (MOBO) | 4.706 | PRES |
| BAAO | 3.83 | PRES |
| BACOLOD MGE3 (JAMORAWON) | 7.251 | PRES |
| BALAWING | 1.921 | PRES |
| BALETE (AROROY) | 11.406 | PRES |
| BANTIGUE | 11.793 | PRES |
| BARA MGE1 | 10.747 | PRES |
| BARA MGE2 | 10.352 | PRES |
| BARA MGE3 | 3.993 | PRES |
| BOLO MG1 | 11.853 | PRES |
Sector | Plant | 2011 Gross MWh | Class |
| BOLO MG2 | 11.033 | PRES |
| BOLO MG3 | 10.617 | PRES |
| BONIFACIO MGE1 | 7.26 | PRES |
| BONIFACIO MGE2 | 2.06 | PRES |
| BUGTONG (MANDAON) | 10.788 | PRES |
| BUGTONG (PIO CORPUS) | 10.622 | PRES |
| BURACAN | 6.227 | PRES |
| BURI MGE1 | 5.204 | PRES |
| CABANGCALAN (AROROY) | 10.499 | PRES |
| CABANGCALAN (PLACER) | 6.151 | PRES |
| CABASOAN | 4.691 | PRES |
| CABAYUGAN MGE1 | 7.817 | PRES |
| CABAYUGAN MGE2 | 3.061 | PRES |
| CAGMASOSO MGE1 | 10.456 | PRES |
| CALANAY MGE1 | 10.759 | PRES |
| CALANAY MGE2 | 2.599 | PRES |
| CALASUCHE | 8.859 | PRES |
| CALUMPANG MGE1 (CAWAYAN) | 3.647 | PRES |
| CALUMPANG (MILAGROS) | 10.175 | PRES |
| CALUMPANG (PLACER) | 3.432 | PRES |
| CAMPANA | 2.518 | PRES |
| CANDELARIA MGE1 | 6.076 | PRES |
| CANDELARIA MGE2 | 6.652 | PRES |
| CANTIL MGE1 | 12.767 | PRES |
| CANTIL MGE2 | 4.49 | PRES |
| CANTIL MGE3 | 5.628 | PRES |
| CANTIL MGE4 | 5.016 | PRES |
| CAWAYAN EXT. (BEL-AT) | 7.256 | PRES |
| CAWAYAN EXT. (POB) | 9.848 | PRES |
| CONCEPTION (AROROY) | 5.029 | PRES |
| COSTA RICA (BATUAN) | 9.394 | PRES |
| DANAO MG2 (SAN JACINTO) | 8.836 | PRES |
| DAYHAGAN MGE1 | 5.505 | PRES |
| DAYHAGAN MGE2 | 5.26 | PRES |
| DIOTAY | 11.873 | PRES |
| DOCOL | 4.488 | PRES |
| DON PABLO | 9.109 | PRES |
| GUINLUTHANGAN MGE1 | 11.157 | PRES |
| GUINLUTHANGAN MGE2 | 5.091 | PRES |
| GUMAHANG MGE1 | 10.81 | PRES |
| GUMAHANG MGE2 | 4.956 | PRES |
| GUMAHANG MGE3 | 4.1 | PRES |
| IRAYA | 6.04 | PRES |
| ITOMBATO | 5.681 | PRES |
| JINTOTOLO MGE1 | 10.63 | PRES |
| JINTOTOLO MGE2 | 8.817 | PRES |
| JINTOTOLO MGE3 | 5.03 | PRES |
| LANANG (AROROY) | 6.981 | PRES |
| LANTANGAN MGE1 | 10.528 | PRES |
| LANTANGAN MGE2 | 3.466 | PRES |
Sector | Plant | 2011 Gross MWh | Class |
| LIBTONG | 2.994 | PRES |
| LOCSOAN | 8.845 | PRES |
| LOOC | 10.646 | PRES |
| LUNA MGE1 (PLACER) | 10.155 | PRES |
| LUNA MGE2 (PLACER) | 5.328 | PRES |
| LUNA MGE3 (PLACER) | 7.207 | PRES |
| LUNA (SAN JACINTO) | 6.884 | PRES |
| MABUHAY | 4.759 | PRES |
| MACABUG MGE1 | 7.903 | PRES |
| MADAMBA MGE1 | 11.306 | PRES |
| MADAMBA MGE2 | 3 | PRES |
| MAGBALON | 6.423 | PRES |
| MAGCARAGUIT MGE1 | 5.821 | PRES |
| MAGCARAGUIT MGE2 | 6.337 | PRES |
| MAGCARAGUIT MGE3 | 6.781 | PRES |
| MAGSALANGI | 3.79 | PRES |
| MAHAYAHAY | 1.485 | PRES |
| MARIPOSA | 6.637 | PRES |
| MATABA | 11.963 | PRES |
| MATABAO (BATUAN) | 4.898 | PRES |
| MATAGBAK | 8.065 | PRES |
| MATALANGTALANG | 9.587 | PRES |
| MATAYUM MGE1 | 10.304 | PRES |
| MATAYUM MGE2 | 7.227 | PRES |
| MATAYUM MGE3 | 4.961 | PRES |
| MATONGOG MGE1 | 5.48 | PRES |
| MATONGOG MGE2 | 3.644 | PRES |
| NADAWISAN | 3.659 | PRES |
| NAGARAO | 10.247 | PRES |
| OSMENA | 4.367 | PRES |
| PAMANGPANGON | 8 | PRES |
| PANANAWAN MGE1 | 8.044 | PRES |
| PANANAWAN MGE2 | 4.643 | PRES |
| PANGLE | 5.992 | PRES |
| PEÑA(CAWAYAN) | 3.417 | PRES |
| PINANAAN (AROROY) | 8.399 | PRES |
| PITOGO MGE1 | 3.935 | PRES |
| PITOGO MGE2 | 3.36 | PRES |
| POBLACION MGE1 (JAMORAWON) | 4.724 | PRES |
| POLO DACU MGE1 | 10.48 | PRES |
| RIZAL (BATUAN) | 4.599 | PRES |
| SAN AGUSTIN MGE1 | 10.786 | PRES |
| SAN AGUSTIN MGE2 | 4.573 | PRES |
| SAN ANDRES (BALUD) | 4.115 | PRES |
| SAN ANTONIO MGE1 | 10.728 | PRES |
| SAN ANTONIO MGE2 | 4.669 | PRES |
| SAN ANTONIO (MILAGROS) | 2.856 | PRES |
| SAN CARLOS (MILAGROS) | 5.048 | PRES |
| SAN ISIDRO (AROROY) | 8.53 | PRES |
| SAN JOSE (USON) | 10.651 | PRES |
Sector | Plant | 2011 Gross MWh | Class |
| SAN RAFAEL (CATAINGAN) | 5.94 | PRES |
| SAN ROQUE MGE1 | 3.894 | PRES |
| SAN VICENTE (USON) | 6.27 | PRES |
| SAPATOS | 6.588 | PRES |
| SAWANG MG1 | 7.465 | PRES |
| SAWANG MG2 | 5.12 | PRES |
| SAWMILL MGE1 (MILAGROS) | 1.819 | PRES |
| SAWMILL MGE2 (MILAGROS) | 4.458 | PRES |
| SAWMILL (MOBO) | 6.901 | PRES |
| SOROSIMBAJAN MGE1 | 4.797 | PRES |
| SOROSIMBAJAN MGE2 | 5.976 | PRES |
| STO NINO (MONREAL) | 9.041 | PRES |
| SYNDICATE | 8.426 | PRES |
| TAGBON (MILAGROS) | 8.418 | PRES |
| TALIB MGE1 | 5.751 | PRES |
| TALIB MGE2 | 6.973 | PRES |
| TAN0AWAN | 7.73 | PRES |
| TIGBAO MGE1 (AROROY) | 10.863 | PRES |
| TIGBAO MGE1 (MILAGROS) | 6.218 | PRES |
| TIGBAO MGE2 (AROROY) | 4.452 | PRES |
| TIGBAO MGE2 (MILAGROS) | 10.568 | PRES |
| TIGBAO MGE3 (AROROY) | 5.792 | PRES |
| TIGBAO MGE3 (MILAGROS) | 5.27 | PRES |
| TIGBAO MGE4 (AROROY) | 4.299 | PRES |
| TIGBAO MGE4 (MILAGROS) | 5.094 | PRES |
| TIGBAO MGE5 (MILAGROS) | 3.952 | PRES |
| TINIGBAN MGE1 | 5.358 | PRES |
| TINIGBAN MGE2 | 9.607 | PRES |
| TINIGBAN MGE3 | 10.437 | PRES |
| TINIGBAN MGE4 | 5.429 | PRES |
| TITONG DPP (MG1) | 10.923 | PRES |
| TITONG DPP (MG2) | 7.87 | PRES |
| TONGA | 6.02 | PRES |
| TUBOD MGE4 (JAMORAWON) | 5.376 | PRES |
| TUGBONGAN MGE2 (JAMORAWON) | 5.46 | PRES |
| TUMALAYTAY MGE1 | 7.967 | PRES |
| TUMALAYTAY MGE2 | 7.935 | PRES |
| TUMALAYTAY MGE3 | 3.888 | PRES |
| UBONGAN DACU | 5.976 | PRES |
| YANGCO | 10.41 | PRES |